AR Workflow Blog/Collections tips

Alaska Mechanics Lien: Deadlines and How to File

Alaska mechanics lien: file within 120 days after completion. Notice rules, home rules and how to file, with the law, in plain English.

Sam Frenzley
Founder, AR Workflow
7 min read

Alaska mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Alaska mechanics lien deadlines in plain English, with the law behind each rule.

Alaska mechanics lien deadlines and how to file

Quick answer: Alaska mechanics lien deadlines

120 days after the claimant's own completion or cessation of work. If the owner records a notice of completion, record the lien (or a notice of right to lien) within 15 days; a timely recorded notice of right to lien preserves the 120-day period (§ 34.35.068).

Last updated: November 23, 2026

This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Alaska statute (AS 34.35.050–.120; homestead § 09.38.065) in November 2026. Read the current law or ask a Alaska construction attorney before you file.

Alaska lien law at a glance

"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.

RuleWhat Alaska requiresLaw
Preliminary notice: prime contractorOptional notice of right to lien (AS 34.35.064), recordable any time after contracting. Strongly recommended: it determines whether an owner's notice of completion cuts the lien window to 15 days.AS 34.35.064, .068(b)
Preliminary notice: subcontractorSame as prime: optional.AS 34.35.064
Preliminary notice: supplierSame: optional.AS 34.35.064
Notice of intent to lienNone.AS 34.35.050-.120
Lien filing deadline: prime contractorIf no notice of completion is recorded: record claim of lien not later than 120 days after the claimant completes its construction contract OR ceases to furnish labor, material, services or equipment. NOT 90 days: HB 253 (SLA 2010 ch. 51) changed 90 to 120 for work furnished on/after its effective date.AS 34.35.068(a); SLA 2010 ch. 51 sec. 1
Lien filing deadline: subcontractor and supplierSame 120 days (claimant's own completion/cessation).AS 34.35.068(a)
Residential projectsSame; no residential-specific deadline.AS 34.35.068
Notice of completion: does it shorten the deadline?Owner may record a notice of completion only after project completion (premature NOC ineffective). At least 5 days before recording, owner must notify claimants who, more than 10 days before recording, gave a notice of right to lien or stop-lending notice. After NOC recording, a 15-day deadline (to record a claim of lien OR a notice of right to lien) applies to: (1) claimants who received that 5-day advance notice, and (2) claimants who never gave a notice of right to lien. Claimants who gave a notice of right to lien but did not receive advance notice keep the 120-day period. Precision vs v3: a claimant who RECEIVED advance notice also gets only 15 days even if it previously gave a notice of right to lien; and recording a notice of right to lien within the 15 days preserves 120 days for those without one (per 068(b) wording 'claim of lien or a notice of right to lien').AS 34.35.068(b),(c); 34.35.071(a),(d),(e)
Serving the owner after you fileNo statutory requirement to serve or mail the recorded claim of lien on the owner.AS 34.35.070
Deadline to sue (enforce the lien)Lien does not bind property more than 6 months after recording unless (1) an enforcement action is commenced within that time, or (2) an extension notice (showing original recording date, book/page or serial number, balance owing) is recorded in the same office within the original 6 months, giving 6 months from recording of the extension notice. Statute does not state a limit on number of extensions; treat as one.AS 34.35.080(a)

Alaska mechanics lien rules for homes and homeowners

Roofing, restoration and remodeling work on homes often has extra rules. In Alaska:

No residential-specific lien notice, deadline or homeowner disclosure found in AS 34.35. Homestead exemption does not bar improvement liens (AS 09.38.065). Contractors must be registered when they agreed to do the work to bring an action for compensation (AS 08.18.151); that likely bars lien foreclosure by unregistered contractors (statute does not mention liens).

Same; no residential-specific deadline.

How to file a mechanics lien in Alaska, step by step

  1. Check the notice rules before you start. Look at the preliminary notice rows above for your role. Send any required notice early, by a method you can prove (like certified mail).
  2. Keep a job file from day one. Save the contract, change orders, invoices, delivery tickets, photos, and your first and last day of work. Most Alaska deadlines count from one of those dates.
  3. Follow up on every unpaid invoice. Send friendly reminders, then firm ones. Most customers pay before it ever gets to a lien.
  4. Send a warning before you file. None.
  5. File the lien on time and serve the owner. Prime: 120 days after completion of the project. Subs and suppliers: 120 days after completion of the project. Then serve the owner as the table explains.
  6. Enforce it or release it. Sue within 6 months after the lien is filed. If you get paid, release the lien right away.

Watch: how to send a notice of intent to lien (3 minutes)

Before you file a lien in Alaska: try to get paid first

A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:

Read the Alaska lien law

Frequently asked questions

What is the deadline to file a mechanics lien in Alaska?

Prime contractors: If no notice of completion is recorded: record claim of lien not later than 120 days after the claimant completes its construction contract OR ceases to furnish labor, material, services or equipment. NOT 90 days: HB 253 (SLA 2010 ch. 51) changed 90 to 120 for work furnished on/after its effective date. Subcontractors and suppliers: Same 120 days (claimant's own completion/cessation).

How do I file a mechanics lien in Alaska?

Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 120 days after completion of the project. Subcontractors and suppliers: 120 days after completion of the project. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.

Do subcontractors need to send a preliminary notice in Alaska?

Same as prime: optional.

Do I need to send a notice of intent to lien in Alaska?

None.

Are there special lien rules for homes in Alaska?

No residential-specific lien notice, deadline or homeowner disclosure found in AS 34.35. Homestead exemption does not bar improvement liens (AS 09.38.065). Contractors must be registered when they agreed to do the work to bring an action for compensation (AS 08.18.151); that likely bars lien foreclosure by unregistered contractors (statute does not mention liens).

How long do I have to enforce a mechanics lien in Alaska?

Lien does not bind property more than 6 months after recording unless (1) an enforcement action is commenced within that time, or (2) an extension notice (showing original recording date, book/page or serial number, balance owing) is recorded in the same office within the original 6 months, giving 6 months from recording of the extension notice. Statute does not state a limit on number of extensions; treat as one.

Mechanics lien deadlines in nearby states

See mechanics lien deadlines for all 50 states

Get paid before it gets to a lien.

AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.

Book a demo

Sam Frenzley
About the authorSam Frenzley

Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.

You did the work. Let AI chase the money.

AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.

  • Keep QuickBooks
  • Start with one invoice
  • Stay in control