Missouri mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Missouri mechanics lien deadlines in plain English, with the law behind each rule.

Missouri mechanics lien deadlines and how to file

Quick answer: Missouri mechanics lien deadlines

6 months after the debt accrues (last furnishing); equipment lessors 60 days after removal (§ 429.080).

Last updated: November 23, 2026

This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Missouri statute (RSMo §§ 429.010–.360) in November 2026. Read the current law or ask a Missouri construction attorney before you file.

Missouri lien law at a glance

"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.

RuleWhat Missouri requiresLaw
Preliminary notice: prime contractorRequired for every original contractor (residential AND commercial). Written NOTICE TO OWNER in 10-point bold type, delivered at contract signing, when materials are delivered, when work starts, or with the first invoice, and in all cases before receiving any payment. It is a condition precedent to the prime's lien. Exempt only for new residences where the buyer got lien coverage from a Missouri-registered title insurer (429.012.4).RSMo 429.012.1, .2, .4
Preliminary notice: subcontractorNo preliminary notice for subs. They need the 10-day pre-filing notice (429.100). On owner-occupied residential repair, remodel or additions (4 units or fewer), they need the owner's signed CONSENT OF OWNER in the prime contract (429.013).RSMo 429.100; 429.013
Preliminary notice: supplierNo general supplier preliminary notice. Equipment lessors have a lien only if three conditions are all met: commercial property, claim over $5,000, and written notice to the owner within 15 business days after use begins, naming the renting entity and the equipment. Otherwise there is no lien. A contractor that merely USES rented equipment is not subject to this rule (429.010.2, last paragraph).RSMo 429.010.2 (eff. 8/28/2013, SB 357)
Notice of intent to lienEvery claimant other than the original contractor (subs, sub-subs, suppliers, laborers, equipment lessors) must serve the owner or the owner's agent at least 10 days before filing the lien. The notice states the claim, the amount, and from whom it is due. It must be served by an officer authorized to serve civil process or by any competent adult witness, and service is proved by the officer's return or the server's affidavit. The notice does NOT extend the lien-filing period (Continental Casualty Co. v. Allsop Lumber Co., 336 F.2d 445 (8th Cir. 1964)), so it must go out by (lien deadline minus 10 days).RSMo 429.100
Lien filing deadline: prime contractorFile a verified lien account with the circuit clerk of the county where the property is located within 6 months after the indebtedness accrued. Courts read accrual as the date of last labor or materials furnished under the contract.RSMo 429.080; Manning Constr. Co. v. MCI Partners, LLC, WD75284 (Mo. App. W.D. 2013)
Lien filing deadline: subcontractor and supplierSame 6 months after accrual (last furnishing) for subs, suppliers and laborers. Equipment lessors: 60 days after the last rental equipment is removed from the property.RSMo 429.080
Residential projectsSame 6 months. Two residential overlays apply. (1) Owner-occupied repair, remodel or addition, 4 units or fewer: a non-prime lien is void unless the owner's signed Consent of Owner is attached to the lien (429.013). (2) Residential property that is NOT owner-occupied with 4 units or fewer, when sold: if the owner records a notice of intended sale at least 45 days before closing, a claimant must record a notice of rights at least 5 days before closing or forfeit the lien (429.016; wave 1 verified, not re-fetched this wave).RSMo 429.013; 429.016
Notice of completion: does it shorten the deadline?Missouri has no notice of completion or commencement. Only the 429.016 notice-of-intended-sale procedure cuts off liens on non-owner-occupied residential sales.RSMo ch. 429; 429.016
Serving the owner after you fileNo post-filing service on the owner. The owner-facing service step is the 10-day pre-filing notice (429.100).RSMo 429.080, 429.100
Deadline to sue (enforce the lien)Suit must be commenced within 6 months after the lien is FILED (not after last work). Otherwise the lien ceases to exist.RSMo 429.170

Missouri mechanics lien rules for homes and homeowners

Roofing, restoration and remodeling work on homes often has extra rules. In Missouri:

429.013 applies only to repair, remodeling or additions to owner-occupied residential property of 4 units or fewer. It does not apply to construction of the original unit or to original development. Owner-occupied includes an owner who intends to occupy the property within a reasonable time after completion. A non-original contractor has NO lien unless the owner agreed in a written contract to be liable. That consent must be in 10-point bold type, signed separately from the 429.012 notice, and a copy must be attached to the recorded lien or the lien is invalid. One owner's signature binds all owners. The prime must keep copies and give them to subs and suppliers on request. Without consent, full payment to the prime is a complete defense, and partial payment is a defense to the extent paid. 429.016 covers sale of non-owner-occupied residential property.

Same 6 months. Two residential overlays apply. (1) Owner-occupied repair, remodel or addition, 4 units or fewer: a non-prime lien is void unless the owner's signed Consent of Owner is attached to the lien (429.013). (2) Residential property that is NOT owner-occupied with 4 units or fewer, when sold: if the owner records a notice of intended sale at least 45 days before closing, a claimant must record a notice of rights at least 5 days before closing or forfeit the lien (429.016; wave 1 verified, not re-fetched this wave).

How to file a mechanics lien in Missouri, step by step

  1. Check the notice rules before you start. Look at the preliminary notice rows above for your role. Send any required notice early, by a method you can prove (like certified mail).
  2. Keep a job file from day one. Save the contract, change orders, invoices, delivery tickets, photos, and your first and last day of work. Most Missouri deadlines count from one of those dates.
  3. Follow up on every unpaid invoice. Send friendly reminders, then firm ones. Most customers pay before it ever gets to a lien.
  4. Send a warning before you file. Every claimant other than the original contractor (subs, sub-subs, suppliers, laborers, equipment lessors) must serve the owner or the owner's agent at least 10 days before filing the lien. The notice states the claim, the amount, and from whom it is due. It must be served by an officer authorized to serve civil process or by any competent adult witness, and service is proved by the officer's retu
  5. File the lien on time and serve the owner. Prime: 6 months after your last day of work or materials. Subs and suppliers: 6 months after your last day of work or materials. Then serve the owner as the table explains.
  6. Enforce it or release it. Sue within 6 months after the lien is filed. If you get paid, release the lien right away.

Watch: how to send a notice of intent to lien (3 minutes)

Before you file a lien in Missouri: try to get paid first

A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:

Read the Missouri lien law

Frequently asked questions

What is the deadline to file a mechanics lien in Missouri?

Prime contractors: File a verified lien account with the circuit clerk of the county where the property is located within 6 months after the indebtedness accrued. Courts read accrual as the date of last labor or materials furnished under the contract. Subcontractors and suppliers: Same 6 months after accrual (last furnishing) for subs, suppliers and laborers. Equipment lessors: 60 days after the last rental equipment is removed from the property.

How do I file a mechanics lien in Missouri?

Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 6 months after your last day of work or materials. Subcontractors and suppliers: 6 months after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.

Do subcontractors need to send a preliminary notice in Missouri?

No preliminary notice for subs. They need the 10-day pre-filing notice (429.100). On owner-occupied residential repair, remodel or additions (4 units or fewer), they need the owner's signed CONSENT OF OWNER in the prime contract (429.013).

Do I need to send a notice of intent to lien in Missouri?

Every claimant other than the original contractor (subs, sub-subs, suppliers, laborers, equipment lessors) must serve the owner or the owner's agent at least 10 days before filing the lien. The notice states the claim, the amount, and from whom it is due. It must be served by an officer authorized to serve civil process or by any competent adult witness, and service is proved by the officer's return or the server's affidavit. The notice does NOT extend the lien-filing period (Continental Casualty Co. v. Allsop Lumber Co., 336 F.2d 445 (8th Cir. 1964)), so it must go out by (lien deadline minus 10 days).

Are there special lien rules for homes in Missouri?

429.013 applies only to repair, remodeling or additions to owner-occupied residential property of 4 units or fewer. It does not apply to construction of the original unit or to original development. Owner-occupied includes an owner who intends to occupy the property within a reasonable time after completion. A non-original contractor has NO lien unless the owner agreed in a written contract to be liable. That consent must be in 10-point bold type, signed separately from the 429.012 notice, and a copy must be attached to the recorded lien or the lien is invalid. One owner's signature binds all owners. The prime must keep copies and give them to subs and suppliers on request. Without consent, full payment to the prime is a complete defense, and partial payment is a defense to the extent paid. 429.016 covers sale of non-owner-occupied residential property.

How long do I have to enforce a mechanics lien in Missouri?

Suit must be commenced within 6 months after the lien is FILED (not after last work). Otherwise the lien ceases to exist.

Mechanics lien deadlines in nearby states

See mechanics lien deadlines for all 50 states

Get paid before it gets to a lien.

AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.

Book a demo

Sam Frenzley
About the authorSam Frenzley

Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.

You did the work. Let AI chase the money.

AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.

  • Keep QuickBooks
  • Start with one invoice
  • Stay in control