Kansas mechanics lien: primes file within 4 months after last work, subs within 3 months after last work. Notice and home rules, in plain English.
Kansas mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Kansas mechanics lien deadlines in plain English, with the law behind each rule.

Quick answer: Kansas mechanics lien deadlines
Prime 4 months, sub/supplier 3 months after last furnishing. A notice of extension filed within the original period extends to 5 months total (§§ 60-1102(c), 60-1103(e)); NOT available on residential property (structure for no more than two families, owner-occupied or not, § 60-1102(d)).
Last updated: November 23, 2026
This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Kansas statute (K.S.A. 60-1101 to -1112) in November 2026. Read the current law or ask a Kansas construction attorney before you file.
"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.
| Rule | What Kansas requires | Law |
|---|---|---|
| Preliminary notice: prime contractor | None for the prime's own lien. Only exception: new residential structure later sold to a good-faith purchaser needs a notice of intent to perform filed before the deed is recorded (see notice_of_intent), which applies to any claimant including the prime. | K.S.A. 60-1102, 60-1103b |
| Preliminary notice: subcontractor | Residential improvement only (existing structure the owner lives in when claimant first furnishes, incl. attached additions/garages/fences/pools/outbuildings; or new construction on property owned/acquired by an individual that becomes that individual's principal residence; excludes >2-family or commercial use): sub may claim lien only if it mailed the statutory warning statement to any one owner, or holds an owner-signed and dated statement that the GC or claimant gave it. Not required if total claim <= $250. Lien statement must attach the sub/supplier's affidavit that the warning was given. No fixed day deadline, but owner is protected for payments made before receiving the warning, so send at start of work. | K.S.A. 60-1103a(a),(b); 60-1103(a)(2), (d) |
| Preliminary notice: supplier | Same as prelim_sub: suppliers to a contractor/sub need the 60-1103a warning on residential improvements (claim > $250). No commercial notice. | K.S.A. 60-1103a, 60-1103(a)(2) |
| Notice of intent to lien | New residential property (new structure built for use as a residence; NOT improvements/additions to existing structures): to keep lien rights against a good-faith purchaser for value, claimant must file a notice of intent to perform with the district court clerk in the county before the deed passing title is recorded. Notice expires 18 months after filing unless a lien is filed within that time. No service/mailing requirement. No pre-lien notice of intent to lien exists in Kansas. | K.S.A. 60-1103b |
| Lien filing deadline: prime contractor | 4 months after last labor/materials furnished, filed with clerk of district court of county. Non-residential only: 5 months if a notice of extension is filed within the 4 months with the district court and mailed certified AND regular mail to the owner (Judicial Council form). | K.S.A. 60-1102(a),(c) |
| Lien filing deadline: subcontractor and supplier | 3 months after last furnishing by the claimant. Non-residential only: 5 months if a notice of extension is filed within the 3 months with the district court clerk, mailed certified and regular mail to the GC or construction manager, and a copy by regular mail to the owner if known. | K.S.A. 60-1103(a)(1),(e) |
| Residential projects | Prime 4 months, sub/supplier 3 months; no notice-of-extension option. For the extension exclusion, 'residential property' = a structure built for use as a residence and not used/intended for more than two families. This test is occupancy-neutral: rented single-family homes and duplexes are residential (no extension) even though the owner does not live there. | K.S.A. 60-1102(d) (applies to 60-1102 and 60-1103) |
| Notice of completion: does it shorten the deadline? | No notice of completion/commencement mechanism. Deadlines run only from claimant's own last furnishing. | K.S.A. 60-1101 to -1112 |
| Serving the owner after you file | Sub/supplier must cause a copy of the lien statement to be served personally on any one owner and any party obligated to pay (and recorded equitable-interest holders), or by restricted mail, or by posting on the premises if address cannot be found with reasonable diligence. No fixed service deadline; actual receipt cures defects. On residential real property no foreclosure may proceed unless the recorded equitable-interest holder was served. Prime: 60-1102 has no service requirement for the lien statement itself (only the extension notice is mailed to owner). | K.S.A. 60-1103(c); 60-1102(c) |
| Deadline to sue (enforce the lien) | Foreclosure action within 1 year from filing the lien statement; if a promissory note was attached instead of an itemized statement, within 1 year from the note's maturity. Statute of duration: estoppel does not enlarge it. | K.S.A. 60-1105(a) |
Roofing, restoration and remodeling work on homes often has extra rules. In Kansas:
(1) 60-1103a warning statement for sub/supplier liens on owner-resident improvements and new principal residences (claim > $250), with affidavit attached to lien; owner liable beyond contract price only for payments after receiving warning. (2) 60-1103b notice of intent to perform for new residential structures before deed to good-faith purchaser is recorded; expires 18 months. (3) No notice of extension on <=2-family residential property (60-1102(d), 60-1103(e)). (4) Residential foreclosure requires service on recorded equitable-interest holder (60-1103(c)).
Prime 4 months, sub/supplier 3 months; no notice-of-extension option. For the extension exclusion, 'residential property' = a structure built for use as a residence and not used/intended for more than two families. This test is occupancy-neutral: rented single-family homes and duplexes are residential (no extension) even though the owner does not live there.
A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:
Prime contractors: 4 months after last labor/materials furnished, filed with clerk of district court of county. Non-residential only: 5 months if a notice of extension is filed within the 4 months with the district court and mailed certified AND regular mail to the owner (Judicial Council form). Subcontractors and suppliers: 3 months after last furnishing by the claimant. Non-residential only: 5 months if a notice of extension is filed within the 3 months with the district court clerk, mailed certified and regular mail to the GC or construction manager, and a copy by regular mail to the owner if known.
Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 4 months after your last day of work or materials. Subcontractors and suppliers: 3 months after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.
Residential improvement only (existing structure the owner lives in when claimant first furnishes, incl. attached additions/garages/fences/pools/outbuildings; or new construction on property owned/acquired by an individual that becomes that individual's principal residence; excludes >2-family or commercial use): sub may claim lien only if it mailed the statutory warning statement to any one owner, or holds an owner-signed and dated statement that the GC or claimant gave it. Not required if total claim <= $250. Lien statement must attach the sub/supplier's affidavit that the warning was given. No fixed day deadline, but owner is protected for payments made before receiving the warning, so send at start of work.
New residential property (new structure built for use as a residence; NOT improvements/additions to existing structures): to keep lien rights against a good-faith purchaser for value, claimant must file a notice of intent to perform with the district court clerk in the county before the deed passing title is recorded. Notice expires 18 months after filing unless a lien is filed within that time. No service/mailing requirement. No pre-lien notice of intent to lien exists in Kansas.
(1) 60-1103a warning statement for sub/supplier liens on owner-resident improvements and new principal residences (claim > $250), with affidavit attached to lien; owner liable beyond contract price only for payments after receiving warning. (2) 60-1103b notice of intent to perform for new residential structures before deed to good-faith purchaser is recorded; expires 18 months. (3) No notice of extension on <=2-family residential property (60-1102(d), 60-1103(e)). (4) Residential foreclosure requires service on recorded equitable-interest holder (60-1103(c)).
Foreclosure action within 1 year from filing the lien statement; if a promissory note was attached instead of an itemized statement, within 1 year from the note's maturity. Statute of duration: estoppel does not enlarge it.
See mechanics lien deadlines for all 50 states
Get paid before it gets to a lien.
AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.
Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.
AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.