Arizona mechanics lien: file within 120 days after completion. Notice rules, home rules and how to file, with the law, in plain English.
Arizona mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Arizona mechanics lien deadlines in plain English, with the law behind each rule.

Quick answer: Arizona mechanics lien deadlines
Earlier of 120 days after completion or 60 days after a recorded notice of completion that the owner mailed to claimants within 15 days of recording (§ 33-993). Completion = earlier of 30 days after final inspection/acceptance or 60 consecutive days with no work; with no permit, last furnishing.
Last updated: November 23, 2026
This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Arizona statute (A.R.S. §§ 33-981 to -1008) in November 2026. Read the current law or ask a Arizona construction attorney before you file.
"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.
| Rule | What Arizona requires | Law |
|---|---|---|
| Preliminary notice: prime contractor | Required. Every claimant except a person performing actual labor for wages must serve the preliminary 20-day notice, including the original contractor. | A.R.S. 33-992.01(B) |
| Preliminary notice: subcontractor | Required within 20 days after first furnishing at the jobsite. A late notice covers only work furnished within 20 days before service and after. | A.R.S. 33-992.01(C),(E) |
| Preliminary notice: supplier | Required. Same rule as for subs. | A.R.S. 33-992.01(B),(C) |
| Notice of intent to lien | None. | A.R.S. 33-993 |
| Lien filing deadline: prime contractor | 120 days after completion of the building, structure or improvement. If a notice of completion is recorded, 60 days after its recording, but only for claimants who were mailed a copy within 15 days of recording. | A.R.S. 33-993(A),(I) |
| Lien filing deadline: subcontractor and supplier | Same as prime. The trigger is completion of the whole improvement, not the sub's last work. | A.R.S. 33-993(A),(C),(D) |
| Residential projects | On a project of several residential buildings, each building is a separate work, and its period runs from completion of that building. On an owner-occupied dwelling, only a claimant with a written contract signed directly with the owner-occupant may lien (33-1002). | A.R.S. 33-993(B); 33-1002(B) |
| Notice of completion: does it shorten the deadline? | A recorded notice of completion shortens the period to 60 days after recording, but only for a claimant to whom the owner mailed a copy (certified or registered) within 15 days of recording. Mailing goes to the original contractor and everyone who sent the owner a 20-day notice. An unmailed claimant keeps 120 days from completion. | A.R.S. 33-993(A),(I) |
| Serving the owner after you file | Within a reasonable time after recording, serve a copy of the recorded lien on the owner if the owner can be found in the county. | A.R.S. 33-993(A) |
| Deadline to sue (enforce the lien) | File the foreclosure action and record a notice of pendency (A.R.S. 12-1191) within 6 months after the lien is recorded. 12-1191(A) also requires the notice of pendency within 5 days of filing the action. An answer or cross-claim asserting the lien in another claimant's suit counts. | A.R.S. 33-998(A); 12-1191(A) |
Roofing, restoration and remodeling work on homes often has extra rules. In Arizona:
No lien may be recorded against the dwelling of a person who was an owner-occupant before work began, except by a person who executed a written contract directly with the owner-occupant. Subs, sub-subs and suppliers have no lien on owner-occupied dwellings. An oral contract also defeats the prime's lien. A waiver of 33-1002 in the owner's agreement is void.
On a project of several residential buildings, each building is a separate work, and its period runs from completion of that building. On an owner-occupied dwelling, only a claimant with a written contract signed directly with the owner-occupant may lien (33-1002).
A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:
Prime contractors: 120 days after completion of the building, structure or improvement. If a notice of completion is recorded, 60 days after its recording, but only for claimants who were mailed a copy within 15 days of recording. Subcontractors and suppliers: Same as prime. The trigger is completion of the whole improvement, not the sub's last work.
Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 120 days after completion of the project. Subcontractors and suppliers: 120 days after completion of the project. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.
Required within 20 days after first furnishing at the jobsite. A late notice covers only work furnished within 20 days before service and after.
None.
No lien may be recorded against the dwelling of a person who was an owner-occupant before work began, except by a person who executed a written contract directly with the owner-occupant. Subs, sub-subs and suppliers have no lien on owner-occupied dwellings. An oral contract also defeats the prime's lien. A waiver of 33-1002 in the owner's agreement is void.
File the foreclosure action and record a notice of pendency (A.R.S. 12-1191) within 6 months after the lien is recorded. 12-1191(A) also requires the notice of pendency within 5 days of filing the action. An answer or cross-claim asserting the lien in another claimant's suit counts.
See mechanics lien deadlines for all 50 states
Get paid before it gets to a lien.
AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.
Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.
AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.