Ohio mechanics lien: file within 75 days after last work. Notice rules, home rules and how to file, with the law, in plain English.
Ohio mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Ohio mechanics lien deadlines in plain English, with the law behind each rule.

Quick answer: Ohio mechanics lien deadlines
75 days after last furnishing (commercial); 60 days for 1–2 family dwellings and residential condo units; 120 days for oil/gas wells (§ 1311.06(B)).
Last updated: November 23, 2026
This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Ohio statute (R.C. §§ 1311.01–1311.22) in November 2026. Read the current law or ask a Ohio construction attorney before you file.
"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.
| Rule | What Ohio requires | Law |
|---|---|---|
| Preliminary notice: prime contractor | None. Original contractors do not serve a Notice of Furnishing on the owner they contracted with. | R.C. 1311.05 |
| Preliminary notice: subcontractor | Conditional. If a Notice of Commencement (NOC) is recorded and the job is not a home construction contract, a sub or supplier not in privity serves a Notice of Furnishing (NOF) on the owner's designee named in the NOC (or the owner if none) and on the original contractor, within 21 days after first furnishing. Deadline extends to 21 days after the NOC is recorded (1311.04(I)) or actually served after written request (1311.04(J)) if the owner failed to do so. Late NOF: lien covers only work in the 21 days before service and after. Exempt: laborers; no NOC recorded; home construction contracts; NOC filed under 1311.04(O); a first-tier sub need not serve the original contractor (but still serves the owner). | R.C. 1311.05; 1311.04(I),(J),(O) |
| Preliminary notice: supplier | Same as subs. A supplier in direct privity with the owner is exempt. | R.C. 1311.05 |
| Notice of intent to lien | None required. | R.C. ch. 1311 |
| Lien filing deadline: prime contractor | Record affidavit with the county recorder within 75 days after the claimant's last labor or materials. 60 days for a one- or two-family dwelling or residential condo unit. 120 days for oil/gas well liens under 1311.021. | R.C. 1311.06(B)(1)-(3) |
| Lien filing deadline: subcontractor and supplier | Same as prime, measured from the claimant's own last furnishing. | R.C. 1311.06(B) |
| Residential projects | 60 days after last furnishing for any lien 'in connection with a one- or two-family dwelling' or residential condo unit. This applies whether or not the home is owner-occupied (e.g., rentals and builder spec homes too). | R.C. 1311.06(B)(1) |
| Notice of completion: does it shorten the deadline? | No notice shortens the lien filing deadline. HB 96 (eff. 9/30/2025) added: (1) an NOC expires 4 years after recording unless it states otherwise (was 6); (2) the owner may record an affidavit of completion, and the recorder marks the NOC expired. The owner mails a copy to the original contractor and to anyone who served an NOF. Expiration does not affect lien attachment, continuance or priority (1311.04(U)). Service of the affidavit does not extend any lien rights or periods (1311.04(T)(4)). It does not cut short the 60/75-day filing period. | R.C. 1311.04(S),(T),(U) (HB 96) |
| Serving the owner after you file | Serve a copy of the filed affidavit on the owner, part owner or lessee (or the designee in the NOC) within 30 days after filing, by 1311.19 methods. If service cannot be made, post it in a conspicuous place on the premises within 10 days after the 30 days end. Treat missing this as fatal: Suburban Heating Co. v. Lougher, 4 Ohio App.2d 343 (1964), reversed a lien judgment where no service was shown. In re Charms, 142 B.R. 186 (Bankr. N.D. Ohio 1992), reads Suburban Heating as holding that failure to serve invalidates the lien. Contrast: R.C. 1311.22 says substantial compliance is enough, and In re Rickert, 156 B.R. 200 (Bankr. S.D. Ohio 1993), held that early service (before filing) substantially complied. | R.C. 1311.07; 1311.22 |
| Deadline to sue (enforce the lien) | The lien lasts 6 years after the affidavit is filed. If suit is filed within that time, it lasts until final adjudication. Conditional: an owner or other interested party may have the sheriff serve a notice to commence suit. If no suit within 60 days after service is complete, the lien is void. | R.C. 1311.13; 1311.11 |
Roofing, restoration and remodeling work on homes often has extra rules. In Ohio:
A home construction contract is a contract between an original contractor and an owner, part owner or lessee to improve a 1-2 family dwelling or condo unit used or intended as a personal residence. It expressly includes siding, roofing, storm windows and awnings. 'Improvement' includes altering and repairing (1311.01), so roofing, siding and restoration jobs on a personal residence qualify. Rules: (1) no NOC (1311.04(O)) and no NOF (1311.05); (2) no lien for anyone if the owner paid the original contractor in full before receiving a copy of the lien affidavit; (3) sub, supplier and laborer liens are capped at the unpaid contract balance minus cost to complete, pro rata, with laborers first; (4) the owner may withhold payment until the original contractor gives an affidavit that all claims are paid; (5) a lienholder who fails to release within 30 days after notice of full payment is liable for damages, costs and attorney fees.
60 days after last furnishing for any lien 'in connection with a one- or two-family dwelling' or residential condo unit. This applies whether or not the home is owner-occupied (e.g., rentals and builder spec homes too).
Example: A subcontractor's last day of work on a Ohio job was Monday, March 2, 2026. With a 75-day deadline from the last day of work, count 75 days forward: the lien must be filed by Saturday, May 16, 2026. Don't wait for the last day. Set a reminder a few weeks earlier, and check whether a notice of completion or other rule in the table above changes your clock.
A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:
Prime contractors: Record affidavit with the county recorder within 75 days after the claimant's last labor or materials. 60 days for a one- or two-family dwelling or residential condo unit. 120 days for oil/gas well liens under 1311.021. Subcontractors and suppliers: Same as prime, measured from the claimant's own last furnishing.
Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 75 days after your last day of work or materials. Subcontractors and suppliers: 75 days after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.
Conditional. If a Notice of Commencement (NOC) is recorded and the job is not a home construction contract, a sub or supplier not in privity serves a Notice of Furnishing (NOF) on the owner's designee named in the NOC (or the owner if none) and on the original contractor, within 21 days after first furnishing. Deadline extends to 21 days after the NOC is recorded (1311.04(I)) or actually served after written request (1311.04(J)) if the owner failed to do so. Late NOF: lien covers only work in the 21 days before service and after. Exempt: laborers; no NOC recorded; home construction contracts; NOC filed under 1311.04(O); a first-tier sub need not serve the original contractor (but still serves the owner).
None required.
A home construction contract is a contract between an original contractor and an owner, part owner or lessee to improve a 1-2 family dwelling or condo unit used or intended as a personal residence. It expressly includes siding, roofing, storm windows and awnings. 'Improvement' includes altering and repairing (1311.01), so roofing, siding and restoration jobs on a personal residence qualify. Rules: (1) no NOC (1311.04(O)) and no NOF (1311.05); (2) no lien for anyone if the owner paid the original contractor in full before receiving a copy of the lien affidavit; (3) sub, supplier and laborer liens are capped at the unpaid contract balance minus cost to complete, pro rata, with laborers first; (4) the owner may withhold payment until the original contractor gives an affidavit that all claims are paid; (5) a lienholder who fails to release within 30 days after notice of full payment is liable for damages, costs and attorney fees.
The lien lasts 6 years after the affidavit is filed. If suit is filed within that time, it lasts until final adjudication. Conditional: an owner or other interested party may have the sheriff serve a notice to commence suit. If no suit within 60 days after service is complete, the lien is void.
See mechanics lien deadlines for all 50 states
Get paid before it gets to a lien.
AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.
Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.
AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.