Retainage calculator for construction pay apps.

See how much retainage is held this month, how much you get paid now, and how much retainage the customer owes you by the end of the job.

This is not legal advice. Rules differ by state. Some states and public jobs cap retainage or set a deadline to release it.

Figure your retainage

Work billed on earlier pay apps.
Common contract term. Applies to billing after 50%.
$0Held this pay app
$0Paid to you now
$0Total retainage owed to you

Fill in the boxes to see your numbers.

The math

How retainage is figured

Retainage is a part of each payment the customer holds back until the job is done. It protects them if work is not finished. It also slows down your cash.

Retainage held = amount billed x retainage %
Paid now = amount billed - retainage heldExample: $75,000 billed x 10% = $7,500 held. You get $67,500 now. The $7,500 is added to the retainage you collect at the end.

Track it on its own

Keep retainage receivable separate from your regular AR. If it hides in the aging report, it gets forgotten.

Know the release date

Write down when retainage is due: substantial completion, final completion, or a date in your state's law.

Ask the day it is due

Send the retainage invoice and lien waiver the day the job closes. Then follow up on a set schedule until it is paid.

Learn more

Get your retainage back sooner

Retainage is often the last money in and the easiest to lose track of. Read our full guide to retainage in construction, check how retainage changes your numbers with the construction DSO calculator, and see how contractors track pay apps and retainage in construction AR software.

FAQ

Retainage questions

How do you calculate retainage?

Multiply the amount you are billing by the retainage percent. If you bill $50,000 this month and the contract holds 10% retainage, $5,000 is held back and you get paid $45,000 now. The $5,000 is paid later, usually at the end of the job.

What is a normal retainage percentage?

5% to 10% is most common in construction. Many public jobs and some states cap retainage at 5%. Some contracts drop the retainage from 10% to 5% once the job is half done.

When is retainage paid?

Usually after the job is substantially complete or fully complete, and after any punch list and paperwork are done, like lien waivers. Some states set a deadline for releasing retainage after the job is done.

Is retainage income or a receivable?

Retainage you are owed is money you earned but have not been paid yet. Most contractors track it as retainage receivable, separate from regular accounts receivable, so it does not hide in the aging report.

Can retainage be reduced during the job?

Often, yes. Many contracts lower the retainage percent once the job reaches 50% complete. Ask for it in writing, and track the new percent on each pay application.

Why does retainage hurt cash flow?

Because you pay your crew and suppliers in full, but you only get paid 90% to 95% until the end. On a big job, that can tie up tens of thousands of dollars for months. Following up on retainage as soon as it is due gets that cash back sooner.

What is the difference between retainage and retention?

They mean the same thing. Retention is the more common word in some places and on some contracts.