Utah mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Utah mechanics lien deadlines in plain English, with the law behind each rule.

Utah mechanics lien deadlines and how to file

Quick answer: Utah mechanics lien deadlines

180 days after final completion of the project, or 90 days after a filed notice of completion (capped at 180) (§ 38-1a-502).

Last updated: November 23, 2026

This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Utah statute (Utah Code §§ 38-1a-101 et seq.; § 38-11-101) in November 2026. Read the current law or ask a Utah construction attorney before you file.

Utah lien law at a glance

"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.

RuleWhat Utah requiresLaw
Preliminary notice: prime contractorRequired. Any person who wants to claim a construction lien, including the original contractor, files a preliminary notice on the State Construction Registry (SCR) within 20 days after starting construction work. The statute has no exemption.Utah Code 38-1a-501(1)(a),(e)
Preliminary notice: subcontractorRequired within 20 days after the claimant starts work. A late notice is allowed, but no lien covers work done before 5 days after the late notice is filed. A notice filed more than 10 days after a notice of completion has no effect.Utah Code 38-1a-501(1)(a),(c),(d)
Preliminary notice: supplierSame as prelim_sub.Utah Code 38-1a-501
Notice of intent to lienNone for private projects. A notice of commencement exists ONLY for government projects: the original contractor, owner or owner-builder files it within 15 days after physical work starts. If it is not filed, the 38-1b notice-of-completion sections do not apply.Utah Code 38-1b-201(1),(7)
Lien filing deadline: prime contractor180 days after final completion of the original contract. If a notice of completion is filed, 90 days after that filing, but never later than 180 days after final completion.Utah Code 38-1a-502(1)
Lien filing deadline: subcontractor and supplierSame as prime. The trigger is final completion of the ORIGINAL contract, not the sub's last work.Utah Code 38-1a-502(1); 38-1a-102(17)
Residential projectsSame deadlines. On owner-occupied residences, non-direct claimants may be barred entirely (38-11-107).Utah Code 38-1a-502; 38-11-107
Notice of completion: does it shorten the deadline?A notice of completion filed on the SCR (by the owner, original contractor, lender, surety or title company, upon final completion) shortens the lien deadline to 90 days after filing, capped at 180 days after final completion. Preliminary notices filed more than 10 days after the NOC are void.Utah Code 38-1a-507(1); 38-1a-502(1); 38-1a-501(1)(d)
Serving the owner after you fileWithin 30 days after filing the lien, deliver it or send it by certified mail to the reputed or record owner. Failure bars costs and attorney fees against the owner. The lien survives.Utah Code 38-1a-502(4)
Deadline to sue (enforce the lien)File the enforcement action within 180 days after filing the notice of lien, and record a lis pendens within the same period. If the owner files bankruptcy first, the claimant has 90 days after the stay lifts. Missing the suit deadline makes the lien automatically void. A missing lis pendens voids the lien except against parties and those with actual knowledge. On a residence, the complaint must be served with the DOPL owner-rights instructions and form, or the lien is barred.Utah Code 38-1a-701(2),(3),(4),(6)

Utah mechanics lien rules for homes and homeowners

Roofing, restoration and remodeling work on homes often has extra rules. In Utah:

(1) A claimant who did not contract directly with the owner of an owner-occupied residence is barred from a lien if the owner (a) had a written contract with a licensed or exempt original contractor (or a developer or factory-built housing retailer) and (b) paid that contractor in full. A subsequent owner who occupies within 180 days is also protected. (2) A sub on a 'contract residence' is barred if the general contract totals no more than $5,000, whether or not the GC is licensed. (3) The owner obtains a DOPL certificate of compliance. The claimant then must remove the lien within 15 days after the postmark to avoid costs, fees and damages. (4) The Residence Lien Recovery Fund is DEPLETED (DOPL, June 2026) and no longer pays claimants. The 38-11-107 lien bar is unchanged in statute and DOPL says homeowners remain protected.

Same deadlines. On owner-occupied residences, non-direct claimants may be barred entirely (38-11-107).

How to file a mechanics lien in Utah, step by step

  1. Check the notice rules before you start. Look at the preliminary notice rows above for your role. Send any required notice early, by a method you can prove (like certified mail).
  2. Keep a job file from day one. Save the contract, change orders, invoices, delivery tickets, photos, and your first and last day of work. Most Utah deadlines count from one of those dates.
  3. Follow up on every unpaid invoice. Send friendly reminders, then firm ones. Most customers pay before it ever gets to a lien.
  4. Send a warning before you file. None for private projects. A notice of commencement exists ONLY for government projects: the original contractor, owner or owner-builder files it within 15 days after physical work starts. If it is not filed, the 38-1b notice-of-completion sections do not apply.
  5. File the lien on time and serve the owner. Prime: 180 days after final completion of the project. Subs and suppliers: 180 days after final completion of the project. Then serve the owner as the table explains.
  6. Enforce it or release it. Sue within 180 days after the lien is filed. If you get paid, release the lien right away.

Watch: how to send a notice of intent to lien (3 minutes)

Before you file a lien in Utah: try to get paid first

A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:

Read the Utah lien law

Frequently asked questions

What is the deadline to file a mechanics lien in Utah?

Prime contractors: 180 days after final completion of the original contract. If a notice of completion is filed, 90 days after that filing, but never later than 180 days after final completion. Subcontractors and suppliers: Same as prime. The trigger is final completion of the ORIGINAL contract, not the sub's last work.

How do I file a mechanics lien in Utah?

Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 180 days after final completion of the project. Subcontractors and suppliers: 180 days after final completion of the project. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.

Do subcontractors need to send a preliminary notice in Utah?

Required within 20 days after the claimant starts work. A late notice is allowed, but no lien covers work done before 5 days after the late notice is filed. A notice filed more than 10 days after a notice of completion has no effect.

Do I need to send a notice of intent to lien in Utah?

None for private projects. A notice of commencement exists ONLY for government projects: the original contractor, owner or owner-builder files it within 15 days after physical work starts. If it is not filed, the 38-1b notice-of-completion sections do not apply.

Are there special lien rules for homes in Utah?

(1) A claimant who did not contract directly with the owner of an owner-occupied residence is barred from a lien if the owner (a) had a written contract with a licensed or exempt original contractor (or a developer or factory-built housing retailer) and (b) paid that contractor in full. A subsequent owner who occupies within 180 days is also protected. (2) A sub on a 'contract residence' is barred if the general contract totals no more than $5,000, whether or not the GC is licensed. (3) The owner obtains a DOPL certificate of compliance. The claimant then must remove the lien within 15 days after the postmark to avoid costs, fees and damages. (4) The Residence Lien Recovery Fund is DEPLETED (DOPL, June 2026) and no longer pays claimants. The 38-11-107 lien bar is unchanged in statute and DOPL says homeowners remain protected.

How long do I have to enforce a mechanics lien in Utah?

File the enforcement action within 180 days after filing the notice of lien, and record a lis pendens within the same period. If the owner files bankruptcy first, the claimant has 90 days after the stay lifts. Missing the suit deadline makes the lien automatically void. A missing lis pendens voids the lien except against parties and those with actual knowledge. On a residence, the complaint must be served with the DOPL owner-rights instructions and form, or the lien is barred.

Mechanics lien deadlines in nearby states

See mechanics lien deadlines for all 50 states

Get paid before it gets to a lien.

AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.

Book a demo

Sam Frenzley
About the authorSam Frenzley

Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.

You did the work. Let AI chase the money.

AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.

  • Keep QuickBooks
  • Start with one invoice
  • Stay in control