Florida mechanics lien: file within 90 days after last work. Notice rules, home rules and how to file, with the law, in plain English.
Florida mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Florida mechanics lien deadlines in plain English, with the law behind each rule.

Quick answer: Florida mechanics lien deadlines
90 days after final furnishing; if the contract is terminated, the earlier of 90 days after termination or after final furnishing (§ 713.08(5)).
Last updated: November 23, 2026
This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Florida statute (Fla. Stat. §§ 713.001–713.37) in November 2026. Read the current law or ask a Florida construction attorney before you file.
"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.
| Rule | What Florida requires | Law |
|---|---|---|
| Preliminary notice: prime contractor | No notice to owner for the prime (in privity). The direct contract for 1-4 family dwellings over $2,500 must contain the § 713.015 statutory disclosure (12-pt bold caps, front page or separate page signed and dated by owner). Failure does not bar the lien against an owner who was not adversely affected. | Fla. Stat. § 713.015; § 713.06(1)-(2)(a) |
| Preliminary notice: subcontractor | All lienors not in privity with the owner, except laborers, must serve a Notice to Owner before commencing or not later than 45 days after commencing to furnish, and before the owner's final payment after the contractor's final payment affidavit. Sub-subs and suppliers to subs also serve a copy on the contractor; a supplier to a sub-sub serves the subcontractor too. Failure is a complete defense to the lien. | Fla. Stat. § 713.06(2)(a) |
| Preliminary notice: supplier | Same as sub: NTO within 45 days after first furnishing, copy to contractor (and to the subcontractor if supplying a sub-sub). Certified/registered/Global Express Guaranteed mail within 40 days after first furnishing is effective on mailing. | Fla. Stat. §§ 713.06(2)(a), 713.18(2) |
| Notice of intent to lien | No pre-lien notice of intent for construction liens. Prime (contractor in privity) must deliver the contractor's final payment affidavit to the owner at least 5 days before instituting an action to enforce the lien; a contractor in default of this has no lien or right of action against the owner. Statute text sets no 90-day deadline for the affidavit; it must simply precede suit by 5 days (and suit must be within the 1-year lien life). | Fla. Stat. § 713.06(3)(d)1.; A. Alexis Varela, Inc. v. Pagio, No. 5D21-2077 (Fla. 5th DCA May 20, 2022) |
| Lien filing deadline: prime contractor | Record claim of lien not later than 90 days after the lienor's final furnishing; if the contract is terminated/contractor defaults (§ 713.07(4)), not later than 90 days after termination or final furnishing, whichever occurs first. | Fla. Stat. § 713.08(5) |
| Lien filing deadline: subcontractor and supplier | Same as prime: 90 days after that lienor's own final furnishing (earlier of termination date + 90 if contract terminated). | Fla. Stat. § 713.08(5); § 713.01(12) |
| Residential projects | Same 90 days. No residential-specific recording deadline. | Fla. Stat. § 713.08(5) |
| Notice of completion: does it shorten the deadline? | No notice of completion. Notice of Commencement does not change the 45/90-day clocks (NOC gives constructive notice and governs priority/proper payment; void if work not commenced within 90 days of recording; expires 1 year after recording unless stated). Owner's recorded Notice of Contest: lien extinguished automatically unless suit filed within 60 days after clerk's service. Order to show cause: lienor must show cause within 20 days after service of summons or lien is cancelled. | Fla. Stat. §§ 713.13(2),(3),(6); 713.22(2); 713.21(4) |
| Serving the owner after you file | Serve claim of lien on owner per § 713.18 before recording or within 15 days after recording; failure renders lien voidable only to the extent prejudicial. | Fla. Stat. § 713.08(4)(c) |
| Deadline to sue (enforce the lien) | Suit within 1 year after recording the claim of lien (or 1 year after recording an amended claim showing a later final furnishing date). Shortened to 60 days after service of Notice of Contest, or 20 days after service of order-to-show-cause summons. Lis pendens needed for the lien to bind creditors/subsequent purchasers without notice. | Fla. Stat. § 713.22(1)-(2); § 713.21(4) |
Roofing, restoration and remodeling work on homes often has extra rules. In Florida:
§ 713.015 disclosure for 1-4 family direct contracts > $2,500 (prime only; failure bars lien only vs. adversely affected owner). Direct contracts of $2,500 or less are exempt from Part I except § 713.05 (lien right kept; NTO/NOC etc. not required) per wave 3. Unlicensed contractors/subs have no lien (§ 713.02(7)). NOC required before first inspection for direct contracts > $5,000 (§ 713.135, as amended 2023).
Same 90 days. No residential-specific recording deadline.
Example: A subcontractor's last day of work on a Florida job was Monday, March 2, 2026. With a 90-day deadline from the last day of work, count 90 days forward: the lien must be filed by Sunday, May 31, 2026. Don't wait for the last day. Set a reminder a few weeks earlier, and check whether a notice of completion or other rule in the table above changes your clock.
A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:
Prime contractors: Record claim of lien not later than 90 days after the lienor's final furnishing; if the contract is terminated/contractor defaults (§ 713.07(4)), not later than 90 days after termination or final furnishing, whichever occurs first. Subcontractors and suppliers: Same as prime: 90 days after that lienor's own final furnishing (earlier of termination date + 90 if contract terminated).
Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 90 days after your last day of work or materials. Subcontractors and suppliers: 90 days after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.
All lienors not in privity with the owner, except laborers, must serve a Notice to Owner before commencing or not later than 45 days after commencing to furnish, and before the owner's final payment after the contractor's final payment affidavit. Sub-subs and suppliers to subs also serve a copy on the contractor; a supplier to a sub-sub serves the subcontractor too. Failure is a complete defense to the lien.
No pre-lien notice of intent for construction liens. Prime (contractor in privity) must deliver the contractor's final payment affidavit to the owner at least 5 days before instituting an action to enforce the lien; a contractor in default of this has no lien or right of action against the owner. Statute text sets no 90-day deadline for the affidavit; it must simply precede suit by 5 days (and suit must be within the 1-year lien life).
§ 713.015 disclosure for 1-4 family direct contracts > $2,500 (prime only; failure bars lien only vs. adversely affected owner). Direct contracts of $2,500 or less are exempt from Part I except § 713.05 (lien right kept; NTO/NOC etc. not required) per wave 3. Unlicensed contractors/subs have no lien (§ 713.02(7)). NOC required before first inspection for direct contracts > $5,000 (§ 713.135, as amended 2023).
Suit within 1 year after recording the claim of lien (or 1 year after recording an amended claim showing a later final furnishing date). Shortened to 60 days after service of Notice of Contest, or 20 days after service of order-to-show-cause summons. Lis pendens needed for the lien to bind creditors/subsequent purchasers without notice.
See mechanics lien deadlines for all 50 states
Get paid before it gets to a lien.
AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.
Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.
AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.