Minnesota Mechanics Lien: Deadlines and How to File

Minnesota mechanics lien: file within 120 days after last work. Notice rules, home rules and how to file, with the law, in plain English.

Sam Frenzley
Founder, AR Workflow
9 min read

Minnesota mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Minnesota mechanics lien deadlines in plain English, with the law behind each rule.

Minnesota mechanics lien deadlines and how to file

Quick answer: Minnesota mechanics lien deadlines

Record and serve lien statement within 120 days after last furnishing (§ 514.08).

Last updated: November 23, 2026

This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Minnesota statute (Minn. Stat. §§ 514.01–.135) in November 2026. Read the current law or ask a Minnesota construction attorney before you file.

Minnesota lien law at a glance

"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.

RuleWhat Minnesota requiresLaw
Preliminary notice: prime contractorRequired for every contractor who contracts directly with the owner and has or will have subs or suppliers, unless an exemption applies. The notice must be in the written contract. With no written contract, deliver it within 10 days after the work is agreed upon. It must use the statutory text in 10-point bold (or capitals if typewritten). If it is missed, the prime has NO lien. Exempt: the contractor is the owner, or is under common control with the owner (subd. 4a); wholly residential property with more than 4 family units (subd. 4b); nonresidential or partly nonresidential, nonagricultural work adding or involving more than 5,000 usable sq ft (subd. 4c).Minn. Stat. 514.011 subd. 1, 4a, 4b, 4c
Preliminary notice: subcontractorSubs and suppliers not in direct contract with the owner must give the owner, or the owner's authorized agent, written notice no later than 45 days after first furnishing labor, skill or materials. Delivery is personal or by certified mail. The same exemptions as the prime apply (subd. 4a-4c). There is a good-faith savings clause: the lien is not lost for lack of strict compliance if a good-faith effort was made, unless the owner or another claimant proves direct damage.Minn. Stat. 514.011 subd. 2
Preliminary notice: supplierSame as prelim_sub: 45 days after first furnishing, unless exempt.Minn. Stat. 514.011 subd. 2
Notice of intent to lienThere is no separate notice of intent. The lien statement itself contains the 'notice of intention to claim and hold a lien' (514.08 subd. 2).Minn. Stat. 514.08 subd. 2
Lien filing deadline: prime contractorFile with the county recorder (or the registrar of titles for Torrens land) AND serve the owner within 120 days after doing the last of the work.Minn. Stat. 514.08 subd. 1
Lien filing deadline: subcontractor and supplierSame as prime: 120 days after the claimant's own last work, for both filing and service.Minn. Stat. 514.08 subd. 1
Residential projectsSame 120 days. The residential differences are prerequisites (pre-lien notice always required on property with 4 or fewer units; unlicensed residential contractors have no lien), not a different deadline.Minn. Stat. 514.08; 514.011 subd. 4b; 326B.845 subd. 2
Notice of completion: does it shorten the deadline?Minnesota has no notice of completion, commencement or termination that shortens lien deadlines.Minn. Stat. ch. 514
Serving the owner after you fileServe a copy of the lien statement personally or by certified mail on the owner, the owner's authorized agent, or the person who entered into the contract with the contractor, within the same 120 days. If service is missed, the lien ceases.Minn. Stat. 514.08 subd. 1
Deadline to sue (enforce the lien)Start the enforcement action (complaint or answer filed with the court administrator) and record a notice of lis pendens within 1 year after the date of the last item of the claim as stated in the recorded lien statement. Parties not joined within the year are not bound.Minn. Stat. 514.12 subd. 1, 3

Minnesota mechanics lien rules for homes and homeowners

Roofing, restoration and remodeling work on homes often has extra rules. In Minnesota:

(1) The pre-lien notice (prime and sub) is required on all residential property with 4 or fewer family units. Only wholly residential property with more than 4 units is exempt (514.011 subd. 4b). (2) A residential contractor who knowingly works unlicensed in violation of 326B.802-.885 has no lien, and the lien is void (326B.845 subd. 2). Licensed contractors' and suppliers' rights are preserved. (3) Lien amount cap: total liens cannot exceed the contract price, less owner payments made before receiving notice, payments to discharge liens under 514.07, and payments made against valid waivers (514.03 subd. 2). (4) Homestead agricultural land: the lien is limited to 40 acres (514.03 subd. 3). There is no written-contract requirement beyond the pre-lien notice; SF 4363 failed.

Same 120 days. The residential differences are prerequisites (pre-lien notice always required on property with 4 or fewer units; unlicensed residential contractors have no lien), not a different deadline.

How to file a mechanics lien in Minnesota, step by step

  1. Check the notice rules before you start. Look at the preliminary notice rows above for your role. Send any required notice early, by a method you can prove (like certified mail).
  2. Keep a job file from day one. Save the contract, change orders, invoices, delivery tickets, photos, and your first and last day of work. Most Minnesota deadlines count from one of those dates.
  3. Follow up on every unpaid invoice. Send friendly reminders, then firm ones. Most customers pay before it ever gets to a lien.
  4. Send a warning before you file. There is no separate notice of intent. The lien statement itself contains the 'notice of intention to claim and hold a lien' (514.08 subd. 2).
  5. File the lien on time and serve the owner. Prime: 120 days after your last day of work or materials. Subs and suppliers: 120 days after your last day of work or materials. Then serve the owner as the table explains.
  6. Enforce it or release it. Sue within 1 year after your last day of work or materials. If you get paid, release the lien right away.

Example: A subcontractor's last day of work on a Minnesota job was Monday, March 2, 2026. With a 120-day deadline from the last day of work, count 120 days forward: the lien must be filed by Tuesday, June 30, 2026. Don't wait for the last day. Set a reminder a few weeks earlier, and check whether a notice of completion or other rule in the table above changes your clock.

Watch: how to send a notice of intent to lien (3 minutes)

Before you file a lien in Minnesota: try to get paid first

A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:

Read the Minnesota lien law

Frequently asked questions

What is the deadline to file a mechanics lien in Minnesota?

Prime contractors: File with the county recorder (or the registrar of titles for Torrens land) AND serve the owner within 120 days after doing the last of the work. Subcontractors and suppliers: Same as prime: 120 days after the claimant's own last work, for both filing and service.

How do I file a mechanics lien in Minnesota?

Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 120 days after your last day of work or materials. Subcontractors and suppliers: 120 days after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.

Do subcontractors need to send a preliminary notice in Minnesota?

Subs and suppliers not in direct contract with the owner must give the owner, or the owner's authorized agent, written notice no later than 45 days after first furnishing labor, skill or materials. Delivery is personal or by certified mail. The same exemptions as the prime apply (subd. 4a-4c). There is a good-faith savings clause: the lien is not lost for lack of strict compliance if a good-faith effort was made, unless the owner or another claimant proves direct damage.

Do I need to send a notice of intent to lien in Minnesota?

There is no separate notice of intent. The lien statement itself contains the 'notice of intention to claim and hold a lien' (514.08 subd. 2).

Are there special lien rules for homes in Minnesota?

(1) The pre-lien notice (prime and sub) is required on all residential property with 4 or fewer family units. Only wholly residential property with more than 4 units is exempt (514.011 subd. 4b). (2) A residential contractor who knowingly works unlicensed in violation of 326B.802-.885 has no lien, and the lien is void (326B.845 subd. 2). Licensed contractors' and suppliers' rights are preserved. (3) Lien amount cap: total liens cannot exceed the contract price, less owner payments made before receiving notice, payments to discharge liens under 514.07, and payments made against valid waivers (514.03 subd. 2). (4) Homestead agricultural land: the lien is limited to 40 acres (514.03 subd. 3). There is no written-contract requirement beyond the pre-lien notice; SF 4363 failed.

How long do I have to enforce a mechanics lien in Minnesota?

Start the enforcement action (complaint or answer filed with the court administrator) and record a notice of lis pendens within 1 year after the date of the last item of the claim as stated in the recorded lien statement. Parties not joined within the year are not bound.

Mechanics lien deadlines in nearby states

See mechanics lien deadlines for all 50 states

Get paid before it gets to a lien.

AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.

Book a demo

Sam Frenzley
About the authorSam Frenzley

Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.

You did the work. Let AI chase the money.

AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.

  • Keep QuickBooks
  • Start with one invoice
  • Stay in control