South Carolina mechanics lien: file within 90 days after last work. Notice rules, home rules and how to file, with the law, in plain English.
South Carolina mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the South Carolina mechanics lien deadlines in plain English, with the law behind each rule.

Quick answer: South Carolina mechanics lien deadlines
Sworn statement filed and served within 90 days after last furnishing (§ 29-5-90).
Last updated: November 23, 2026
This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the South Carolina statute (S.C. Code §§ 29-5-10 to -440) in November 2026. Read the current law or ask a South Carolina construction attorney before you file.
"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.
| Rule | What South Carolina requires | Law |
|---|---|---|
| Preliminary notice: prime contractor | None. Prime may (optionally) file a Notice of Project Commencement within 15 days of commencement of work. | S.C. Code § 29-5-23 |
| Preliminary notice: subcontractor | First-tier sub (employed by contractor, not owner): must give written notice to owner of the furnishing for the lien to attach against the owner (§ 29-5-40); no fixed deadline (Ferguson Fire 2014: any time), but lien is capped at owner's unpaid balance at notice. Sub-subs and suppliers to subs: if a NOPC was filed, send notice of furnishing to the CONTRACTOR by certified/registered mail (§ 29-5-20(B)) to avoid being capped at what the contractor owes the sub. | S.C. Code §§ 29-5-20(B), 29-5-23, 29-5-40 |
| Preliminary notice: supplier | Same as sub: § 29-5-40 owner notice; § 29-5-20(B) notice of furnishing to contractor when NOPC filed. No fixed deadline; send at first furnishing. | S.C. Code §§ 29-5-20(B), 29-5-40 |
| Notice of intent to lien | None. | S.C. Code ch. 29-5 |
| Lien filing deadline: prime contractor | Serve on owner (or person in possession) and file certificate of lien with register of deeds/clerk within 90 days after ceasing to furnish labor or materials. | S.C. Code § 29-5-90 |
| Lien filing deadline: subcontractor and supplier | Same 90 days from that claimant's own last furnishing. | S.C. Code § 29-5-90 |
| Residential projects | Same 90 days; no residential exception except real-estate licensees under § 29-5-21(B)(3). | S.C. Code § 29-5-90 |
| Notice of completion: does it shorten the deadline? | No completion notice. NOPC does not shorten any deadline; it only activates the § 29-5-20(B) notice-of-furnishing regime and § 29-5-60(B). | S.C. Code § 29-5-23 |
| Serving the owner after you file | Serve owner (or person in possession if owner can't be found) within the same 90 days as filing. | S.C. Code § 29-5-90 |
| Deadline to sue (enforce the lien) | Commence suit AND record notice of pendency (lis pendens) within 6 months after ceasing to furnish; otherwise lien dissolved. Release by court order or attorney affidavit after 6 months with no suit/lis pendens (§ 29-5-120(B)). | S.C. Code § 29-5-120 |
Roofing, restoration and remodeling work on homes often has extra rules. In South Carolina:
No separate lien track. Prevailing-party attorney fees + costs capped at lien amount (§ 29-5-10(a)). Prompt-pay interest § 29-6-60 does not apply to residential improvements of 16 or fewer units (Clement Rivers). Residential defect claims have 90-day pre-suit notice (§ 40-59-840) relevant to counterclaims.
Same 90 days; no residential exception except real-estate licensees under § 29-5-21(B)(3).
Example: A subcontractor's last day of work on a South Carolina job was Monday, March 2, 2026. With a 90-day deadline from the last day of work, count 90 days forward: the lien must be filed by Sunday, May 31, 2026. Don't wait for the last day. Set a reminder a few weeks earlier, and check whether a notice of completion or other rule in the table above changes your clock.
A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:
Prime contractors: Serve on owner (or person in possession) and file certificate of lien with register of deeds/clerk within 90 days after ceasing to furnish labor or materials. Subcontractors and suppliers: Same 90 days from that claimant's own last furnishing.
Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 90 days after your last day of work or materials. Subcontractors and suppliers: 90 days after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.
First-tier sub (employed by contractor, not owner): must give written notice to owner of the furnishing for the lien to attach against the owner (§ 29-5-40); no fixed deadline (Ferguson Fire 2014: any time), but lien is capped at owner's unpaid balance at notice. Sub-subs and suppliers to subs: if a NOPC was filed, send notice of furnishing to the CONTRACTOR by certified/registered mail (§ 29-5-20(B)) to avoid being capped at what the contractor owes the sub.
None.
No separate lien track. Prevailing-party attorney fees + costs capped at lien amount (§ 29-5-10(a)). Prompt-pay interest § 29-6-60 does not apply to residential improvements of 16 or fewer units (Clement Rivers). Residential defect claims have 90-day pre-suit notice (§ 40-59-840) relevant to counterclaims.
Commence suit AND record notice of pendency (lis pendens) within 6 months after ceasing to furnish; otherwise lien dissolved. Release by court order or attorney affidavit after 6 months with no suit/lis pendens (§ 29-5-120(B)).
See mechanics lien deadlines for all 50 states
Get paid before it gets to a lien.
AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.
Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.
AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.