Oklahoma mechanics lien: primes file within 4 months after last work, subs within 90 days after last work. Notice and home rules, in plain English.
Oklahoma mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Oklahoma mechanics lien deadlines in plain English, with the law behind each rule.

Quick answer: Oklahoma mechanics lien deadlines
Prime 4 months; others 90 days after last furnishing (§§ 142, 143).
Last updated: November 23, 2026
This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Oklahoma statute (42 O.S. §§ 141–143.4, 171–178) in November 2026. Read the current law or ask a Oklahoma construction attorney before you file.
"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.
| Rule | What Oklahoma requires | Law |
|---|---|---|
| Preliminary notice: prime contractor | None. The pre-lien notice duty applies only to claimants other than the original contractor. A 'Homeowner Notice' before work, claimed by Levelset and Billd, was REPEALED effective 2011-11-01 (former 42 O.S. 142.1, 142.3, 142.5). | 42 O.S. 142.6(A); Laws 2011, c. 23 |
| Preliminary notice: subcontractor | Pre-lien notice to the original contractor and the owner, no later than 75 days after the last date of supply of material, services, labor or equipment. Only one notice per project; none needed for agreed retainage. Exempt: an aggregate claim under $10,000, and residential projects of 4 or fewer units where none is owner-occupied. The exemptions do not apply to property occupied as a dwelling by an owner, where the notice is always required. Service: hand delivery with a delivery confirmation receipt, automated transaction (12A O.S. 15-115), or certified mail RRR (effective on mailing). A notarized compliance affidavit is filed with the lien statement. | 42 O.S. 142.6(B)(1)-(6),(C) |
| Preliminary notice: supplier | Same as sub (any claimant other than the original contractor). | 42 O.S. 142.6 |
| Notice of intent to lien | No separate notice of intent. The 75-day pre-lien notice is the only pre-filing notice. | 42 O.S. 142.6 |
| Lien filing deadline: prime contractor | File the lien statement with the county clerk of the county where the land lies within 4 months after the date material or equipment was last furnished or labor last performed. | 42 O.S. 142 |
| Lien filing deadline: subcontractor and supplier | A sub or supplier under the original contractor files a verified statement with the county clerk within 90 days after material or equipment was last furnished or labor last performed under the subcontract. | 42 O.S. 143 |
| Residential projects | Same 4 months / 90 days. Owner-occupied dwellings make the 75-day pre-lien notice mandatory for non-primes regardless of amount. | 42 O.S. 142, 143, 142.6(B)(1) |
| Notice of completion: does it shorten the deadline? | No completion or commencement notice shortens deadlines. | 42 O.S. 141-143.4 |
| Serving the owner after you file | Unchanged from wave 2 (143.1 was not re-fetched this session). The claimant gives the addresses and pays the fee; the clerk mails notice of the lien by certified mail within 5 business days. If the owner cannot be found, serve the occupant or post the property, by affidavit, within 60 days of filing. | 42 O.S. 143.1 |
| Deadline to sue (enforce the lien) | Civil action in the district court of the county within 1 year from filing the lien with the county clerk. | 42 O.S. 172 |
Roofing, restoration and remodeling work on homes often has extra rules. In Oklahoma:
Owner-occupied dwelling (any size): a non-prime's lien is invalid without the 75-day pre-lien notice, even under $10,000. Non-owner-occupied residential of 4 or fewer units: exempt. No prime homeowner notice (repealed 2011). The homestead exemption does not bar liens for improvement work (31 O.S. 5). Equipment lessors are excluded on homestead or agricultural land (143.3, per Levelset).
Same 4 months / 90 days. Owner-occupied dwellings make the 75-day pre-lien notice mandatory for non-primes regardless of amount.
Example: A subcontractor's last day of work on a Oklahoma job was Monday, March 2, 2026. With a 90-day deadline from the last day of work, count 90 days forward: the lien must be filed by Sunday, May 31, 2026. Don't wait for the last day. Set a reminder a few weeks earlier, and check whether a notice of completion or other rule in the table above changes your clock.
A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:
Prime contractors: File the lien statement with the county clerk of the county where the land lies within 4 months after the date material or equipment was last furnished or labor last performed. Subcontractors and suppliers: A sub or supplier under the original contractor files a verified statement with the county clerk within 90 days after material or equipment was last furnished or labor last performed under the subcontract.
Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 4 months after your last day of work or materials. Subcontractors and suppliers: 90 days after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.
Pre-lien notice to the original contractor and the owner, no later than 75 days after the last date of supply of material, services, labor or equipment. Only one notice per project; none needed for agreed retainage. Exempt: an aggregate claim under $10,000, and residential projects of 4 or fewer units where none is owner-occupied. The exemptions do not apply to property occupied as a dwelling by an owner, where the notice is always required. Service: hand delivery with a delivery confirmation receipt, automated transaction (12A O.S. 15-115), or certified mail RRR (effective on mailing). A notarized compliance affidavit is filed with the lien statement.
No separate notice of intent. The 75-day pre-lien notice is the only pre-filing notice.
Owner-occupied dwelling (any size): a non-prime's lien is invalid without the 75-day pre-lien notice, even under $10,000. Non-owner-occupied residential of 4 or fewer units: exempt. No prime homeowner notice (repealed 2011). The homestead exemption does not bar liens for improvement work (31 O.S. 5). Equipment lessors are excluded on homestead or agricultural land (143.3, per Levelset).
Civil action in the district court of the county within 1 year from filing the lien with the county clerk.
See mechanics lien deadlines for all 50 states
Get paid before it gets to a lien.
AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.
Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.
AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.