Mechanics lien deadlines by state decide whether you can use a lien to get paid at all. Every state sets its own clock for notices, for filing the lien and for suing to enforce it. Miss one and the lien can be thrown out. This page lists the mechanics lien deadlines in all 50 states and Washington, DC, in plain English, with a full guide for each state.

Mechanics lien deadlines by state

This is not legal advice. Rules differ by state and change over time. We checked each deadline against the text of the state statute in November 2026. These rules are for private projects; public projects use bond claims. Check the current statute or ask a construction attorney before you file.

Free tool: mechanics lien deadline calculator

Pick your state, your role and the type of job. Enter your first and last day of work. See the last day to send each notice, file your lien and sue.

Open the lien deadline calculator

What is a construction lien?

A construction lien, also called a mechanics lien, is a legal claim on a property for unpaid construction work or materials. If the owner does not pay, the lien can block a sale or a new loan until you are paid. In the end, a court can order the property sold to pay you.

Most states let these people file a construction lien:

A lien only works if you follow your state's steps and deadlines. Miss one and the lien can be thrown out. That is why every state guide below shows each deadline, and our lien deadline calculator turns them into real dates for your job.

How mechanics lien deadlines work

Most states follow the same four steps. The names and days change from state to state:

  1. Preliminary notice: a heads-up to the owner early in the job, often required for subs and suppliers.
  2. Notice of intent to lien: a warning before you file, required in some states. See how to send a notice of intent to lien.
  3. File the lien: record the lien with the county by the deadline, usually counted from your last day of work.
  4. Enforce it: sue to foreclose the lien before it expires, or release it once you are paid.

Most deadlines count from your last day of work or materials, but some count from the end of the whole project or from a notice the owner records. Write down your first and last day on every job.

Watch: notice of intent to lien in 3 minutes

Mechanics lien deadlines in all 50 states and DC

Click a state for notices, step-by-step instructions, an example and FAQs.

StateFile the lien: prime contractorFile the lien: subcontractorSue to enforce
Alabama6 months after your last day of work or materials4 months after your last day of work or materials6 months after the debt comes due
Alaska120 days after completion of the project120 days after completion of the project6 months after the lien is filed
Arizona120 days after completion of the project120 days after completion of the project6 months after the lien is filed
Arkansas120 days after your last day of work or materials120 days after your last day of work or materials15 months after the lien is filed
California90 days after completion of the project90 days after completion of the project90 days after the lien is filed
Colorado4 months after your last day of work or materials4 months after your last day of work or materials6 months after your last work or completion
Connecticut90 days after your last day of work or materials90 days after your last day of work or materials1 year after the lien is filed
Delaware180 days after completion of the project120 days after your last day of work or materialsThere is no separate enforcement deadline. The statement of claim, labeled as a complaint, starts the scire facias action (§ 2712(a)). Default judgment is avail
District of Columbia90 days after completion of the project90 days after completion of the project180 days after the lien is filed
Florida90 days after your last day of work or materials90 days after your last day of work or materials1 year after the lien is filed
Georgia90 days after your last day of work or materials90 days after your last day of work or materials365 days after the lien is filed
Hawaii45 days after completion of the project45 days after completion of the project3 months after a court order
Idaho90 days after your last day of work or materials90 days after your last day of work or materials6 months after the lien is filed
Illinois4 months after completion of the project4 months after your last day of work or materials2 years after completion of the project
Indiana90 days after your last day of work or materials90 days after your last day of work or materials1 year after the lien is filed
Iowa90 days after your last day of work or materials90 days after your last day of work or materials2 years after the 90-day filing period ends
Kansas4 months after your last day of work or materials3 months after your last day of work or materials1 year after the lien is filed
Kentucky6 months after your last day of work or materials6 months after your last day of work or materials12 months after the lien is filed
Louisiana60 days after completion of the project60 days after completion of the project1 year after the lien is filed
MaineA claimant in direct contract with the owner need not record the 3253 statement; the lien is preserved by filing suit within 120 days. However, a bona fide purc90 days after your last day of work or materials120 days after your last day of work or materials
Maryland180 days after your last day of work or materials180 days after your last day of work or materials1 year after the lien is filed
Massachusetts90 days after your last day of work or materials90 days after your last day of work or materials90 days after the statement is filed
Michigan90 days after your last day of work or materials90 days after your last day of work or materials1 year after the lien is filed
Minnesota120 days after your last day of work or materials120 days after your last day of work or materials1 year after your last day of work or materials
Mississippi90 days after your last day of work or materials90 days after your last day of work or materials180 days after the lien is filed
Missouri6 months after your last day of work or materials6 months after your last day of work or materials6 months after the lien is filed
Montana90 days after your last day of work or materials90 days after your last day of work or materials2 years after the lien is filed
Nebraska120 days after your last day of work or materials120 days after your last day of work or materials2 years after the lien is filed
Nevada90 days after completion of the project90 days after completion of the project6 months after the lien is filed
New Hampshire120 days after your last day of work or materials120 days after your last day of work or materials120 days after your last day of work or materials
New Jersey90 days after your last day of work or materials90 days after your last day of work or materials1 year after your last day of work or materials
New Mexico120 days after completion of your contract90 days after completion of the project2 years after the lien is filed
New York8 months after completion or your last day of work8 months after completion or your last day of work1 year after the lien is filed
North Carolina120 days after your last day of work or materials120 days after your last day of work or materials180 days after your last day of work or materials
North Dakota90 days after your last day of work or materials90 days after your last day of work or materials3 years after the lien is filed
Ohio75 days after your last day of work or materials75 days after your last day of work or materials6 years after the lien is filed
Oklahoma4 months after your last day of work or materials90 days after your last day of work or materials1 year after the lien is filed
Oregon75 days after the earlier of your last day of work or project completion75 days after the earlier of your last day of work or project completion120 days after the lien is filed
Pennsylvania6 months after your last day of work or materials6 months after your last day of work or materials2 years after the lien is filed
Rhode Island200 days after your last day of work or materials200 days after your last day of work or materials40 days after the lien is filed
South Carolina90 days after your last day of work or materials90 days after your last day of work or materials6 months after your last day of work or materials
South Dakota120 days after your last day of work or materials120 days after your last day of work or materials6 years after your last day of work or materials
Tennessee90 days after completion of the project90 days after completion of the project90 days after the owner sends a notice
Texas15th day of the 4th month after the month your work was completed15th day of the 4th month after the month of your last work or materials1 year after the last day you could have filed the lien
Utah180 days after final completion of the project180 days after final completion of the project180 days after the lien is filed
Vermont180 days after the date payment was due180 days after the date payment was due180 days after the lien is filed
Virginia90 days after the month of your last work or materials90 days after the month of your last work or materials6 months after the lien is filed
Washington90 days after your last day of work or materials90 days after your last day of work or materials8 months after the lien is filed
West Virginia100 days after completion of your contract100 days after your last day of work or materials6 months after the lien is filed
Wisconsin6 months after your last day of work or materials6 months after your last day of work or materials2 years after the lien is filed
Wyoming150 days after the earlier of your last day of work or project completion120 days after the earlier of your last day of work or project completion180 days after the lien is filed

Notice deadlines by role: prime, sub and supplier

Before you can file a lien, many states make you send notices first. This table shows the preliminary notice for each role and the notice of intent to lien for subcontractors, on a commercial job. "Only in some cases" means it depends on the job size, the type of job, or whether the owner filed a notice. Read the state guide for the details.

StatePreliminary notice: primePreliminary notice: subPreliminary notice: supplierNotice of intent: subCalculator
AlabamaNot requiredOptional: Before your first day of work or delivery.Optional: Before your first day of work or delivery.Before you file the lien.Get my dates
AlaskaOptional: Notice of right to lien may be given/recorded any time after contracting.Optional: Notice of right to lien may be given/recorded any time after contracting.Optional: Notice of right to lien may be given/recorded any time after contracting.Not requiredGet my dates
ArizonaWithin 20 days after your first day of work or delivery.Within 20 days after your first day of work or delivery.Within 20 days after your first day of work or delivery.Not requiredGet my dates
ArkansasNot requiredWithin 75 days after your first day of work or delivery.Within 75 days after your first day of work or delivery.At least 10 days before you file the lien.Get my dates
CaliforniaOnly in some cases: Within 20 days after your first day of work or delivery.Within 20 days after your first day of work or delivery.Within 20 days after your first day of work or delivery.Not requiredGet my dates
ColoradoNot requiredNot requiredNot requiredAt least 10 days before you file the lien.Get my dates
ConnecticutNot requiredNot requiredNot requiredOnly in some cases: Within 90 days after your last day of work or delivery.Get my dates
DelawareNot requiredNot requiredNot requiredNot requiredGet my dates
District of ColumbiaNot requiredNot requiredNot requiredNot requiredGet my dates
FloridaNot requiredWithin 45 days after your first day of work or delivery.Within 45 days after your first day of work or delivery.Not requiredGet my dates
GeorgiaOptional: Optional Preliminary Notice of Lien Rights: file within 30 days after furnishing, and send a copy within 7 days.Optional: Optional Preliminary Notice of Lien Rights: file within 30 days after furnishing, and send a copy within 7 days.Only in some cases: Within 30 days after the notice of commencement is recorded.Not requiredGet my dates
HawaiiNot requiredNot requiredNot requiredNot requiredGet my dates
IdahoNot requiredNot requiredNot requiredNot requiredGet my dates
IllinoisNot requiredWithin 90 days after your last day of work or delivery.Within 90 days after your last day of work or delivery.Not requiredGet my dates
IndianaNot requiredNot requiredNot requiredNot requiredGet my dates
IowaNot requiredNot requiredNot requiredNot requiredGet my dates
KansasNot requiredNot requiredNot requiredNot requiredGet my dates
KentuckyNot requiredNot requiredNot requiredWithin 75 days after your last day of work or delivery.Get my dates
LouisianaNot requiredOnly in some cases: Within 30 days after the contract is signed.Only in some cases: Send a notice of nonpayment to the owner and the contractor within 75 days after the end of the month you delivered.Not requiredGet my dates
MaineNot requiredOptional: Send as early as possible. It protects recovery only against owner payments to the prime made AFTER the owner receives it.Optional: Send as early as possible. It protects recovery only against owner payments to the prime made AFTER the owner receives it.Not requiredGet my dates
MarylandNot requiredNot requiredNot requiredWithin 120 days after your last day of work or delivery.Get my dates
MassachusettsNot requiredNot requiredOptional: Within 30 days after your first day of work or delivery.Not requiredGet my dates
MichiganNot requiredWithin 20 days after your first day of work or delivery.Within 20 days after your first day of work or delivery.Not requiredGet my dates
MinnesotaOnly in some cases: Within 10 days after the contract is signed.Only in some cases: Within 45 days after your first day of work or delivery.Only in some cases: Within 45 days after your first day of work or delivery.Not requiredGet my dates
MississippiNot requiredNot requiredOnly in some cases: Within 30 days after your first day of work or delivery.Not requiredGet my dates
MissouriGive the 429.012 NOTICE TO OWNER (10-pt bold) at contract signing, at material delivery, at work start, or with the first invoice.Not requiredNot requiredAt least 10 days before you file the lien.Get my dates
MontanaNot requiredOnly in some cases: Within 20 days after your first day of work or delivery.Only in some cases: Within 20 days after your first day of work or delivery.Not requiredGet my dates
NebraskaNot requiredNot requiredNot requiredNot requiredGet my dates
NevadaNot requiredWithin 31 days after your first day of work or delivery.Within 31 days after your first day of work or delivery.Not requiredGet my dates
New HampshireNot requiredBefore your first day of work or delivery.Before your first day of work or delivery.Not requiredGet my dates
New JerseyNot requiredNot requiredNot requiredNot requiredGet my dates
New MexicoNot requiredNot requiredNot requiredNot requiredGet my dates
New YorkNot requiredNot requiredNot requiredNot requiredGet my dates
North CarolinaOnly in some cases: Within 15 days after your first day of work or delivery.Only in some cases: Within 15 days after your first day of work or delivery.Only in some cases: Within 15 days after your first day of work or delivery.Not requiredGet my dates
North DakotaNot requiredNot requiredNot requiredAt least 10 days before the lien is recorded.Get my dates
OhioNot requiredOnly in some cases: Within 21 days after your first day of work or delivery.Only in some cases: Within 21 days after your first day of work or delivery.Not requiredGet my dates
OklahomaNot requiredOnly in some cases: Within 75 days after your last day of work or delivery.Only in some cases: Within 75 days after your last day of work or delivery.Not requiredGet my dates
OregonNot requiredOptional: No NRL is required on a commercial improvement for labor-only providers or labor-and-material (installing) subs.Within 8 business days after your first day of work or delivery.Not requiredGet my dates
PennsylvaniaNot requiredOnly in some cases: Within 45 days after your first day of work or delivery.Only in some cases: Within 45 days after your first day of work or delivery.At least 30 days before you file the lien.Get my dates
Rhode IslandBefore your first day of work or delivery.Not requiredNot requiredNot requiredGet my dates
South CarolinaNot requiredOnly in some cases: Notify owner in writing of the labor/materials furnished and value. No deadline.Only in some cases: Notify owner in writing of the labor/materials furnished and value. No deadline.Not requiredGet my dates
South DakotaNot requiredNot requiredOnly in some cases: Within 60 days after your last day of work or delivery.Not requiredGet my dates
TennesseeNot requiredOnly in some cases: Serve a notice of nonpayment within 90 days of the last day of EACH month in which unpaid work or materials were furnished.Only in some cases: Serve a notice of nonpayment within 90 days of the last day of EACH month in which unpaid work or materials were furnished.Not requiredGet my dates
TexasNot requiredBy the 15th day of the 3rd month after the month of the unpaid work.By the 15th day of the 3rd month after the month of the unpaid work.Not requiredGet my dates
UtahWithin 20 days after your first day of work or delivery.Within 20 days after your first day of work or delivery.Within 20 days after your first day of work or delivery.Not requiredGet my dates
VermontNot requiredGive written notice to the owner (or the owner's agent in charge) that a lien will be claimed, stating the payment due date if known.Give written notice to the owner (or the owner's agent in charge) that a lien will be claimed, stating the payment due date if known.Not requiredGet my dates
VirginiaNot requiredNot requiredNot requiredNot requiredGet my dates
WashingtonNot requiredOnly in some cases: Within 60 days after your first day of work or delivery.Only in some cases: Within 60 days after your first day of work or delivery.Not requiredGet my dates
West VirginiaNot requiredOptional: Optional pre-work notice to the owner.Optional: Optional pre-work notice to the owner.Not requiredGet my dates
WisconsinNot requiredNot requiredNot requiredAt least 30 days before you file the lien.Get my dates
WyomingSend before receiving ANY payment from the owner, including advances. Trigger 'other' = the first owner payment or advance.Within 30 days after your first day of work or delivery.Within 30 days after your first day of work or delivery.At least 20 days before you file the lien.Get my dates

Want the whole picture on notices? Read our guide to preliminary notice rules by state.

Before you file: get paid first

Tools and related guides

Official law and forms: each state guide links to the state lien law. Many states print the lien form or notice wording right in the law, so use the state form if there is one.

Frequently asked questions

Is a construction lien the same as a mechanics lien?

Yes. They are two names for the same thing. Some states, like Michigan, Florida and New Jersey, call it a construction lien. Others call it a mechanics lien or a materialman's lien. The rules work the same way.

How long do you have to file a mechanics lien?

It depends on the state and your role. Most states give you 60 to 120 days after your last day of work, or after the project is finished. A few give longer, like New York at 8 months. Find your state in the table above, or use our lien deadline calculator.

Can a contractor put a lien on a house?

Yes, in every state. But homes often have extra rules, like a notice to the homeowner before work starts or shorter deadlines. Some states protect homeowners who already paid the prime contractor. Read your state guide for the home rules.

Do I need a lawyer to file a mechanics lien?

Not always. Many contractors file their own liens using the state form. But the details matter, and a mistake can make the lien invalid. For a large claim or a lawsuit to enforce the lien, talk to a construction lawyer.

Which state has the shortest mechanics lien deadline?

Deadlines vary a lot. Some states give as little as 60 to 90 days after your last work, while others allow several months. Check your state in the table above, and file early rather than near the deadline. Check your state's page above, and file early rather than near the deadline.

When does the mechanics lien deadline start?

In most states it starts on your last day of work or materials on the job. Some states count from completion of the whole project or from a notice of completion the owner records. Your state's page explains which event starts your clock.

Do subcontractors have different lien deadlines?

Often, yes. Subcontractors and suppliers without a direct contract with the owner usually have to send a preliminary notice, and some states give them a different filing deadline. The table shows both.

What happens if I miss the lien deadline?

You usually lose the right to file a lien for that job. You may still be able to sue on the contract, so talk to a construction attorney. This is not legal advice.

Get paid before it gets to a lien.

AR Workflow works with QuickBooks and follows up on every invoice for you. Bring one overdue invoice to a demo and see what we would send, and when.

Book a demo

Sam Frenzley
About the authorSam Frenzley

Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.

You did the work. Let AI chase the money.

AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.

  • Keep QuickBooks
  • Start with one invoice
  • Stay in control