Wisconsin mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Wisconsin mechanics lien deadlines in plain English, with the law behind each rule.

Wisconsin mechanics lien deadlines and how to file

Quick answer: Wisconsin mechanics lien deadlines

6 months after last furnishing (§ 779.06).

Last updated: November 23, 2026

This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Wisconsin statute (Wis. Stat. §§ 779.01–.17) in November 2026. Read the current law or ask a Wisconsin construction attorney before you file.

Wisconsin lien law at a glance

"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.

RuleWhat Wisconsin requiresLaw
Preliminary notice: prime contractorA prime who contracts with the owner and has contracted, or will contract, with subs, suppliers or service providers must put the statutory notice in any written contract with the owner (at least 8-point bold if printed, or capitals if typewritten) and give the owner a copy. If there is no written contract, the notice is prepared separately and served on the owner or agent within 10 days after first labor or materials. Exempt: more than 4 family living units; partly or wholly nonresidential work; a prime that is itself the owner or controls the corporate owner. If missed, the prime has no lien, unless it pays all subs and suppliers within the 779.06 deadlines and none gave notice or all fully waived (2)(c).Wis. Stat. 779.02(1)(c)-(d), (2)(a), (2)(c)
Preliminary notice: subcontractorServe a written notice, in 2 signed copies, on the owner or authorized agent at the last-known post-office address within 60 days after first labor, services, materials, plans or specifications. Same exemptions (more than 4 units or any nonresidential). If missed there is no lien, but a late notice preserves the lien for work after the owner actually receives it.Wis. Stat. 779.02(2)(b), (3)
Preliminary notice: supplierSame as sub.Wis. Stat. 779.02(2)(b)
Notice of intent to lienRequired of ALL claimants, residential or commercial, even if a 779.02 notice was given. Serve the owner with written notice of intent to file a lien claim at least 30 days before the timely filing. It must briefly describe the claim, its amount, and the land and improvement. Practical latest date: (6-month filing deadline) minus 30 days.Wis. Stat. 779.06(2)
Lien filing deadline: prime contractorFile the claim with the clerk of circuit court of the county where the land lies within 6 months after the claimant's own last labor, services, materials, plans or specifications.Wis. Stat. 779.06(1)
Lien filing deadline: subcontractor and supplierSame.Wis. Stat. 779.06(1)
Residential projectsSame 6 months. Residential differs only in the 779.02 notices.Wis. Stat. 779.06(1)
Notice of completion: does it shorten the deadline?No notice of completion or commencement procedure in 779.01-.17 shortens the deadlines. None found in the sections read.Wis. Stat. 779.06
Serving the owner after you fileWithin 30 days after filing, serve a copy of the claim for lien on the owner. Before filing, also serve the 30-day notice of intent (see notice_of_intent).Wis. Stat. 779.06(1)
Deadline to sue (enforce the lien)Bring the action, with summons and complaint filed, within 2 years from the date of filing the claim. Otherwise no lien exists and no action can be maintained.Wis. Stat. 779.06(1)

Wisconsin lien deadlines by role

Here is each deadline for prime contractors, subcontractors and suppliers on a commercial job. Homes have some different rules in Wisconsin. See the home rules below. "Prime" means you have a contract with the owner. Some deadlines change if the owner records a notice, so check the full rules below.

StepPrime contractorSubcontractorSupplier
Preliminary noticeNot requiredNot requiredNot required
Notice of intent to lienAt least 30 days before you file the lien.At least 30 days before you file the lien.At least 30 days before you file the lien.
File the lienWithin 6 months after your last day of work or delivery.Within 6 months after your last day of work or delivery.Within 6 months after your last day of work or delivery.
Serve a copy of the lienWithin 30 days after you file the lien.Within 30 days after you file the lien.Within 30 days after you file the lien.
Sue to enforce the lienWithin 2 years after you file the lien.Within 2 years after you file the lien.Within 2 years after you file the lien.

Get your exact Wisconsin dates

Enter your first and last day of work. Our free calculator shows the last day to send each notice, file your lien and sue.

Open the Wisconsin lien calculator

Wisconsin mechanics lien rules for homes and homeowners

Roofing, restoration and remodeling work on homes often has extra rules. In Wisconsin:

The 779.02(2) prime contract notice and the 60-day sub notice apply only to wholly residential work adding 4 or fewer family living units. The 30-day notice of intent, 6-month filing and 2-year enforcement apply to all projects. Trust-fund / theft-by-contractor rule in 779.02(5). 2025 Act 32 bars liens on non-improvement contracts.

Same 6 months. Residential differs only in the 779.02 notices.

How to file a mechanics lien in Wisconsin, step by step

  1. Check the notice rules before you start. Look at the preliminary notice rows above for your role. Send any required notice early, by a method you can prove (like certified mail).
  2. Keep a job file from day one. Save the contract, change orders, invoices, delivery tickets, photos, and your first and last day of work. Most Wisconsin deadlines count from one of those dates.
  3. Follow up on every unpaid invoice. Send friendly reminders, then firm ones. Most customers pay before it ever gets to a lien.
  4. Send a warning before you file. Required of ALL claimants, residential or commercial, even if a 779.02 notice was given. Serve the owner with written notice of intent to file a lien claim at least 30 days before the timely filing. It must briefly describe the claim, its amount, and the land and improvement. Practical latest date: (6-month filing deadline) minus 30 days.
  5. File the lien on time and serve the owner. Prime: 6 months after your last day of work or materials. Subs and suppliers: 6 months after your last day of work or materials. Then serve the owner as the table explains.
  6. Enforce it or release it. Sue within 2 years after the lien is filed. If you get paid, release the lien right away.

Watch: how to send a notice of intent to lien (3 minutes)

Wisconsin prompt payment act: how fast you must be paid

A prompt payment act sets how fast you must be paid. Before a lien, it is your first tool when a pay app is late. Here are the Wisconsin rules. Wisconsin has no general prompt pay law for private jobs, so your contract sets the terms there.

RulePrivate jobsPublic jobs
Owner pays the primeNo general law30 days after invoice
Prime pays the subNo general law7 days after prime is paid
Late interestNone stated12% per year

Law: public: Wis. Stat. 16.528; 16.53(2); 66.0135. Our plain-English summary of the ASA and Kegler Brown 2024 prompt pay chart. Check the statute before you rely on it.

See every state side by side in our prompt payment act rules by state.

Before you file a lien in Wisconsin: try to get paid first

A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:

Wisconsin lien laws and forms: read the statute

Tools and related guides

Official law and forms: Many states print the lien form or notice wording right in the law. Read the Wisconsin lien law and use the state form if it has one.

Frequently asked questions

What is the deadline to file a mechanics lien in Wisconsin?

Prime contractors: File the claim with the clerk of circuit court of the county where the land lies within 6 months after the claimant's own last labor, services, materials, plans or specifications. Subcontractors and suppliers: Same.

How do I file a mechanics lien in Wisconsin?

Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 6 months after your last day of work or materials. Subcontractors and suppliers: 6 months after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.

Do subcontractors need to send a preliminary notice in Wisconsin?

Serve a written notice, in 2 signed copies, on the owner or authorized agent at the last-known post-office address within 60 days after first labor, services, materials, plans or specifications. Same exemptions (more than 4 units or any nonresidential). If missed there is no lien, but a late notice preserves the lien for work after the owner actually receives it.

Do I need to send a notice of intent to lien in Wisconsin?

Required of ALL claimants, residential or commercial, even if a 779.02 notice was given. Serve the owner with written notice of intent to file a lien claim at least 30 days before the timely filing. It must briefly describe the claim, its amount, and the land and improvement. Practical latest date: (6-month filing deadline) minus 30 days.

Are there special lien rules for homes in Wisconsin?

The 779.02(2) prime contract notice and the 60-day sub notice apply only to wholly residential work adding 4 or fewer family living units. The 30-day notice of intent, 6-month filing and 2-year enforcement apply to all projects. Trust-fund / theft-by-contractor rule in 779.02(5). 2025 Act 32 bars liens on non-improvement contracts.

How long do I have to enforce a mechanics lien in Wisconsin?

Bring the action, with summons and complaint filed, within 2 years from the date of filing the claim. Otherwise no lien exists and no action can be maintained.

Does Wisconsin have a prompt payment act?

On private jobs: owner pays the prime: no general law; prime pays the sub: no general law. On public jobs: owner pays the prime: 30 days after invoice; prime pays the sub: 7 days after prime is paid. Check the statute for exceptions.

Mechanics lien deadlines in nearby states

See mechanics lien deadlines for all 50 states

Get paid before it gets to a lien.

AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.

Book a demo

Sam Frenzley
About the authorSam Frenzley

Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.

You did the work. Let AI chase the money.

AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.

  • Keep QuickBooks
  • Start with one invoice
  • Stay in control