Nevada mechanics lien laws in plain English: deadlines for primes, subs and suppliers, notice rules, home rules and how to file. Free deadline calculator.
Nevada mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Nevada mechanics lien deadlines in plain English, with the law behind each rule.

Quick answer: Nevada mechanics lien deadlines
90 days after the latest of completion, last furnishing, or last work; 40 days after recorded notice of completion (§ 108.226).
Last updated: November 23, 2026
This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Nevada statute (Nev. Rev. Stat. §§ 108.221–.246) in November 2026. Read the current law or ask a Nevada construction attorney before you file.
"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.
| Rule | What Nevada requires | Law |
|---|---|---|
| Preliminary notice: prime contractor | none. Prime contractors, anyone else who contracts directly with the owner, and suppliers who sell directly to the owner give no Notice of Right to Lien. | NRS 108.245(5) |
| Preliminary notice: subcontractor | Required for every non-privity claimant except labor-only claimants. Deliver the Notice of Right to Lien to the owner in person or by certified mail, with an information-only copy to the prime contractor. It may be given at any time after first furnishing, but the lien covers only what was furnished in the 31 days before the notice plus everything after. App: set the target as first furnishing + 31 days, which is a look-back, not a hard deadline. Without the notice, a lien for anything other than labor cannot be perfected. | NRS 108.245(1),(3),(6) |
| Preliminary notice: supplier | Required for suppliers to a prime or a sub. Exempt when selling directly to the owner. | NRS 108.245(1),(5) |
| Notice of intent to lien | On construction, alteration or repair of single-family or multifamily residences (apartment houses included), every claimant except laborers must serve a 15-day notice of intent to lien on both the owner and the reputed prime contractor before recording. A prime serves only the owner. Service is by personal delivery or certified mail. Without the notice, a lien for materials or equipment (anything except labor) cannot be perfected. Nonresidential projects are exempt (108.226(7)). The notice must be served at least 15 days before recording. | NRS 108.226(6),(7) |
| Lien filing deadline: prime contractor | Record the notice of lien within 90 days after the LATEST of (i) completion of the work of improvement, (ii) the claimant's last delivery of materials or equipment, or (iii) the claimant's last performance of work. Or, if earlier, within 40 days after a valid notice of completion is recorded and served under 108.228. | NRS 108.226(1)(a),(b) |
| Lien filing deadline: subcontractor and supplier | Same as prime: 90 days after the latest of completion, last delivery, or last work; 40 days after a valid notice of completion that was recorded and served on this claimant. | NRS 108.226(1) |
| Residential projects | 105 days after the latest of completion, last delivery, or last work, or 55 days after a valid, served NOC. This applies only if the 15-day notice of intent is served, and it must be served at least 15 days before recording. In practice the notice must go out by day 90 (or day 40 after the NOC) to leave the 15-day gap. Treat the 55-day figure as the textual reading. It is not confirmed by case law, so the app should urge recording by day 40 after the NOC where possible. | NRS 108.226(1),(6) |
| Notice of completion: does it shorten the deadline? | The owner may record a verified notice of completion after completion. The statute sets no recording deadline. Within 10 days after recording, the owner must mail copies by certified mail to each prime contractor and to each potential claimant who sent a Notice of Right to Lien or asked for the NOC. The deadline then becomes 40 days after recording (55 on residential jobs with the notice of intent), but only for claimants who were properly sent a copy. For anyone owed a copy who was not sent one, the NOC is ineffective and the 90-day rule applies. | NRS 108.228(1),(3)-(5); 108.226(1)(b) |
| Serving the owner after you file | Serve a copy of the recorded notice of lien on the owner within 30 days after recording. Methods: personal delivery to the owner or registered agent; certified mail, return receipt requested; or, if no address can be found, posting on the property plus delivery to a resident plus mail to specified addresses. Serving one of several owners is enough. | NRS 108.227(1) |
| Deadline to sue (enforce the lien) | File the foreclosure complaint no earlier than 30 days after recording and no later than 6 months after recording. The 6 months can be extended only by a written, acknowledged agreement signed by the claimant and the persons in interest. The agreement must be recorded within the 6-month period, the extension cannot run past 1 year after the lien was recorded, and no extension is allowed if it would delay other outstanding liens. At filing: record a lis pendens and publish notice of foreclosure once a week for 3 successive weeks (108.239). | NRS 108.233(1)-(3); 108.244; 108.239(2) |
Here is each deadline for prime contractors, subcontractors and suppliers on a commercial job. Homes have some different rules in Nevada. See the home rules below. "Prime" means you have a contract with the owner. Some deadlines change if the owner records a notice, so check the full rules below.
| Step | Prime contractor | Subcontractor | Supplier |
|---|---|---|---|
| Preliminary notice | Not required | Within 31 days after your first day of work or delivery. | Within 31 days after your first day of work or delivery. |
| Notice of intent to lien | Not required | Not required | Not required |
| File the lien | Within 90 days after the project is finished. | Within 90 days after the project is finished. | Within 90 days after the project is finished. |
| Serve a copy of the lien | Within 30 days after the lien is recorded. | Within 30 days after the lien is recorded. | Within 30 days after the lien is recorded. |
| Sue to enforce the lien | Within 6 months after the lien is recorded. | Within 6 months after the lien is recorded. | Within 6 months after the lien is recorded. |
Get your exact Nevada dates
Enter your first and last day of work. Our free calculator shows the last day to send each notice, file your lien and sue.
Roofing, restoration and remodeling work on homes often has extra rules. In Nevada:
On residential jobs (single-family or multifamily, apartments included, whether or not owner-occupied), every claimant except laborers, primes included, must serve the 15-day notice of intent on the owner and the reputed prime at least 15 days before recording. It extends the recording deadline by 15 days (105 days, or 55 after the NOC). Without it, the non-labor portion of the lien cannot be perfected. The NRL rules are the same as on commercial jobs. There is no separate owner-occupied track in 108.226/.245.
105 days after the latest of completion, last delivery, or last work, or 55 days after a valid, served NOC. This applies only if the 15-day notice of intent is served, and it must be served at least 15 days before recording. In practice the notice must go out by day 90 (or day 40 after the NOC) to leave the 15-day gap. Treat the 55-day figure as the textual reading. It is not confirmed by case law, so the app should urge recording by day 40 after the NOC where possible.
A prompt payment act sets how fast you must be paid. Before a lien, it is your first tool when a pay app is late. Here are the Nevada rules.
| Rule | Private jobs | Public jobs |
|---|---|---|
| Owner pays the prime | 21 days after invoice unless agreed | 30 days after invoice |
| Prime pays the sub | 10 days after prime is paid | 10 days after prime is paid |
| Late interest | Prime rate plus 4% or agreed rate if higher | Top 90-day CD rate (to prime) |
Law: private: Nev. Rev. Stat. 624.606 to 624.630; public: Nev. Rev. Stat. 338.400 to 338.645. Limits: Some rules not for FAA contracts. Our plain-English summary of the ASA and Kegler Brown 2024 prompt pay chart. Check the statute before you rely on it.
See every state side by side in our prompt payment act rules by state.
A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:
Tools and related guides
Official law and forms: Many states print the lien form or notice wording right in the law. Read the Nevada lien law and use the state form if it has one.
Prime contractors: Record the notice of lien within 90 days after the LATEST of (i) completion of the work of improvement, (ii) the claimant's last delivery of materials or equipment, or (iii) the claimant's last performance of work. Or, if earlier, within 40 days after a valid notice of completion is recorded and served under 108.228. Subcontractors and suppliers: Same as prime: 90 days after the latest of completion, last delivery, or last work; 40 days after a valid notice of completion that was recorded and served on this claimant.
Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 90 days after completion of the project. Subcontractors and suppliers: 90 days after completion of the project. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.
Required for every non-privity claimant except labor-only claimants. Deliver the Notice of Right to Lien to the owner in person or by certified mail, with an information-only copy to the prime contractor. It may be given at any time after first furnishing, but the lien covers only what was furnished in the 31 days before the notice plus everything after. App: set the target as first furnishing + 31 days, which is a look-back, not a hard deadline. Without the notice, a lien for anything other than labor cannot be perfected.
On construction, alteration or repair of single-family or multifamily residences (apartment houses included), every claimant except laborers must serve a 15-day notice of intent to lien on both the owner and the reputed prime contractor before recording. A prime serves only the owner. Service is by personal delivery or certified mail. Without the notice, a lien for materials or equipment (anything except labor) cannot be perfected. Nonresidential projects are exempt (108.226(7)). The notice must be served at least 15 days before recording.
On residential jobs (single-family or multifamily, apartments included, whether or not owner-occupied), every claimant except laborers, primes included, must serve the 15-day notice of intent on the owner and the reputed prime at least 15 days before recording. It extends the recording deadline by 15 days (105 days, or 55 after the NOC). Without it, the non-labor portion of the lien cannot be perfected. The NRL rules are the same as on commercial jobs. There is no separate owner-occupied track in 108.226/.245.
File the foreclosure complaint no earlier than 30 days after recording and no later than 6 months after recording. The 6 months can be extended only by a written, acknowledged agreement signed by the claimant and the persons in interest. The agreement must be recorded within the 6-month period, the extension cannot run past 1 year after the lien was recorded, and no extension is allowed if it would delay other outstanding liens. At filing: record a lis pendens and publish notice of foreclosure once a week for 3 successive weeks (108.239).
On private jobs: owner pays the prime: 21 days after invoice unless agreed; prime pays the sub: 10 days after prime is paid. On public jobs: owner pays the prime: 30 days after invoice; prime pays the sub: 10 days after prime is paid. Check the statute for exceptions.
See mechanics lien deadlines for all 50 states
Get paid before it gets to a lien.
AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.
Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.
AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.