AR Workflow Blog/Collections tips

North Dakota Mechanics Lien: Deadlines and How to File

North Dakota mechanics lien: file within 90 days after last work. Notice rules, home rules and how to file, with the law, in plain English.

Sam Frenzley
Founder, AR Workflow
9 min read

North Dakota mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the North Dakota mechanics lien deadlines in plain English, with the law behind each rule.

North Dakota mechanics lien deadlines and how to file

Quick answer: North Dakota mechanics lien deadlines

90 days after completing the claimant's contribution for full rights; a later lien is still valid against the owner except for amounts the owner paid a contractor before recording; outer limit 3 years after the FIRST material furnished (§§ 35-27-13, -14). Lien never exceeds what the owner still owes (§ 35-27-02(2)).

Last updated: November 23, 2026

This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the North Dakota statute (N.D. Cent. Code ch. 35-27) in November 2026. Read the current law or ask a North Dakota construction attorney before you file.

North Dakota lien law at a glance

"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.

RuleWhat North Dakota requiresLaw
Preliminary notice: prime contractornoneN.D.C.C. ch. 35-27 (no preliminary-notice section; 35-27-05 notice of intention repealed S.L. 2009 ch. 293 s.16)
Preliminary notice: subcontractornoneN.D.C.C. ch. 35-27
Preliminary notice: suppliernoneN.D.C.C. ch. 35-27; 35-27-21 (optional)
Notice of intent to lienRequired for ALL claimants, including primes in privity with the owner: written notice that a lien will be claimed, sent by certified mail to the legal or equitable owner at least 10 days before the lien is recorded. App rule: send by day 80 after last contribution, or earlier for a safety margin.N.D.C.C. 35-27-02(4) (as amended S.L. 2023 ch. 320 and ch. 321)
Lien filing deadline: prime contractor90 days after all of the claimant's contribution is done (last furnishing), for full protection. A later lien is still valid against the owner, except to the extent the owner paid a contractor before the lien was recorded, and except against good-faith purchasers or encumbrancers for value whose rights accrued before filing. Absolute cap: no lien may be filed more than 3 years after the FIRST item of material was furnished.N.D.C.C. 35-27-13; 35-27-14
Lien filing deadline: subcontractor and supplierSame as prime: 90 days after the claimant's contribution is done, with the 3-year cap from first furnishing. Recovery is limited by owner payments: a lien is limited to the difference between the price the owner paid and the value of the contribution, and no lien is allowed if the owner has paid the full price.N.D.C.C. 35-27-13, -14; 35-27-02(2); 35-27-09
Residential projectsSame as commercial; ch. 35-27 has no separate residential or owner-occupied deadline.N.D.C.C. 35-27-13
Notice of completion: does it shorten the deadline?No notice of completion or commencement mechanism; nothing shortens the lien deadline. Related: within 15 days after completion of the contract, the owner may require a lienor to furnish an itemized, verified account, and no enforcement action may begin until 10 days after it is furnished.N.D.C.C. ch. 35-27; 35-27-09
Serving the owner after you file(1) 10-day pre-recording notice by certified mail to the legal or equitable owner (35-27-02(4)). (2) No statutory duty to serve a copy of the recorded lien. (3) Before suit: written notice of intent to enforce, personally served at least 10 days before suit, or by registered mail to the owner's last-known address at least 20 days before suit (35-27-24).N.D.C.C. 35-27-02(4); 35-27-24
Deadline to sue (enforce the lien)The claimant must commence suit AND record a lis pendens within 3 years after the lien is recorded, or the lien is deemed satisfied. If the owner, or someone for the owner, delivers a written demand to the lienor and files it with the county recorder, suit and lis pendens are due within 30 days after delivery, regardless of delivery method, or the lien is forfeited. An owner who successfully contests a lien recovers full costs and reasonable attorney's fees (35-27-24.1).N.D.C.C. 35-27-25; 35-27-24.1

North Dakota mechanics lien rules for homes and homeowners

Roofing, restoration and remodeling work on homes often has extra rules. In North Dakota:

No residential-specific lien rules in ch. 35-27. The homestead exemption does not protect against construction liens for work or material furnished exclusively to improve that homestead (47-18-04(1)). Separately, for 1-2 family dwellings and improvements over $2,000 to a dwelling, 43-07-26 requires the contractor to give the owner written notice of the defect-notice and right-to-cure requirements at completion of the improvement. The owner must mail defect notice within 6 months of knowledge, and the contractor has about 30 business days to inspect and cure. This is not a lien prerequisite.

Same as commercial; ch. 35-27 has no separate residential or owner-occupied deadline.

How to file a mechanics lien in North Dakota, step by step

  1. Check the notice rules before you start. Look at the preliminary notice rows above for your role. Send any required notice early, by a method you can prove (like certified mail).
  2. Keep a job file from day one. Save the contract, change orders, invoices, delivery tickets, photos, and your first and last day of work. Most North Dakota deadlines count from one of those dates.
  3. Follow up on every unpaid invoice. Send friendly reminders, then firm ones. Most customers pay before it ever gets to a lien.
  4. Send a warning before you file. Required for ALL claimants, including primes in privity with the owner: written notice that a lien will be claimed, sent by certified mail to the legal or equitable owner at least 10 days before the lien is recorded. App rule: send by day 80 after last contribution, or earlier for a safety margin.
  5. File the lien on time and serve the owner. Prime: 90 days after your last day of work or materials. Subs and suppliers: 90 days after your last day of work or materials. Then serve the owner as the table explains.
  6. Enforce it or release it. Sue within 3 years after the lien is filed. If you get paid, release the lien right away.

Example: A subcontractor's last day of work on a North Dakota job was Monday, March 2, 2026. With a 90-day deadline from the last day of work, count 90 days forward: the lien must be filed by Sunday, May 31, 2026. Don't wait for the last day. Set a reminder a few weeks earlier, and check whether a notice of completion or other rule in the table above changes your clock.

Watch: how to send a notice of intent to lien (3 minutes)

Before you file a lien in North Dakota: try to get paid first

A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:

Read the North Dakota lien law

Frequently asked questions

What is the deadline to file a mechanics lien in North Dakota?

Prime contractors: 90 days after all of the claimant's contribution is done (last furnishing), for full protection. A later lien is still valid against the owner, except to the extent the owner paid a contractor before the lien was recorded, and except against good-faith purchasers or encumbrancers for value whose rights accrued before filing. Absolute cap: no lien may be filed more than 3 years after the FIRST item of material was furnished. Subcontractors and suppliers: Same as prime: 90 days after the claimant's contribution is done, with the 3-year cap from first furnishing. Recovery is limited by owner payments: a lien is limited to the difference between the price the owner paid and the value of the contribution, and no lien is allowed if the owner has paid the full price.

How do I file a mechanics lien in North Dakota?

Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 90 days after your last day of work or materials. Subcontractors and suppliers: 90 days after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.

Do subcontractors need to send a preliminary notice in North Dakota?

none

Do I need to send a notice of intent to lien in North Dakota?

Required for ALL claimants, including primes in privity with the owner: written notice that a lien will be claimed, sent by certified mail to the legal or equitable owner at least 10 days before the lien is recorded. App rule: send by day 80 after last contribution, or earlier for a safety margin.

Are there special lien rules for homes in North Dakota?

No residential-specific lien rules in ch. 35-27. The homestead exemption does not protect against construction liens for work or material furnished exclusively to improve that homestead (47-18-04(1)). Separately, for 1-2 family dwellings and improvements over $2,000 to a dwelling, 43-07-26 requires the contractor to give the owner written notice of the defect-notice and right-to-cure requirements at completion of the improvement. The owner must mail defect notice within 6 months of knowledge, and the contractor has about 30 business days to inspect and cure. This is not a lien prerequisite.

How long do I have to enforce a mechanics lien in North Dakota?

The claimant must commence suit AND record a lis pendens within 3 years after the lien is recorded, or the lien is deemed satisfied. If the owner, or someone for the owner, delivers a written demand to the lienor and files it with the county recorder, suit and lis pendens are due within 30 days after delivery, regardless of delivery method, or the lien is forfeited. An owner who successfully contests a lien recovers full costs and reasonable attorney's fees (35-27-24.1).

Mechanics lien deadlines in nearby states

See mechanics lien deadlines for all 50 states

Get paid before it gets to a lien.

AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.

Book a demo

Sam Frenzley
About the authorSam Frenzley

Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.

You did the work. Let AI chase the money.

AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.

  • Keep QuickBooks
  • Start with one invoice
  • Stay in control