AR Workflow Blog/Construction

Construction Payment Schedule: Progress Payments Guide

Progress payment basics: what a construction payment schedule includes, milestone and pay app examples, retainage, and how to get paid on time.

Sam Frenzley
Founder, AR Workflow
Updated 17 min read

A progress payment is money a contractor collects as the work moves forward, instead of waiting for the whole job to be done. On anything bigger than a service call, progress payments are what keep payroll, subs and suppliers paid while the project is still open. The construction payment schedule in your contract decides when each progress payment is due, how much it is, and what you have to hand over to get it.

Most payment fights on a job come back to a schedule that was vague, missing, or ignored. I ran three restoration companies for more than 14 years, and the jobs that stayed on time financially had a payment schedule everyone understood before the first day of work. This guide explains how progress payments work, the common types of construction payment schedules, two filled-in examples (a residential remodel and a commercial pay app with retainage), the rules that apply to prompt payment, the methods of payment in construction, and how to keep each progress payment from sliding past its due date.

Watch: progress billing in 3 minutes

In this video:

Read the full video transcript

Progress billing lets contractors get paid as the work gets done, instead of waiting until the end of the job. If you've ever floated payroll and materials for months on a big project, this video is for you. You'll learn how to set up a payment schedule, use a schedule of values, plan for retainage, and get each payment on time.

Here's the idea. On a big job, you split the contract into payments tied to progress. Instead of one invoice at the end, you send several along the way. The money comes in closer to when you spend it. That keeps your cash flow steady, and it lowers your risk if the customer stops paying.

Step one: agree on the payment schedule before work starts. Put it in the contract. Take a sixty thousand dollar addition. Ten percent deposit, thirty percent at framing, thirty percent at rough in, twenty percent at drywall, and ten percent at the final walkthrough. Everyone knows what's due, and when.

Step two: on bigger jobs, use a schedule of values. It lists each part of the work and what it's worth. Each billing period, you bill the percent complete on each line. If framing is worth eighteen thousand dollars and it's half done, you bill nine thousand.

Step three: tie each payment to something anyone can see. 'Roof dried in' is clear. 'Most of the work' is not. Clear milestones stop arguments before they start. Take photos when you hit each one, and send them with the invoice.

Step four: plan for retainage. On many commercial jobs, the customer holds back five or ten percent of each payment until the end. Show it on every invoice, track it on its own line, and bill for it the day the job is done. Don't let it sit forgotten for months.

Step five: bill the day you hit the milestone, not at the end of the month. Send the invoice with photos, and lien waivers if they're needed. Then follow up. A payment that's three weeks late is three weeks of payroll you're covering yourself.

Let's recap. One, put the payment schedule in the contract. Two, use a schedule of values on bigger jobs. Three, tie each payment to a clear milestone. Four, track retainage on its own line. Five, bill the day you hit the milestone, and follow up. Do you bill in stages today? Tell us in the comments.

If keeping track of every payment is a headache, that's what we built AR Workflow for. It works with QuickBooks, follows up on each progress invoice, and keeps retainage from slipping through the cracks. Over 3,200 users get paid about 21 days faster. Bring one overdue invoice and book a demo. The link is below.

KEY TAKEAWAYS

What is a progress payment?

A progress payment is a partial payment on a construction contract, made as the work progresses. Instead of one payment at the end, the contract price is split into pieces, and each piece is billed when a set condition is met: a stage of work is finished, a percentage of the work is complete, or a billing period (usually a month) ends.

Progress payments exist because construction is expensive to carry. A contractor might pay for labor, materials, equipment and subs for weeks before the owner sees a finished product. Progress billing spreads that cost so neither side carries all the risk. The owner pays only for work in place, and the contractor does not finance the whole project out of pocket.

You will also hear progress payments called progress billing, interim payments, draws (common on bank-financed jobs) or pay apps (short for payment applications on commercial work).

What's a payment schedule in construction?

A payment schedule is the part of the contract that says when each payment is due and how much it will be. In construction, a good payment schedule answers five questions:

If your contract cannot answer all five, the customer will fill in the blanks for you, and their version will usually be slower than yours. For wording on terms and due dates, see our guide to contractor payment terms.

Types of construction payment schedules

There is no single right schedule. The type of job, the customer and how the job is financed decide which one fits.

Schedule typeHow progress payments are triggeredCommon on
Deposit plus milestonesA deposit at signing, then fixed amounts when named stages are finished (demo, rough-in, drywall, final)Residential remodels, additions, roofing, smaller commercial jobs
Percent complete (schedule of values)The contract is broken into line items, and each period you bill the percentage of each line that is completeCommercial and public work, larger residential builds
Monthly pay applicationA pay app is submitted each month for work completed and materials stored that period, usually on AIA G702 and G703 or similar formsCommercial work for owners and GCs
Bank draw scheduleThe lender releases funds after an inspector confirms each stageNew homes and renovations financed by a construction loan
Time and materialsBilled weekly or every two weeks for actual hours and materials, often with a not-to-exceed capService work, repairs, emergency and restoration jobs
Unit priceBilled by measured quantities installed (linear feet, cubic yards, squares)Site work, paving, utilities, some roofing

Tip: Front-loading (pricing early line items high so you collect more up front) is a common temptation on a schedule of values. Owners, GCs and lenders look for it, and it can get a pay app rejected. Price each line at its real value.

Progress payment schedule examples

Example 1: residential remodel, deposit plus milestones

Here is a progress payment schedule for an $80,000 kitchen and bath remodel. The company, numbers and stages are made up for illustration.

PaymentTrigger%Amount
DepositContract signed10%$8,000
Progress payment 1Demo complete and framing changes done20%$16,000
Progress payment 2Rough plumbing and electrical inspections passed25%$20,000
Progress payment 3Drywall finished and cabinets set25%$20,000
Progress payment 4Substantial completion (counters, fixtures, trim)15%$12,000
Final paymentPunch list complete and final walkthrough signed5%$4,000
Total100%$80,000

Two things make this schedule work. Each trigger is something both sides can see (an inspection card, a signed walkthrough), and the last payment is small enough that the homeowner does not hold the whole job hostage over a punch list item. Deposit rules vary by state. California, for example, limits the down payment on home improvement contracts under Business and Professions Code section 7159, so check your own state before you set a deposit percentage.

Example 2: commercial pay application with retainage

On commercial work, progress payments usually run through a monthly pay app. Here is the math for the third monthly pay app on a $600,000 contract with 10% retainage. Again, the numbers are made up.

Line (as on a G702-style summary)Amount
Original contract sum$600,000
Net change by approved change orders$0
Work completed to date (from the schedule of values)$270,000
Materials presently stored$15,000
Total completed and stored to date$285,000
Retainage (10%)($28,500)
Total earned less retainage$256,500
Less previous certificates for payment($171,000)
Current payment due$85,500
Balance to finish, including retainage$343,500

If the forms and line items are new to you, our pay application guide to AIA G702 and G703 walks through each line and the schedule of values behind it.

Bring one overdue invoice.

We will show you how that progress bill would be followed up, and what your customer would see when they pay.

Book a demo

Example: progress billing a $60,000 addition

Here is one job billed in stages. The numbers are an example.

Example: a $60,000 home addition

On a commercial job with 10% retainage, each progress payment would be paid at 90%, and the held amount (here up to $6,000) is tracked on its own line and billed at completion.

Instead of carrying $60,000 of payroll and materials until the end, the contractor is never more than one stage behind.

Related guides: retainage and construction cash flow.

How progress payments work on commercial jobs

Commercial progress payments add a few moving parts that residential jobs usually skip:

Construction billing: how to bill each progress payment

Construction billing goes wrong in small ways that add up: a missing waiver, a math error, a change order nobody signed. Use the same checklist for every progress bill:

1Bill the day the trigger is met. Not at the end of the week. Every day between the milestone and the invoice is a day added to how long you wait.
2Reference the contract. Name the milestone or billing period, the contract date and the payment schedule section it comes from.
3Show the contract math. Original contract, approved changes, completed to date, retainage, previous payments and amount due now. Our contractor invoice template has a contract summary block you can copy.
4Bill change orders separately. Only signed change orders, each on its own line, on the next progress bill after approval.
5Attach what the payer needs. Photos, inspection cards, lien waivers, stored materials invoices, certificates of insurance.
6Send it to the person who pays. The PM who approves your percentages is often not the AP clerk who releases the money. Send it to both.
7Put a payment link and exact due date on it. "Due November 20, 2026" gets paid sooner than "Net 15."

If you are still building pay apps and progress invoices in spreadsheets, our roundup of construction billing software covers tools that handle schedules of values, retainage and AIA forms. For setting up progress invoicing in QuickBooks Online, see our QuickBooks for contractors guide.

Prompt payment rules and progress payments

Prompt payment laws set deadlines for paying contractors and subcontractors and may add interest when payments are late. They exist at the federal level and in many states, but the details are very different from place to place. A few facts to know:

Rules vary by state and change over time. Check your state's statute, read your contract, and talk to a construction attorney before you rely on a prompt payment deadline or interest claim. This is general information, not legal advice.

Methods of payment in construction

Once a progress payment is approved, how the money moves matters too. Here are the common methods of payment in construction and where each one fits.

MethodHow it worksWatch out for
CheckStill common for owners, GCs and insurance carriersMail time, deposit holds and "it's in the mail" delays
ACH bank transferDirect bank-to-bank payment, usually settling in one to two business daysConfirm any change to bank details by phone to avoid fraud
Credit or debit cardFast and easy for homeowners, often through a payment linkProcessing fees, and state and card network rules on surcharges
Wire transferSame-day, used for large commercial payments and closingsHard to reverse; verify instructions by phone every time
Joint checkMade out to both a sub or supplier and the contractor above them, so both must endorseRead any joint check agreement carefully; it can affect lien rights in some states
Construction loan drawLender releases funds after an inspection confirms the stageInspection scheduling and title updates add days
Payment planA homeowner pays a balance over set installments, by card or ACHPut it in writing with dates and amounts

For homeowner progress payments, a payment link with card and ACH options gets money in faster than waiting for a check. See how card, ACH and payment plans for contractors work. On insurance jobs, carriers pay through their own claim process: send adjusters documentation, never a payment link.

How to get progress payments paid on time

A clean schedule and a clean bill solve most problems. The rest is follow-up. Put every progress bill on the same schedule:

Day 0Send the progress bill with backup and a payment link; confirm the right person received it
Due - 3Friendly reminder with the due date and the amount
Due + 3Polite past-due email and text; ask if anything is holding it up
Due + 7Phone call or voicemail to the payer, and to the PM on commercial jobs
Due + 15Firm notice with a pay-by date; on residential jobs, offer a payment plan
Due + 30Owner-to-owner call. Check your state's lien and notice deadlines now, not later

If you need wording for each step, copy our construction collection email templates, which include follow-ups for late pay apps and retainage release. For the bigger picture, see how to reduce late payments in construction.

Let the follow-up run itself

Keeping that schedule going on every open progress bill is the part most contractors drop. AR Workflow is receivables follow-up that runs on top of QuickBooks Online. It syncs your open invoices, puts each one on a follow-up schedule, and sends emails, two-way texts and ringless voicemails from a dedicated number with a card or ACH payment link. Customers can pay in full or on a payment plan, payments post back to QuickBooks, and follow-up stops when the invoice is paid. It is not accounting or pay app software; it is the follow-up that gets your progress payments collected.

Not sure what a term means? See our construction payment terms glossary: 41 terms in plain English.

Frequently asked questions

What is a progress payment in construction?

A progress payment is a partial payment made during a construction project as work is completed. It is triggered by a milestone, a percentage of completion or the end of a billing period, as set out in the contract's payment schedule.

What's a payment schedule?

A payment schedule is the section of a contract that lists each payment, when it is due, how much it is and what triggers it. In construction it usually includes a deposit, progress payments and a final payment, plus any retainage and when it is released.

How are progress payments calculated?

On milestone schedules, each payment is a set amount or percentage of the contract. On percent-complete schedules, you bill the value of work completed and materials stored to date, subtract retainage and subtract what has already been paid. The difference is the progress payment due now.

What is the difference between a progress payment and a final payment?

Progress payments are made during the job for work completed so far. The final payment is made when the job is complete and accepted, and on commercial work it usually includes the release of retainage, along with final lien waivers and closeout documents.

Is retainage part of a progress payment?

Retainage is a portion of each progress payment that the owner or GC holds back until the job is substantially or fully complete. It is still owed to you, but it is paid later. The rate and release terms are set by the contract, and some states limit them.

How do you set up a progress billing schedule?

Put it in the contract before work starts: list each payment, the milestone that triggers it and the amount or percent. A common split is a deposit, payments at major milestones like framing and rough-in, and a final payment at the walkthrough.

What is a schedule of values?

A schedule of values lists each part of the job and what it is worth. Each billing period you bill the percent complete on each line, which is how most commercial progress billing works.

How does retainage work with progress billing?

On many commercial jobs the customer holds back 5 to 10% of each progress payment until the job is done. Show it on every invoice, track it on its own line, and bill for it as soon as the job is complete.

What is the difference between progress billing and a draw schedule?

They work together. A draw schedule is the list of payments and when each one is due, often used on bigger jobs with lenders or owners. Progress billing is sending each invoice on that schedule as you hit the next step of the job.

Related reading

More short videos for contractors

Each guide below has a 3-minute video at the top.

See all contractor videos in one place

Your invoice, not a feature tour.

Bring one overdue invoice to a demo and see what AR Workflow would send, when, and how your customer would pay.

Book a demo

This article is general information, not legal advice. Prompt payment, deposit, retainage, lien waiver and pay-when-paid rules vary by state; talk to a construction attorney about your situation.

Sam Frenzley
About the authorSam Frenzley

Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.

You did the work. Let AI chase the money.

AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.

  • Keep QuickBooks
  • Start with one invoice
  • Stay in control