Maryland mechanics lien: file within 180 days after last work. Notice rules, home rules and how to file, with the law, in plain English.

Sam Frenzley
Founder, AR Workflow
9 min read

Maryland mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Maryland mechanics lien deadlines in plain English, with the law behind each rule.

Maryland mechanics lien deadlines and how to file

Quick answer: Maryland mechanics lien deadlines

Court petition to establish the lien within 180 days after last furnishing (§§ 9-105, -106).

Last updated: November 23, 2026

This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Maryland statute (Md. Code, Real Prop. §§ 9-101 to -114) in November 2026. Read the current law or ask a Maryland construction attorney before you file.

Maryland lien law at a glance

"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.

RuleWhat Maryland requiresLaw
Preliminary notice: prime contractorNone. The 9-104 notice applies only to subcontractors. A prime (in privity with the owner) goes straight to the 180-day petition.Md. Code, Real Prop. 9-104(a)
Preliminary notice: subcontractorRequired, post-work. Give the owner written notice of intention to claim a lien, substantially in the 9-104(b) form and sworn under penalty of perjury, within 120 days after doing the work or furnishing the materials. Practitioners measure the 120 days from the sub's last work (Fox Rothschild). Delivery: registered or certified mail, return receipt requested, or personal delivery by the claimant or its agent. Posting on the building door or front, with a competent witness, is allowed if the owner cannot be served. Notice to any one co-owner suffices.RP 9-104(a)(1),(b),(c),(d),(e)
Preliminary notice: supplierSame 120-day notice. Suppliers to a contractor or sub are 'subcontractors' under the subtitle.RP 9-101 (definitions, not re-fetched); 9-104
Notice of intent to lienThe 120-day 9-104 notice is the notice of intent (subs only).RP 9-104
Lien filing deadline: prime contractorFile a PETITION TO ESTABLISH the lien in the circuit court for the county where the land lies within 180 days after the work has been finished or the materials furnished. This is a lawsuit, not a recording. It is docketed as an action in equity, with an affidavit and the material papers.RP 9-105(a),(b)
Lien filing deadline: subcontractor and supplierSame 180-day petition. A sub's petition must also plead facts showing the 9-104 notice was properly mailed or served.RP 9-105(a)(1)
Residential projectsSame 120/180 days. Two residential limits apply: (a) the 15% rule for repair or improvement work, and (b) the new single-family owner-residence payment defense (see residential_rules).RP 9-102(a); 9-104(a)(2),(f)(3)
Notice of completion: does it shorten the deadline?None. Maryland has no notice of completion or commencement. Filing the 9-105 petition itself gives purchasers notice (9-102(e)).RP 9-102(e)
Serving the owner after you fileNo separate claimant service deadline. After the petition is filed, the court issues a show-cause order, which is served on the owner with the petition. The owner has 15 days after service to respond. Sub's 120-day notice: certified or registered mail RRR, personal delivery, or witnessed posting.RP 9-106 (wave 2 statute read); 9-104(c),(e)
Deadline to sue (enforce the lien)Within 1 year from the day the petition to establish was FIRST FILED, file a petition to enforce in the same lien proceeding, or execute on the release bond. A timely filing preserves the lien until the case concludes.RP 9-109

Maryland mechanics lien rules for homes and homeowners

Roofing, restoration and remodeling work on homes often has extra rules. In Maryland:

(1) 15% RULE: a repaired, rebuilt or improved building is lienable only if the work is 'to the extent of 15 percent of its value'. New construction is exempt from the test. This can bar liens on many roofing or restoration repair jobs, for primes AND subs. (2) NEW-HOME RULE: for a single-family dwelling being erected on the owner's land for the owner's own residence, a sub has a lien only if it gives the 120-day notice AND the owner had not paid the contractor in full before receiving it. The lien is capped at what the owner still owed when notified. This applies to new construction only, not to repair or remodel of an existing home. (3) BFP: no lien if legal title passed to a bona fide purchaser for value before the lien is established (York Roofing v. Adcock, 333 Md. 158 (1993)). (4) TENANT work of 25% of value: the lien reaches only the tenant's interest (9-103(c)(2)). (5) No prospective waiver in a contractor-sub contract (9-113, per ALFA).

Same 120/180 days. Two residential limits apply: (a) the 15% rule for repair or improvement work, and (b) the new single-family owner-residence payment defense (see residential_rules).

How to file a mechanics lien in Maryland, step by step

  1. Check the notice rules before you start. Look at the preliminary notice rows above for your role. Send any required notice early, by a method you can prove (like certified mail).
  2. Keep a job file from day one. Save the contract, change orders, invoices, delivery tickets, photos, and your first and last day of work. Most Maryland deadlines count from one of those dates.
  3. Follow up on every unpaid invoice. Send friendly reminders, then firm ones. Most customers pay before it ever gets to a lien.
  4. Send a warning before you file. The 120-day 9-104 notice is the notice of intent (subs only).
  5. File the lien on time and serve the owner. Prime: 180 days after your last day of work or materials. Subs and suppliers: 180 days after your last day of work or materials. Then serve the owner as the table explains.
  6. Enforce it or release it. Sue within 1 year after the lien is filed. If you get paid, release the lien right away.

Example: A subcontractor's last day of work on a Maryland job was Monday, March 2, 2026. With a 180-day deadline from the last day of work, count 180 days forward: the lien must be filed by Saturday, August 29, 2026. Don't wait for the last day. Set a reminder a few weeks earlier, and check whether a notice of completion or other rule in the table above changes your clock.

Watch: how to send a notice of intent to lien (3 minutes)

Before you file a lien in Maryland: try to get paid first

A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:

Read the Maryland lien law

Frequently asked questions

What is the deadline to file a mechanics lien in Maryland?

Prime contractors: File a PETITION TO ESTABLISH the lien in the circuit court for the county where the land lies within 180 days after the work has been finished or the materials furnished. This is a lawsuit, not a recording. It is docketed as an action in equity, with an affidavit and the material papers. Subcontractors and suppliers: Same 180-day petition. A sub's petition must also plead facts showing the 9-104 notice was properly mailed or served.

How do I file a mechanics lien in Maryland?

Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 180 days after your last day of work or materials. Subcontractors and suppliers: 180 days after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.

Do subcontractors need to send a preliminary notice in Maryland?

Required, post-work. Give the owner written notice of intention to claim a lien, substantially in the 9-104(b) form and sworn under penalty of perjury, within 120 days after doing the work or furnishing the materials. Practitioners measure the 120 days from the sub's last work (Fox Rothschild). Delivery: registered or certified mail, return receipt requested, or personal delivery by the claimant or its agent. Posting on the building door or front, with a competent witness, is allowed if the owner cannot be served. Notice to any one co-owner suffices.

Do I need to send a notice of intent to lien in Maryland?

The 120-day 9-104 notice is the notice of intent (subs only).

Are there special lien rules for homes in Maryland?

(1) 15% RULE: a repaired, rebuilt or improved building is lienable only if the work is 'to the extent of 15 percent of its value'. New construction is exempt from the test. This can bar liens on many roofing or restoration repair jobs, for primes AND subs. (2) NEW-HOME RULE: for a single-family dwelling being erected on the owner's land for the owner's own residence, a sub has a lien only if it gives the 120-day notice AND the owner had not paid the contractor in full before receiving it. The lien is capped at what the owner still owed when notified. This applies to new construction only, not to repair or remodel of an existing home. (3) BFP: no lien if legal title passed to a bona fide purchaser for value before the lien is established (York Roofing v. Adcock, 333 Md. 158 (1993)). (4) TENANT work of 25% of value: the lien reaches only the tenant's interest (9-103(c)(2)). (5) No prospective waiver in a contractor-sub contract (9-113, per ALFA).

How long do I have to enforce a mechanics lien in Maryland?

Within 1 year from the day the petition to establish was FIRST FILED, file a petition to enforce in the same lien proceeding, or execute on the release bond. A timely filing preserves the lien until the case concludes.

Mechanics lien deadlines in nearby states

See mechanics lien deadlines for all 50 states

Get paid before it gets to a lien.

AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.

Book a demo

Sam Frenzley
About the authorSam Frenzley

Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.

You did the work. Let AI chase the money.

AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.

  • Keep QuickBooks
  • Start with one invoice
  • Stay in control