Idaho mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Idaho mechanics lien deadlines in plain English, with the law behind each rule.

Idaho mechanics lien deadlines and how to file

Quick answer: Idaho mechanics lien deadlines

90 days after completing labor or furnishing (§ 45-507).

Last updated: November 23, 2026

This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Idaho statute (Idaho Code §§ 45-501 et seq.; § 54-5208) in November 2026. Read the current law or ask a Idaho construction attorney before you file.

Idaho lien law at a glance

"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.

RuleWhat Idaho requiresLaw
Preliminary notice: prime contractorNo preliminary notice. Residential GC disclosure under 45-525 (see residential_rules).Idaho Code 45-507; 45-525
Preliminary notice: subcontractorNone.Idaho Code 45-507
Preliminary notice: supplierNone.Idaho Code 45-507
Notice of intent to lienNone.Idaho Code 45-507
Lien filing deadline: prime contractorFile claim with county recorder within 90 days after completion of labor/services or furnishing of materials. Courts measure from substantial completion; trivial later work does not extend (Hap Taylor; Franklin Bldg. Supply).Idaho Code 45-507(2)
Lien filing deadline: subcontractor and supplierSame 90 days.Idaho Code 45-507(2)
Residential projectsSame 90 days; a GC claim for work under 45-525 must include the proof of disclosure and the homeowner's acknowledgment of receipt.Idaho Code 45-507(3)
Notice of completion: does it shorten the deadline?None.Idaho Code ch. 45-5
Serving the owner after you fileServe a true and correct copy on owner or reputed owner no later than 5 BUSINESS DAYS after filing, by personal delivery by an officer authorized to serve process, or by certified mail to owner's last known address. Deed-of-trust trustee is not an 'owner'. The old 24-hour rule is superseded. Ashley Glass Co. v. Bithell (Idaho 1993, under the 24-hour version) held timely service is a statutory condition of an effective lien.Idaho Code 45-507(5),(6)
Deadline to sue (enforce the lien)Lien lapses 6 months after filing unless foreclosure is commenced. If a payment on account or extension of credit (with expiration date) is endorsed on the lien record, 6 months run from the payment or the credit's expiration. Must name necessary parties within that period. Judgment lien lasts 10 years.Idaho Code 45-510(1)

Idaho lien deadlines by role

Here is each deadline for prime contractors, subcontractors and suppliers on a commercial job. Homes have some different rules in Idaho. See the home rules below. "Prime" means you have a contract with the owner. Some deadlines change if the owner records a notice, so check the full rules below.

StepPrime contractorSubcontractorSupplier
Preliminary noticeNot requiredNot requiredNot required
Notice of intent to lienNot requiredNot requiredNot required
File the lienWithin 90 days after your last day of work or delivery.Within 90 days after your last day of work or delivery.Within 90 days after your last day of work or delivery.
Serve a copy of the lienWithin 5 business days after you file the lien.Within 5 business days after you file the lien.Within 5 business days after you file the lien.
Sue to enforce the lienWithin 6 months after you file the lien.Within 6 months after you file the lien.Within 6 months after you file the lien.

Get your exact Idaho dates

Enter your first and last day of work. Our free calculator shows the last day to send each notice, file your lien and sue.

Open the Idaho lien calculator

Idaho mechanics lien rules for homes and homeowners

Roofing, restoration and remodeling work on homes often has extra rules. In Idaho:

45-525 applies to residential real property of 1-4 dwelling units (owner or non-owner occupied). Before entering any contract over $2,000, the GC must give the homeowner a disclosure statement (rights to lien waivers, proof of general liability incl. completed operations insurance, extended title insurance for purchasers, surety bond) with an acknowledgment of receipt executed by the homeowner. Within a reasonable time before closing/final payment, GC must also give a signed list of direct subs, suppliers and equipment lessors furnishing over $500. Exempt: homeowner-initiated contact for bona fide emergency repairs. Noncompliance is an Idaho Consumer Protection Act violation (45-525(4)); the lien consequence comes from 45-507(3): a GC claim lacking the proof of disclosure and acknowledgment is invalid (GRSM 2022). Unregistered contractors: 54-5208 (from v3; not re-fetched).

Same 90 days; a GC claim for work under 45-525 must include the proof of disclosure and the homeowner's acknowledgment of receipt.

How to file a mechanics lien in Idaho, step by step

  1. Check the notice rules before you start. Look at the preliminary notice rows above for your role. Send any required notice early, by a method you can prove (like certified mail).
  2. Keep a job file from day one. Save the contract, change orders, invoices, delivery tickets, photos, and your first and last day of work. Most Idaho deadlines count from one of those dates.
  3. Follow up on every unpaid invoice. Send friendly reminders, then firm ones. Most customers pay before it ever gets to a lien.
  4. Send a warning before you file. None.
  5. File the lien on time and serve the owner. Prime: 90 days after your last day of work or materials. Subs and suppliers: 90 days after your last day of work or materials. Then serve the owner as the table explains.
  6. Enforce it or release it. Sue within 6 months after the lien is filed. If you get paid, release the lien right away.

Example: A subcontractor's last day of work on a Idaho job was Monday, March 2, 2026. With a 90-day deadline from the last day of work, count 90 days forward: the lien must be filed by Sunday, May 31, 2026. Don't wait for the last day. Set a reminder a few weeks earlier, and check whether a notice of completion or other rule in the table above changes your clock.

Watch: how to send a notice of intent to lien (3 minutes)

Idaho prompt payment act: how fast you must be paid

A prompt payment act sets how fast you must be paid. Before a lien, it is your first tool when a pay app is late. Here are the Idaho rules. Idaho has no general prompt pay law for private jobs, so your contract sets the terms there.

RulePrivate jobsPublic jobs
Owner pays the primeNo general law60 days after invoice
Prime pays the subNo general lawNo rule
Late interestNone statedRate set by law

Law: public: Idaho Code 67-2302. Our plain-English summary of the ASA and Kegler Brown 2024 prompt pay chart. Check the statute before you rely on it.

See every state side by side in our prompt payment act rules by state.

Before you file a lien in Idaho: try to get paid first

A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:

Idaho lien laws and forms: read the statute

Tools and related guides

Official law and forms: Many states print the lien form or notice wording right in the law. Read the Idaho lien law and use the state form if it has one.

Frequently asked questions

What is the deadline to file a mechanics lien in Idaho?

Prime contractors: File claim with county recorder within 90 days after completion of labor/services or furnishing of materials. Courts measure from substantial completion; trivial later work does not extend (Hap Taylor; Franklin Bldg. Supply). Subcontractors and suppliers: Same 90 days.

How do I file a mechanics lien in Idaho?

Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 90 days after your last day of work or materials. Subcontractors and suppliers: 90 days after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.

Do subcontractors need to send a preliminary notice in Idaho?

None.

Do I need to send a notice of intent to lien in Idaho?

None.

Are there special lien rules for homes in Idaho?

45-525 applies to residential real property of 1-4 dwelling units (owner or non-owner occupied). Before entering any contract over $2,000, the GC must give the homeowner a disclosure statement (rights to lien waivers, proof of general liability incl. completed operations insurance, extended title insurance for purchasers, surety bond) with an acknowledgment of receipt executed by the homeowner. Within a reasonable time before closing/final payment, GC must also give a signed list of direct subs, suppliers and equipment lessors furnishing over $500. Exempt: homeowner-initiated contact for bona fide emergency repairs. Noncompliance is an Idaho Consumer Protection Act violation (45-525(4)); the lien consequence comes from 45-507(3): a GC claim lacking the proof of disclosure and acknowledgment is invalid (GRSM 2022). Unregistered contractors: 54-5208 (from v3; not re-fetched).

How long do I have to enforce a mechanics lien in Idaho?

Lien lapses 6 months after filing unless foreclosure is commenced. If a payment on account or extension of credit (with expiration date) is endorsed on the lien record, 6 months run from the payment or the credit's expiration. Must name necessary parties within that period. Judgment lien lasts 10 years.

Does Idaho have a prompt payment act?

On private jobs: owner pays the prime: no general law; prime pays the sub: no general law. On public jobs: owner pays the prime: 60 days after invoice; prime pays the sub: no rule. Check the statute for exceptions.

Mechanics lien deadlines in nearby states

See mechanics lien deadlines for all 50 states

Get paid before it gets to a lien.

AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.

Book a demo

Sam Frenzley
About the authorSam Frenzley

Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.

You did the work. Let AI chase the money.

AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.

  • Keep QuickBooks
  • Start with one invoice
  • Stay in control