Schedule of Values: Free Template + How to Build One

What a schedule of values (SOV) is in construction, a schedule of values example, how to build one that gets approved fast, and a free Excel SOV template.

Sam Frenzley
Founder, AR Workflow
7 min read

A schedule of values is the list that tells the owner what each part of your job is worth. Every pay app you send is checked against it. Get it right at the start and you get paid on time all job long. Get it wrong and every pay app turns into a fight. This guide shows you how to build one, with a free Excel template you can use today.

Schedule of values template for construction pay apps

Quick answer: what is a schedule of values?

Last updated: November 23, 2026

Free download: schedule of values template (Excel)

A ready-to-use SOV with sample lines, a running total and a check that it matches your contract sum. Change the lines to fit your job.

Download the SOV template (.xlsx)

Need the pay app too? Download our sample pay application (G702 and G703 style).

What is a schedule of values (SOV) in construction?

A schedule of values is a breakdown of your contract price. It lists the parts of the job, like demo, concrete, framing and electrical, and gives each part a dollar value. Add up all the lines and you get the contract sum.

The SOV is the base for every pay application on the job. When you bill, you do not send a new price list. You say how much of each SOV line is done. If framing is worth $61,000 and it is half done, you bill $30,500 for framing that month.

On jobs that use AIA forms, the SOV becomes the first columns of the G703 continuation sheet. Our pay application guide walks through the G702 and G703 line by line.

Why the schedule of values matters for getting paid

Schedule of values example

Here is a simple SOV for a $310,000 commercial remodel. Your template has the same layout.

ItemDescription of workScheduled value
1General conditions (supervision, trailer, cleanup)$28,000
2Mobilization and permits$9,500
3Demolition$14,000
4Concrete$46,000
5Framing$61,000
6Roofing$38,500
7Electrical$44,000
8Plumbing$36,000
9Drywall and paint$33,000
Contract sum$310,000

Each month, you fill in how much of each line is done. The pay app does the math: work done to date, minus retainage, minus what you already billed, equals what is due now.

How to build a schedule of values, step by step

  1. Start with your bid. Use the same cost codes you used to price the job. That way the SOV matches your job cost reports.
  2. Break the job into parts you can see. Each line should be work the owner or architect can walk up to and check. "Framing, level 2" is easy to check. "Misc." is not.
  3. Split labor and materials on big lines. Some owners ask for this. It also lets you bill for materials when they show up on site.
  4. Put general conditions and mobilization on their own lines. These costs happen early. If they are on their own lines, you can bill them early too.
  5. Add a line for closeout. Punch list, as-builts and warranties. A small line here keeps the owner from holding back more than it should.
  6. Make it add up to the contract sum. To the penny. If it does not match, the first pay app will bounce.
  7. Get it approved before the first pay app. Send it in early. You cannot bill against a line that is not on the approved SOV.

Tip: Retainage comes out of every line. Use our retainage calculator to see how much will be held back each month, and how much you are owed at the end.

Front-loading: why it backfires

Front-loading means putting too much value on early lines so you get more cash up front. It is tempting. But most owners and architects know what each part of a job should cost. If your SOV looks heavy at the start, they will push back, slow down approval, or check every pay app more closely after that. A fair SOV gets approved fast and keeps trust high for the whole job.

Six schedule of values mistakes that slow down payment

  1. Lines that are too big. "Building, $250,000" cannot be checked. Break it up.
  2. Lines that are too small. Two hundred lines take forever to review each month.
  3. A total that does not match the contract. The first pay app will be sent back.
  4. No line for closeout. Then the owner holds more money until the very end.
  5. Change orders added in the wrong place. Add each approved change order as its own new line. Do not change old lines.
  6. Waiting to send it. No approved SOV means no first payment.

Schedule of values and lien rights

Your SOV and pay apps are also your paper trail. If a pay app goes unpaid, they show what work you did and what you are owed. Many states also make you send a preliminary notice early in the job to keep your lien rights. Use our lien deadline calculator to see your dates the day the job starts. And check your state's prompt payment rules to see how fast you must be paid once your pay app is approved.

Frequently asked questions

What does SOV stand for in construction?

SOV stands for schedule of values. It is the list of every part of a job with a dollar value for each part, adding up to the contract price.

What is a schedule of values?

A schedule of values is a list of every part of a construction job with a dollar value for each part. The lines add up to the contract price. It is the base for every progress billing and pay application on the job.

Who makes the schedule of values?

The contractor makes it. On a job with a GC, each sub makes one for its own scope and the GC rolls them into one SOV for the owner. The owner, GC or architect then approves it.

When do you send the schedule of values?

Send it right after the contract is signed and before your first pay application. Most contracts say you cannot be paid until it is approved.

Is the schedule of values the same as the G703?

Not quite. The G703 continuation sheet uses the schedule of values as its first columns. Then it adds columns for work done last time, work done this time, stored materials, percent done, balance and retainage.

How many lines should a schedule of values have?

Enough lines that each one can be checked on site, but not so many that the review takes all day. For most jobs, 10 to 40 lines works well. Big lines can be split by floor or area.

How do change orders go on the schedule of values?

Add each approved change order as a new line at the bottom, with its own value. Do not change the original lines. That keeps the history clear.

Is there a free schedule of values template?

Yes. Download our free schedule of values template in Excel. It adds up your lines and checks them against your contract sum.

Tools and related guides

Your pay app is approved. Now get it paid.

AR Workflow works with QuickBooks and follows up on every invoice and pay app for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.

Book a demo

AIA, G702 and G703 are trademarks of the American Institute of Architects. Our templates are not official AIA documents. This article is general information, not legal advice.

Sam Frenzley
About the authorSam Frenzley

Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.

You did the work. Let AI chase the money.

AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.

  • Keep QuickBooks
  • Start with one invoice
  • Stay in control