Oregon mechanics lien guide: deadlines, notice rules, homeowner rules and how to file, with the law behind each rule.
Oregon mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Oregon mechanics lien deadlines in plain English, with the law behind each rule.

Quick answer: Oregon mechanics lien deadlines
75 days after the earlier of ceasing work or completion (§ 87.035).
Last updated: November 23, 2026
This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Oregon statute (ORS 87.001–87.093) in November 2026. Read the current law or ask a Oregon construction attorney before you file.
"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.
| Rule | What Oregon requires | Law |
|---|---|---|
| Preliminary notice: prime contractor | No Notice of Right to a Lien is needed for work furnished at the owner's request (an original contractor). On residential jobs over $2,000, the separate Information Notice to Owner applies (see residential_rules). | ORS 87.021(1); 87.093 |
| Preliminary notice: subcontractor | Conditional. On a 'residential building' (owner-occupied as a residence and no more than 4 units), every claimant not hired by the owner must give the NRL. On a 'commercial improvement' (anything not a residential building, including rentals and spec homes not owner-occupied), labor-only providers, labor-and-material (installing) subs, and equipment renters are exempt. The NRL protects only what was furnished from 8 business days before it was delivered or mailed. | ORS 87.021(1),(3)(a),(3)(b) |
| Preliminary notice: supplier | Required on all private jobs. Material-only suppliers are not in the commercial exemption, so they must send the NRL on commercial and residential work alike. To get priority over a recorded mortgage for materials, the supplier must also notify the mortgagee (87.025). | ORS 87.021(1),(3); 87.025 |
| Notice of intent to lien | Give written notice of intent to foreclose to the owner and mortgagee at least 10 days before starting suit. Failure bars costs, disbursements and attorney fees; it does not void the lien. Separately, the owner may demand an itemized list within 5 days. | ORS 87.057(1),(3) |
| Lien filing deadline: prime contractor | Within 75 days after the claimant ceased to provide labor, rent equipment or furnish materials, or 75 days after completion of construction, whichever is earlier. Design professionals and benefit trustees (87.010(3) etc.) get 75 days after completion of construction. | ORS 87.035(1) |
| Lien filing deadline: subcontractor and supplier | Same as prime: 75 days after the earlier of ceasing to furnish or completion of construction. | ORS 87.035(1) |
| Residential projects | Same 75 days. There is no residential extension. Residential differs only in who must send the NRL (all non-owner-hired claimants), the 87.036 unlicensed-contractor bar, and the 87.037/87.093 prime-contract conditions. | ORS 87.035(1) |
| Notice of completion: does it shorten the deadline? | Completion of construction occurs at the earliest of: (a) substantial completion; (b) posting AND recording of a completion notice; or (c) abandonment. The completion notice may be posted, once all original contractors have substantially performed, by an original contractor, the owner, the mortgagee or their agent, in a conspicuous place on the land or improvement. It must be recorded within 5 days after posting, with an affidavit of posting. Nobody has to be mailed or served. Abandonment occurs on the 75th day after work ceases, unless a nonabandonment notice is recorded by day 74 (renewable every 150 days). Because of the earlier-of rule, a completion notice can only shorten a claimant's deadline. | ORS 87.045(1)-(6) |
| Serving the owner after you file | Mail the owner and mortgagee a notice of filing with a copy of the claim no later than 20 days after filing. Failure bars recovery of costs, disbursements and attorney fees; the lien itself survives. | ORS 87.039(1),(2) |
| Deadline to sue (enforce the lien) | Suit within 120 days after the claim of lien is filed. If the claim of lien states the terms of an extended-payment arrangement, the 120 days run from the end of that period, but no lien lasts more than 2 years after filing. The suit is deemed commenced under ORS 12.020 (filing plus service within 60 days); for other lien claimants joined in the action, it is commenced when the complaint is filed. | ORS 87.055 |
Roofing, restoration and remodeling work on homes often has extra rules. In Oregon:
(1) 87.037: an original contractor has no lien if ORS 701.305 requires a written contract and none exists. (2) 87.093: on residential contracts over $2,000, the original contractor must deliver the CCB Information Notice to Owner (at contract signing, or within 5 days after it knows or should know the price will exceed $2,000). It is not required if the owner is a CCB-licensed contractor. Without it, there is no lien. (3) ADD 87.036: on renovation, remodel, repair or alteration of an existing owner-occupied residence, a sub or supplier cannot perfect a lien if the contractor it dealt with was unlicensed when the sub first contracted or first delivered, whichever was earlier. The bar does not apply to cash or consumer-credit purchases. (4) Every non-owner-hired claimant must send the NRL on owner-occupied buildings of 4 units or fewer.
Same 75 days. There is no residential extension. Residential differs only in who must send the NRL (all non-owner-hired claimants), the 87.036 unlicensed-contractor bar, and the 87.037/87.093 prime-contract conditions.
A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:
Prime contractors: Within 75 days after the claimant ceased to provide labor, rent equipment or furnish materials, or 75 days after completion of construction, whichever is earlier. Design professionals and benefit trustees (87.010(3) etc.) get 75 days after completion of construction. Subcontractors and suppliers: Same as prime: 75 days after the earlier of ceasing to furnish or completion of construction.
Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 75 days after the earlier of your last day of work or project completion. Subcontractors and suppliers: 75 days after the earlier of your last day of work or project completion. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.
Conditional. On a 'residential building' (owner-occupied as a residence and no more than 4 units), every claimant not hired by the owner must give the NRL. On a 'commercial improvement' (anything not a residential building, including rentals and spec homes not owner-occupied), labor-only providers, labor-and-material (installing) subs, and equipment renters are exempt. The NRL protects only what was furnished from 8 business days before it was delivered or mailed.
Give written notice of intent to foreclose to the owner and mortgagee at least 10 days before starting suit. Failure bars costs, disbursements and attorney fees; it does not void the lien. Separately, the owner may demand an itemized list within 5 days.
(1) 87.037: an original contractor has no lien if ORS 701.305 requires a written contract and none exists. (2) 87.093: on residential contracts over $2,000, the original contractor must deliver the CCB Information Notice to Owner (at contract signing, or within 5 days after it knows or should know the price will exceed $2,000). It is not required if the owner is a CCB-licensed contractor. Without it, there is no lien. (3) ADD 87.036: on renovation, remodel, repair or alteration of an existing owner-occupied residence, a sub or supplier cannot perfect a lien if the contractor it dealt with was unlicensed when the sub first contracted or first delivered, whichever was earlier. The bar does not apply to cash or consumer-credit purchases. (4) Every non-owner-hired claimant must send the NRL on owner-occupied buildings of 4 units or fewer.
Suit within 120 days after the claim of lien is filed. If the claim of lien states the terms of an extended-payment arrangement, the 120 days run from the end of that period, but no lien lasts more than 2 years after filing. The suit is deemed commenced under ORS 12.020 (filing plus service within 60 days); for other lien claimants joined in the action, it is commenced when the complaint is filed.
See mechanics lien deadlines for all 50 states
Get paid before it gets to a lien.
AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.
Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.
AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.