We studied 3,200 paid contractor invoices in 10 trades and 50 states. Median wait: 33 days. 57% paid late. See your trade, state and how to get paid faster.

Key findings from 3,200 paid contractor invoices
Last updated: November 23, 2026
Every contractor knows the feeling. The job is done. The invoice is out. The money is not in the bank. You still have to pay your crew, your suppliers and your truck note.
So how long do contractors really wait to get paid? Not a guess. Not a survey where people say what they think. We looked at real paid invoices.
This report studies 3,200 paid invoices sent through AR Workflow by contractors in 10 trades and all 50 states, worth $21 million in total. We tracked the date each invoice went out, the date it was due and the date the money came in. Then we broke it down by trade, state, payment terms, invoice size and month.
In this report
Half of all invoices were paid within 33 days. That is the median, the middle number. The average was longer, 44 days, because a small group of very slow invoices pulls it up.
Here is the full spread. Read it like this: the fastest 10 percent of invoices were paid within 12 days. The slowest 10 percent took 91 days or more.
| Group of invoices | Paid within | What it means |
|---|---|---|
| Fastest 10% | 12 days | Customers who pay right away, often by card or ACH |
| Fastest 25% | 19 days | Good customers on net 15 or net 30 terms |
| Middle (median) | 33 days | The typical contractor invoice |
| Slowest 25% | 56 days or more | Almost two months of waiting |
| Slowest 10% | 91 days or more | A full quarter. These need a real collection plan. |
And here is how many invoices landed in each window:
Add it up and you get a clear picture:
Why the slowest 10 percent matter most
Invoices that went past 90 days held $2.2 million, or about 11 percent of every dollar in this study. These are the invoices that hurt cash flow for a whole season. They are also the ones most likely to need a demand letter or a mechanics lien. Lien deadlines often start counting from your last day of work, so a 90 day wait can eat up most of your time to file.
We counted an invoice as late if the money came in after the due date printed on the invoice. Here is what happened to the 3,200 invoices:
| When it was paid | Share of invoices |
|---|---|
| Before the due date | 42% |
| On the due date | 1% |
| After the due date (late) | 57% |
Only 1 in 100 invoices was paid on the exact due date. Customers either pay early or they pay late. Very few treat the due date as a real deadline.
When an invoice was late, how late was it?
The lesson: once an invoice slips past its due date, it does not come in a few days later. It tends to slide for weeks. The first week after the due date is your best chance to catch it. See our payment reminder email templates for what to send.
We studied 10 trades. Eight of them wait about the same amount of time: 25 to 28 days at the median. Two trades wait much longer.
Here is the full table. "Slowest 10%" shows how long the slowest one in ten invoices took.
| Trade | Invoices | Median days | Average days | Slowest 10% | Paid late | Over 90 days | Median invoice |
|---|---|---|---|---|---|---|---|
| Flooring | 119 | 25 | 33 | 65 | 49% | 3% | $3,281 |
| Drywall | 138 | 25 | 35 | 68 | 46% | 6% | $4,215 |
| Plumbing | 300 | 25 | 35 | 67 | 43% | 5% | $1,681 |
| Electrical | 269 | 26 | 33 | 62 | 42% | 4% | $2,213 |
| Concrete | 177 | 26 | 34 | 60 | 49% | 6% | $5,846 |
| Painting | 197 | 27 | 35 | 67 | 47% | 6% | $2,748 |
| HVAC | 370 | 27 | 36 | 70 | 52% | 6% | $2,644 |
| Roofing | 275 | 28 | 37 | 74 | 51% | 6% | $7,384 |
| General Contracting | 434 | 44 | 56 | 111 | 68% | 16% | $8,659 |
| Restoration | 921 | 44 | 58 | 114 | 69% | 17% | $4,184 |
Three things jump out:
Find your trade below. Each card shows the numbers for that trade, where it is faster or slower by state, and what works to get paid sooner.
921 paid invoices studied
What the numbers say. Restoration was the biggest group in our study, with 921 invoices. It is also the slowest. Only 31 percent of restoration invoices were paid within 30 days, and late invoices were a median of 33 days past due, the longest of any trade. Insurance is the reason. One job can have a carrier, an adjuster, a homeowner, a mortgage company and a held back depreciation payment, and every one of them can stall the check.
By state. Where we had at least 15 restoration invoices: Tennessee 36 days, Georgia 37 days, Nevada 38 days, New York 41 days, Florida 43 days, Texas 45.5 days, North Carolina 47 days, Arizona 47.5 days, Ohio 50 days, California 51 days, Colorado 52 days, Pennsylvania 52 days, Illinois 53 days.
How to get paid faster:
Real result: SERVPRO of NE San Diego cut their days to get paid from 105 to 52. ProRestore went from 94 days to 31.
Restoration collections software | How restoration contractors collect from carriers | Recoverable depreciation guide
434 paid invoices studied
What the numbers say. General contractors bill the biggest invoices in our data (median $8,659) and wait 44 days. Their late invoices were a median of 31 days past due. GC payments depend on many people saying yes: the architect approves the pay app, the owner signs off, the lender releases the draw, and retainage is held until the end.
By state. Where we had at least 15 general contracting invoices: Texas 38 days, California 40 days, North Carolina 40 days, New York 40 days, Florida 47 days, Georgia 49.5 days, Illinois 55 days, Pennsylvania 57 days.
How to get paid faster:
Pay application guide: AIA G702 and G703 | AR automation for general contractors | Construction payment terms glossary
275 paid invoices studied
What the numbers say. Roofers bill large invoices (median $7,384) but still get paid in 28 days. About half of roofing invoices were paid late, and late ones were a median of 22 days past due. Insurance claim roofs and supplements are usually the slow ones.
By state. Where we had at least 15 roofing invoices: California 30 days, Texas 30 days, Florida 33 days.
How to get paid faster:
Real result: Horizon Roofing & Solar went from 45 days to get paid to 25.
370 paid invoices studied
What the numbers say. HVAC was the second biggest trade in our data. Invoices are small (median $2,644) and are paid in 27 days, but just over half are paid late. Commercial maintenance accounts on net 30 are often the slow ones.
By state. Where we had at least 15 hvac invoices: Florida 24 days, California 26.5 days, Texas 26.5 days, Pennsylvania 27 days, Arizona 28 days.
How to get paid faster:
300 paid invoices studied
What the numbers say. Plumbers have the smallest invoices (median $1,681) and are among the fastest paid, at 25 days. Six in ten invoices were paid within 30 days. With so many small invoices, the risk is volume: dozens of small unpaid bills add up and nobody has time to chase each one.
By state. Where we had at least 15 plumbing invoices: Texas 22 days, Florida 24.5 days, California 26 days, New York 30 days.
How to get paid faster:
269 paid invoices studied
What the numbers say. Electricians had the lowest late rate of any trade (42 percent) and the shortest average wait (33 days). Late electrical invoices were a median of 17.5 days past due. Texas electrical invoices were the fastest trade and state pair in our whole study, at 20 days.
By state. Where we had at least 15 electrical invoices: Texas 20 days, California 26.5 days, Florida 30.5 days, North Carolina 40 days.
How to get paid faster:
138 paid invoices studied
What the numbers say. Drywall contractors had the highest share of invoices paid within 30 days (62 percent) and a 25 day median. Many drywall jobs are subcontracts, so pay when paid clauses can slow the slow ones.
By state. Where we had at least 15 drywall invoices: California 20.5 days, Texas 28 days.
How to get paid faster:
119 paid invoices studied
What the numbers say. Flooring had the fewest invoices go past 90 days of any trade, under 3 percent. The median wait was 25 days and the average was 33.
How to get paid faster:
177 paid invoices studied
What the numbers say. Concrete contractors bill fairly large invoices (median $5,846) and get paid in 26 days. About half of concrete invoices were paid late, but the late ones were not very late, a median of 20 days.
By state. Where we had at least 15 concrete invoices: Texas 24 days, Florida 25 days, California 28.5 days.
How to get paid faster:
197 paid invoices studied
What the numbers say. Painters wait 27 days at the median. Late painting invoices had the shortest delay of any trade, a median of just 16 days past due. A quick nudge usually works.
By state. Where we had at least 15 painting invoices: Tennessee 26 days, Texas 30 days, California 32.5 days.
How to get paid faster:
This was the biggest surprise in the data. Many contractors think shorter terms get them paid faster. So they write "due on receipt" or "net 15" on every invoice.
It does not work. Look at the median days to pay:
| Terms on the invoice | Invoices | Median days to pay | Average days to pay | Paid late | Median days late | Over 90 days |
|---|---|---|---|---|---|---|
| Due on receipt | 234 | 32 | 45 | 100% | 32 | 12% |
| Net 15 | 406 | 33.5 | 44 | 84% | 24 | 9% |
| Net 30 | 2,036 | 32 | 44 | 53% | 23 | 10% |
| Net 45 | 335 | 33 | 45 | 34% | 24 | 11% |
| Net 60 | 189 | 33 | 46 | 21% | 24.5 | 10% |
Customers paid in about 32 to 34 days no matter what the invoice said. The terms only changed how many invoices were counted as late. With due on receipt, every single invoice was late. With net 60, only 1 in 5 was.
This held true inside each trade too. Restoration invoices took 38 to 54 days on every kind of terms. General contracting took 38 to 51 days. The customer's own habits, not your terms, set the pace.
What this means for you
Writing shorter terms will not bring the money in sooner. What does move the date is what you do around the due date: a friendly reminder a few days before, a firm note the day after, a phone call at one week late, and a clear next step after that. Terms still matter for one reason. They set when interest, late fees and legal steps can start. So pick terms your customers will see as fair, and then follow up every time. Read more in our payment terms guide.
Not much for timing. Small and large invoices took about the same time to pay.
| Invoice size | Invoices | Median days to pay | Paid late |
|---|---|---|---|
| Under $1,000 | 291 | 32 | 56% |
| $1,000 to $5,000 | 1,621 | 32 | 55% |
| $5,000 to $10,000 | 710 | 35 | 58% |
| $10,000 to $25,000 | 470 | 33 | 60% |
| Over $25,000 | 108 | 36 | 56% |
The median invoice in our study was $3,896. The middle half of invoices fell between $1,921 and $7,665. The average was higher, $6,557, because of a few big commercial invoices.
So why care about size? Because of the money at risk. One late $25,000 invoice can hurt more than twenty late $1,000 invoices. When you plan your follow up, put the biggest dollars at the top of the list, but do not let small invoices slide. In our data, small invoices were just as likely to be paid late.
Where you work changes how long you wait. In our data, the gap between the fastest and slowest states was almost three weeks. Here is every state, sorted from fastest to slowest. Click a state to see its mechanics lien deadlines.
| Rank | State | Invoices | Median days | Paid late | Over 90 days |
|---|---|---|---|---|---|
| 1 | Alaska * | 29 | 21 | 38% | 3% |
| 2 | New Hampshire * | 28 | 23.5 | 36% | 18% |
| 3 | Kentucky | 39 | 24 | 54% | 3% |
| 4 | Indiana * | 28 | 24.5 | 61% | 4% |
| 5 | Nebraska * | 22 | 24.5 | 50% | 5% |
| 6 | Rhode Island | 35 | 26 | 51% | 6% |
| 7 | Montana * | 27 | 27 | 52% | 0% |
| 8 | Utah * | 25 | 27 | 52% | 4% |
| 9 | Arkansas | 33 | 28 | 42% | 3% |
| 10 | Iowa * | 29 | 28 | 45% | 3% |
| 11 | North Dakota * | 19 | 28 | 42% | 0% |
| 12 | Ohio | 119 | 28 | 51% | 9% |
| 13 | Tennessee | 114 | 28 | 50% | 8% |
| 14 | Alabama | 40 | 28.5 | 48% | 5% |
| 15 | Maine | 34 | 29 | 47% | 12% |
| 16 | Missouri | 33 | 29 | 48% | 15% |
| 17 | South Dakota | 38 | 29 | 45% | 3% |
| 18 | Idaho | 40 | 29.5 | 52% | 5% |
| 19 | West Virginia * | 26 | 30 | 46% | 12% |
| 20 | Georgia | 117 | 31 | 60% | 13% |
| 21 | Mississippi | 30 | 31 | 47% | 3% |
| 22 | Oklahoma * | 27 | 31 | 56% | 15% |
| 23 | Texas | 337 | 31 | 54% | 9% |
| 24 | Connecticut | 34 | 31.5 | 65% | 15% |
| 25 | Arizona | 102 | 32.5 | 63% | 12% |
| 26 | New Jersey * | 22 | 32.5 | 55% | 14% |
| 27 | Florida | 270 | 33 | 57% | 11% |
| 28 | Kansas * | 27 | 33 | 67% | 11% |
| 29 | Minnesota | 33 | 33 | 58% | 12% |
| 30 | Virginia | 41 | 33 | 63% | 15% |
| 31 | Washington | 30 | 33.5 | 63% | 7% |
| 32 | Wisconsin | 30 | 33.5 | 60% | 7% |
| 33 | Delaware | 41 | 34 | 56% | 10% |
| 34 | New Mexico * | 25 | 34 | 56% | 12% |
| 35 | Nevada | 98 | 34 | 61% | 12% |
| 36 | California | 372 | 35 | 59% | 10% |
| 37 | Colorado | 79 | 35 | 59% | 9% |
| 38 | New York | 147 | 35 | 58% | 10% |
| 39 | Michigan | 31 | 36 | 65% | 19% |
| 40 | North Carolina | 108 | 36 | 55% | 15% |
| 41 | Vermont | 36 | 36 | 58% | 28% |
| 42 | Hawaii * | 26 | 36.5 | 50% | 12% |
| 43 | Pennsylvania | 120 | 37 | 61% | 12% |
| 44 | Oregon * | 28 | 38 | 68% | 11% |
| 45 | South Carolina | 33 | 38 | 61% | 3% |
| 46 | Wyoming * | 24 | 38.5 | 62% | 4% |
| 47 | Massachusetts | 30 | 39 | 63% | 7% |
| 48 | Maryland * | 21 | 39 | 67% | 14% |
| 49 | Louisiana * | 23 | 42 | 61% | 13% |
| 50 | Illinois | 100 | 43.5 | 72% | 14% |
* Fewer than 30 invoices in our data. Treat these numbers as a rough guide, since a few invoices can move them.
Fastest states with at least 30 invoices: Kentucky (24 days), Rhode Island (26), Tennessee, Ohio and Arkansas (28 each).
Slowest states with at least 30 invoices: Illinois (43.5 days, 72 percent late), Massachusetts (39), South Carolina (38), Pennsylvania (37), and Michigan, North Carolina and Vermont (36 each).
The biggest states: Texas (337 invoices) got paid in 31 days, Florida (270) in 33 days, and California (372) and New York (147) in 35 days.
By region:
| Region | Invoices | Median days | Average days | Paid late | Over 90 days |
|---|---|---|---|---|---|
| South | 1,300 | 31 | 44 | 55% | 10% |
| Midwest | 509 | 32 | 44 | 57% | 10% |
| Northeast | 486 | 34 | 47 | 57% | 12% |
| West | 905 | 34 | 44 | 59% | 9% |
Trade and state together tell an even sharper story. Restoration contractors in Tennessee (36 days) and Georgia (37) got paid more than two weeks faster than restoration contractors in Illinois (53), Pennsylvania (52), Colorado (52) and California (51). General contractors in Texas (38 days) beat those in Pennsylvania (57) and Illinois (55) by almost three weeks.
Many states have prompt payment laws that set how fast owners and GCs must pay, and what interest they owe when they do not. If you work in a slow state, those laws and your lien deadlines are your best tools. We also have free statutory lien waiver forms for Texas and 10 other states that require them.
We grouped invoices by the month they were sent:
| Month sent | Median days to pay | Paid late |
|---|---|---|
| January | 31 | 56% |
| February | 32.5 | 55% |
| March | 33 | 58% |
| April | 32 | 56% |
| May | 32 | 59% |
| June | 33 | 56% |
| July | 32 | 55% |
| August | 32.5 | 53% |
| September | 33 | 58% |
| October | 36 | 61% |
| November | 34 | 58% |
| December | 30 | 56% |
Has it gotten better over time? No. Here is each year by the date invoices were paid:
| Year paid | Invoices | Median days | Average days | Paid late | Over 90 days |
|---|---|---|---|---|---|
| 2024 | 1,055 | 33 | 45 | 57% | 10% |
| 2025 | 1,069 | 33 | 44 | 57% | 11% |
| 2026 (to Nov 23) | 950 | 32 | 45 | 56% | 10% |
Slow payment is not a phase or a bad year. It is how the industry works. The only way to change your number is to change your own process.
Waiting to get paid is not free. Every dollar sitting in an unpaid invoice is a dollar you cannot use for payroll, materials or the next job. Here is a simple way to see your number:
The formula
Cash tied up in unpaid invoices = (yearly revenue ÷ 365) × average days to get paid
Here is what that looks like at the 44 day average from our study, compared to a faster 25 days:
| Yearly revenue | Cash tied up at 44 days | Cash tied up at 25 days | Cash freed up | Yearly interest saved at 10% |
|---|---|---|---|---|
| $500,000 | $60,274 | $34,247 | $26,027 | $2,603 |
| $1,000,000 | $120,548 | $68,493 | $52,055 | $5,205 |
| $2,000,000 | $241,096 | $136,986 | $104,110 | $10,411 |
| $5,000,000 | $602,740 | $342,466 | $260,274 | $26,027 |
For a restoration company, the numbers are bigger. Restoration invoices took 58 days on average. A $2 million restoration company at 58 days has about $317,800 waiting at any time. Getting to 30 days would free up about $153,400.
And that does not count the hidden costs:
Want your exact number? Try our free construction DSO calculator.
Pull a list of your paid invoices from the last 12 months with the invoice date, due date and paid date. Then work out three numbers and compare them to our study.
| Your number | How to work it out | Great | Typical | Needs work |
|---|---|---|---|---|
| Median days to pay | Days from invoice date to paid date. Sort them and take the middle one. | 25 days or less | 26 to 40 days | More than 40 days |
| Share paid late | Invoices paid after the due date, divided by all invoices | Under 45% | 45% to 60% | Over 60% |
| Share over 90 days | Invoices that took more than 90 days, divided by all invoices | Under 5% | 5% to 10% | Over 10% |
Compare yourself to your own trade, not just the overall number. A restoration company at 35 days is doing very well, since the restoration median is 44. A plumber at 35 days is behind, since the plumbing median is 25.
| Trade | Top 25% get paid within | Median | Bottom 25% wait longer than |
|---|---|---|---|
| Flooring | 16 days | 25 days | 44 days |
| Drywall | 15 days | 25 days | 42 days |
| Plumbing | 17 days | 25 days | 43 days |
| Electrical | 17 days | 26 days | 41 days |
| Concrete | 16 days | 26 days | 45 days |
| Painting | 17 days | 27 days | 44 days |
| HVAC | 17 days | 27 days | 45 days |
| Roofing | 17 days | 28 days | 48 days |
| General contracting | 26 days | 44 days | 70 days |
| Restoration | 26 days | 44 days | 74 days |
The data shows that customers do not pay faster because of your terms or the size of your invoice. They pay faster when someone follows up. Here is what the fastest paid contractors do, step by step.
| 1 | Invoice the same day the work is done. Every day you wait to send the invoice is a day added to the wait. Send it from the job site if you can. |
| 2 | Make it easy to pay. Put a pay online link on every invoice. Take cards and ACH. The fastest 10 percent of invoices in our study were paid within 12 days, and easy payment is a big part of that. |
| 3 | Send a friendly reminder 3 days before the due date. Remember, 42 percent of customers pay early. A short reminder catches the ones who just forgot. |
| 4 | Follow up the day after the due date. Only 1 in 100 invoices was paid on the due date. Do not wait for "a few more days." Late invoices in our study slid a median of 25 more days. |
| 5 | Call at 7 days late. A phone call gets answers an email cannot: a lost invoice, a question about the work, a check waiting for a signature. |
| 6 | Send a firm notice at 14 days late. Say what you will do next and when. Use our friendly, firm and final email templates. |
| 7 | Send a demand letter at 30 days late. A clear, written demand often shakes the money loose. Here is a free payment demand letter template. |
| 8 | Know your lien deadline from day one. Use the mechanics lien deadline calculator and put the date on your calendar when the job starts. |
| 9 | Watch your aging report every week. Look at your aging report every Monday. Anything over 60 days gets a plan, not a wait. |
| 10 | Automate the follow up. The steps above only work if they happen every time, for every invoice. That is very hard to do by hand when 57 percent of invoices go late. |
Here is that schedule in one view:
| When | What to send | Tone |
|---|---|---|
| Day the work is done | Invoice with a pay online link | Thank you |
| 3 days before due | Reminder email or text | Friendly |
| 1 day after due | Past due notice | Friendly but clear |
| 7 days late | Phone call | Helpful: is anything wrong? |
| 14 days late | Firm notice with next steps | Firm |
| 30 days late | Demand letter | Final |
| Before your lien deadline | Notice of intent to lien or lien filing | Legal |
Cite this report
AR Workflow. "Contractor Payment Report 2026: How Fast Trades Get Paid." November 2026. https://arworkflow.com/blog/contractor-payment-report-2026
Journalists, bloggers, trade groups and teachers are welcome to use these numbers and charts. Please credit AR Workflow and link back to this page.
In our study of 3,200 paid invoices, the median contractor invoice was paid 33 days after it was sent. The average was 44 days. One in four invoices took 56 days or more, and one in ten took more than 90 days.
57 percent were paid after the due date. About 42 percent were paid early and only 1 percent were paid on the exact due date. Late invoices were a median of 25 days past due.
Restoration and general contracting. Both had a median of 44 days to get paid and an average of 56 to 58 days. About 7 in 10 of their invoices were paid late, and about 1 in 6 took more than 90 days.
Plumbing, drywall and flooring tied at a median of 25 days. Electrical had the lowest late rate of any trade at 42 percent, and flooring had the fewest invoices go past 90 days at under 3 percent.
No. Invoices were paid in a median of 32 to 34 days whether the terms said due on receipt, net 15, net 30, net 45 or net 60. Shorter terms only made more invoices count as late.
A little. Invoices under $5,000 were paid in a median of 32 days. Invoices over $25,000 took 36 days. The bigger risk with large invoices is the dollars at stake, not the days.
Among states with at least 30 invoices in our data, Kentucky (24 days), Rhode Island (26), and Tennessee, Ohio and Arkansas (28) were fastest. Illinois was slowest at 43.5 days, with 72 percent of invoices paid late.
Invoices sent in October were the slowest, with a median of 36 days and 61 percent paid late. December invoices were the fastest at 30 days. Year end budgets and holiday cash flow both seem to play a part.
At the 44 day average in our study, a contractor billing $1 million a year has about $120,000 waiting in unpaid invoices at any time. Getting to 25 days would free up about $52,000.
Yes. Please credit "AR Workflow Contractor Payment Report 2026" and link to https://arworkflow.com/blog/contractor-payment-report-2026.
Tools and related guides
Want to beat the 33 day average?
Bring one overdue invoice to a demo. We will show you how AR Workflow follows up on it for you, automatically, on the schedule in this report.
Data from AR Workflow users, anonymized and aggregated. Results describe paid invoices only and may not match every business. This report is for general information and is not legal or financial advice.
Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.