Hawaii mechanics lien: file within 45 days after completion. Notice rules, home rules and how to file, with the law, in plain English.
Hawaii mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Hawaii mechanics lien deadlines in plain English, with the law behind each rule.

Quick answer: Hawaii mechanics lien deadlines
Application for lien filed in circuit court and served within 45 days after date of completion. If no notice of completion is published, completion is deemed 1 year after actual completion (§ 507-43).
Last updated: November 23, 2026
This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Hawaii statute (Haw. Rev. Stat. §§ 507-41 to -49) in November 2026. Read the current law or ask a Hawaii construction attorney before you file.
"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.
| Rule | What Hawaii requires | Law |
|---|---|---|
| Preliminary notice: prime contractor | None. | HRS §§ 507-42, 507-43 |
| Preliminary notice: subcontractor | None. Siteline's 'Y' is wrong. | HRS §§ 507-42, 507-43 |
| Preliminary notice: supplier | None. Note: on dwellings, a supplier has no lien for materials furnished to an unlicensed contractor or on unreasonable credit (§ 507-49(a), per wave 2). | HRS §§ 507-42, 507-49(a) |
| Notice of intent to lien | None. The lien is sought by filing an Application for Mechanic's and Materialman's Lien, with a Notice of Lien, in circuit court. The lien attaches only when the court enters an Order Directing Lien to Attach after a probable-cause hearing. | HRS § 507-43(a) |
| Lien filing deadline: prime contractor | File the Application and Notice in circuit court within 45 days after the 'date of completion' of the improvement. That date is set by publication of a notice of completion; if no valid notice is published and filed within 1 year after actual completion, completion is deemed 1 year after actual completion or abandonment. | HRS § 507-43(b),(f),(g) |
| Lien filing deadline: subcontractor and supplier | Same as prime: 45 days after the date of completion. | HRS § 507-43(b) |
| Residential projects | Same 45 days. But a prime contractor dealing with a homeowner has no lien at all if it did not comply with § 444-25.5 (see residential_rules). | HRS §§ 507-43(b), 444-25.5 |
| Notice of completion: does it shorten the deadline? | The owner (or the GC, after a written demand that the owner publish and 5 days of owner inaction) publishes a notice of completion or abandonment twice, 7 days apart, in a newspaper of general circulation. The newspaper files the affidavit of publication with the circuit court clerk. The date of completion is when publication is complete, which starts the 45-day clock. If no valid notice is published and filed within 1 year after actual completion, completion is deemed 1 year after actual completion, so the outer deadline is about 1 year + 45 days. In practice the notice sets, rather than shortens, the clock: without it, the clock starts much later. | HRS § 507-43(f),(g) |
| Serving the owner after you file | Serve a copy of the Application and Notice 'in the manner prescribed by law' (like a summons) on the owner, any person with an interest, and the party that contracted for the improvement. If service cannot be made, post on the improvement (wave 2). The return date is 3-10 days after service. For Land Court property, file a certified copy of the attachment order with the assistant registrar within 7 days (wave 2). | HRS § 507-43(a)-(d) |
| Deadline to sue (enforce the lien) | The lien expires 3 months after entry of the Order Directing Lien to Attach unless proceedings to enforce it start within that time. | HRS § 507-43(e) |
Roofing, restoration and remodeling work on homes often has extra rules. In Hawaii:
A licensed contractor contracting with a 'homeowner' (owner or lessee of residential real property, including condo and co-op owners) must: (a) before or at signing, explain verbally and in detail the lien rights of all parties and the homeowner's option to demand bonding, with its approximate cost; and (b) give a written contract containing that information and the § 672E-11 notice of the right to repair construction defects, signed by both parties before any work starts. There is no dollar threshold. Noncompliance is an unfair or deceptive practice, the contract is void, and no § 507-42 lien is available; recovery is limited to quantum meruit. Courts treat the requirements as mandatory and reject substantial compliance (808 Development v. Murakami, 2006; Hiraga v. Baldonado, 2001; Cavalier Construction v. Rice, ICA 2024). Unlicensed GC or sub: no lien for it or for subs under it (§ 507-49(b)).
Same 45 days. But a prime contractor dealing with a homeowner has no lien at all if it did not comply with § 444-25.5 (see residential_rules).
A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:
Prime contractors: File the Application and Notice in circuit court within 45 days after the 'date of completion' of the improvement. That date is set by publication of a notice of completion; if no valid notice is published and filed within 1 year after actual completion, completion is deemed 1 year after actual completion or abandonment. Subcontractors and suppliers: Same as prime: 45 days after the date of completion.
Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 45 days after completion of the project. Subcontractors and suppliers: 45 days after completion of the project. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.
None. Siteline's 'Y' is wrong.
None. The lien is sought by filing an Application for Mechanic's and Materialman's Lien, with a Notice of Lien, in circuit court. The lien attaches only when the court enters an Order Directing Lien to Attach after a probable-cause hearing.
A licensed contractor contracting with a 'homeowner' (owner or lessee of residential real property, including condo and co-op owners) must: (a) before or at signing, explain verbally and in detail the lien rights of all parties and the homeowner's option to demand bonding, with its approximate cost; and (b) give a written contract containing that information and the § 672E-11 notice of the right to repair construction defects, signed by both parties before any work starts. There is no dollar threshold. Noncompliance is an unfair or deceptive practice, the contract is void, and no § 507-42 lien is available; recovery is limited to quantum meruit. Courts treat the requirements as mandatory and reject substantial compliance (808 Development v. Murakami, 2006; Hiraga v. Baldonado, 2001; Cavalier Construction v. Rice, ICA 2024). Unlicensed GC or sub: no lien for it or for subs under it (§ 507-49(b)).
The lien expires 3 months after entry of the Order Directing Lien to Attach unless proceedings to enforce it start within that time.
See mechanics lien deadlines for all 50 states
Get paid before it gets to a lien.
AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.
Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.
AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.