Wisconsin mechanics lien laws in plain English: deadlines for primes, subs and suppliers, notice rules, home rules and how to file. Free deadline calculator.
Wisconsin mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Wisconsin mechanics lien deadlines in plain English, with the law behind each rule.

Quick answer: Wisconsin mechanics lien deadlines
6 months after last furnishing (§ 779.06).
Last updated: November 23, 2026
This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Wisconsin statute (Wis. Stat. §§ 779.01–.17) in November 2026. Read the current law or ask a Wisconsin construction attorney before you file.
"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.
| Rule | What Wisconsin requires | Law |
|---|---|---|
| Preliminary notice: prime contractor | A prime who contracts with the owner and has contracted, or will contract, with subs, suppliers or service providers must put the statutory notice in any written contract with the owner (at least 8-point bold if printed, or capitals if typewritten) and give the owner a copy. If there is no written contract, the notice is prepared separately and served on the owner or agent within 10 days after first labor or materials. Exempt: more than 4 family living units; partly or wholly nonresidential work; a prime that is itself the owner or controls the corporate owner. If missed, the prime has no lien, unless it pays all subs and suppliers within the 779.06 deadlines and none gave notice or all fully waived (2)(c). | Wis. Stat. 779.02(1)(c)-(d), (2)(a), (2)(c) |
| Preliminary notice: subcontractor | Serve a written notice, in 2 signed copies, on the owner or authorized agent at the last-known post-office address within 60 days after first labor, services, materials, plans or specifications. Same exemptions (more than 4 units or any nonresidential). If missed there is no lien, but a late notice preserves the lien for work after the owner actually receives it. | Wis. Stat. 779.02(2)(b), (3) |
| Preliminary notice: supplier | Same as sub. | Wis. Stat. 779.02(2)(b) |
| Notice of intent to lien | Required of ALL claimants, residential or commercial, even if a 779.02 notice was given. Serve the owner with written notice of intent to file a lien claim at least 30 days before the timely filing. It must briefly describe the claim, its amount, and the land and improvement. Practical latest date: (6-month filing deadline) minus 30 days. | Wis. Stat. 779.06(2) |
| Lien filing deadline: prime contractor | File the claim with the clerk of circuit court of the county where the land lies within 6 months after the claimant's own last labor, services, materials, plans or specifications. | Wis. Stat. 779.06(1) |
| Lien filing deadline: subcontractor and supplier | Same. | Wis. Stat. 779.06(1) |
| Residential projects | Same 6 months. Residential differs only in the 779.02 notices. | Wis. Stat. 779.06(1) |
| Notice of completion: does it shorten the deadline? | No notice of completion or commencement procedure in 779.01-.17 shortens the deadlines. None found in the sections read. | Wis. Stat. 779.06 |
| Serving the owner after you file | Within 30 days after filing, serve a copy of the claim for lien on the owner. Before filing, also serve the 30-day notice of intent (see notice_of_intent). | Wis. Stat. 779.06(1) |
| Deadline to sue (enforce the lien) | Bring the action, with summons and complaint filed, within 2 years from the date of filing the claim. Otherwise no lien exists and no action can be maintained. | Wis. Stat. 779.06(1) |
Here is each deadline for prime contractors, subcontractors and suppliers on a commercial job. Homes have some different rules in Wisconsin. See the home rules below. "Prime" means you have a contract with the owner. Some deadlines change if the owner records a notice, so check the full rules below.
| Step | Prime contractor | Subcontractor | Supplier |
|---|---|---|---|
| Preliminary notice | Not required | Not required | Not required |
| Notice of intent to lien | At least 30 days before you file the lien. | At least 30 days before you file the lien. | At least 30 days before you file the lien. |
| File the lien | Within 6 months after your last day of work or delivery. | Within 6 months after your last day of work or delivery. | Within 6 months after your last day of work or delivery. |
| Serve a copy of the lien | Within 30 days after you file the lien. | Within 30 days after you file the lien. | Within 30 days after you file the lien. |
| Sue to enforce the lien | Within 2 years after you file the lien. | Within 2 years after you file the lien. | Within 2 years after you file the lien. |
Get your exact Wisconsin dates
Enter your first and last day of work. Our free calculator shows the last day to send each notice, file your lien and sue.
Roofing, restoration and remodeling work on homes often has extra rules. In Wisconsin:
The 779.02(2) prime contract notice and the 60-day sub notice apply only to wholly residential work adding 4 or fewer family living units. The 30-day notice of intent, 6-month filing and 2-year enforcement apply to all projects. Trust-fund / theft-by-contractor rule in 779.02(5). 2025 Act 32 bars liens on non-improvement contracts.
Same 6 months. Residential differs only in the 779.02 notices.
A prompt payment act sets how fast you must be paid. Before a lien, it is your first tool when a pay app is late. Here are the Wisconsin rules. Wisconsin has no general prompt pay law for private jobs, so your contract sets the terms there.
| Rule | Private jobs | Public jobs |
|---|---|---|
| Owner pays the prime | No general law | 30 days after invoice |
| Prime pays the sub | No general law | 7 days after prime is paid |
| Late interest | None stated | 12% per year |
Law: public: Wis. Stat. 16.528; 16.53(2); 66.0135. Our plain-English summary of the ASA and Kegler Brown 2024 prompt pay chart. Check the statute before you rely on it.
See every state side by side in our prompt payment act rules by state.
A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:
Tools and related guides
Official law and forms: Many states print the lien form or notice wording right in the law. Read the Wisconsin lien law and use the state form if it has one.
Prime contractors: File the claim with the clerk of circuit court of the county where the land lies within 6 months after the claimant's own last labor, services, materials, plans or specifications. Subcontractors and suppliers: Same.
Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 6 months after your last day of work or materials. Subcontractors and suppliers: 6 months after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.
Serve a written notice, in 2 signed copies, on the owner or authorized agent at the last-known post-office address within 60 days after first labor, services, materials, plans or specifications. Same exemptions (more than 4 units or any nonresidential). If missed there is no lien, but a late notice preserves the lien for work after the owner actually receives it.
Required of ALL claimants, residential or commercial, even if a 779.02 notice was given. Serve the owner with written notice of intent to file a lien claim at least 30 days before the timely filing. It must briefly describe the claim, its amount, and the land and improvement. Practical latest date: (6-month filing deadline) minus 30 days.
The 779.02(2) prime contract notice and the 60-day sub notice apply only to wholly residential work adding 4 or fewer family living units. The 30-day notice of intent, 6-month filing and 2-year enforcement apply to all projects. Trust-fund / theft-by-contractor rule in 779.02(5). 2025 Act 32 bars liens on non-improvement contracts.
Bring the action, with summons and complaint filed, within 2 years from the date of filing the claim. Otherwise no lien exists and no action can be maintained.
On private jobs: owner pays the prime: no general law; prime pays the sub: no general law. On public jobs: owner pays the prime: 30 days after invoice; prime pays the sub: 7 days after prime is paid. Check the statute for exceptions.
See mechanics lien deadlines for all 50 states
Get paid before it gets to a lien.
AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.
Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.
AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.