West Virginia mechanics lien laws: deadlines for primes, subs and suppliers, notice rules, home rules and how to file. Free deadline calculator.
West Virginia mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the West Virginia mechanics lien deadlines in plain English, with the law behind each rule.

Quick answer: West Virginia mechanics lien deadlines
Subcontractor: within 100 days after completion of its subcontract, both serve the notice on the owner and record it with the county commission clerk. Materialmen: 100 days after ceasing to furnish (38-2-10, -11). Laborers: 100 days after ceasing work (38-2-13). (W. Va. Code 38-2-9; 38-2-10; 38-2-11; 38-2-13)
Last updated: November 23, 2026
This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the West Virginia statute (W. Va. Code §§ 38-2-1 to -41) in November 2026. Read the current law or ask a West Virginia construction attorney before you file.
"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.
| Rule | What West Virginia requires | Law |
|---|---|---|
| Preliminary notice: prime contractor | None. | W. Va. Code 38-2-8 |
| Preliminary notice: subcontractor | Optional pre-work notice to the owner under 38-2-20, available to 'any laborer or other person employed to do any work or furnish any materials'. It is not required to perfect a lien. | W. Va. Code 38-2-20 |
| Preliminary notice: supplier | Same as sub (optional). | W. Va. Code 38-2-20 |
| Notice of intent to lien | None. | W. Va. Code 38-2 |
| Lien filing deadline: prime contractor | Record the notice of lien with the clerk of the county commission within 100 days after completion of the prime's work under its contract with the owner. The prime is not required to serve the owner. | W. Va. Code 38-2-8; 38-2-7 |
| Lien filing deadline: subcontractor and supplier | Subcontractor: within 100 days after completion of its subcontract, both serve the notice on the owner and record it with the county commission clerk. Materialmen: 100 days after ceasing to furnish (38-2-10, -11). Laborers: 100 days after ceasing work (38-2-13). | W. Va. Code 38-2-9; 38-2-10; 38-2-11; 38-2-13 |
| Residential projects | Same 100 days. No separate residential period. | W. Va. Code 38-2-7 to -13 |
| Notice of completion: does it shorten the deadline? | None. No notice of completion or commencement shortens deadlines. | W. Va. Code 38-2 |
| Serving the owner after you file | Subs, materialmen and laborers not in privity serve the notice on the owner or authorized agent within the same 100 days, by any method for service of a legal notice or summons. If the owner is a nonresident or cannot be found: publish as a Class II legal advertisement and post on the property (38-2-15). Missing service or recording is a complete discharge (38-2-14). Primes record only. | W. Va. Code 38-2-9, -11, -13, -14, -15 |
| Deadline to sue (enforce the lien) | Commence suit in circuit court within 6 months after the notice of lien is filed in the clerk's office, or the lien is discharged. A suit by one lienor preserves the liens of other lienors, who may intervene. | W. Va. Code 38-2-34(a) |
Here is each deadline for prime contractors, subcontractors and suppliers on a commercial job. Homes have some different rules in West Virginia. See the home rules below. "Prime" means you have a contract with the owner. Some deadlines change if the owner records a notice, so check the full rules below.
| Step | Prime contractor | Subcontractor | Supplier |
|---|---|---|---|
| Preliminary notice | Not required | Optional: Optional pre-work notice to the owner. | Optional: Optional pre-work notice to the owner. |
| Notice of intent to lien | Not required | Not required | Not required |
| File the lien | Within 100 days after your contract work is finished. | Within 100 days after your contract work is finished. | Within 100 days after your last day of work or delivery. |
| Serve a copy of the lien | Not required | Within 100 days after your contract work is finished. | Within 100 days after your last day of work or delivery. |
| Sue to enforce the lien | Within 6 months after you file the lien. | Within 6 months after you file the lien. | Within 6 months after you file the lien. |
Get your exact West Virginia dates
Enter your first and last day of work. Our free calculator shows the last day to send each notice, file your lien and sue.
Roofing, restoration and remodeling work on homes often has extra rules. In West Virginia:
For an existing single-family dwelling, a residence built under the owner's contract before occupancy as a primary residence, or a single-family owner-occupied dwelling, the owner has an affirmative defense (full or partial) that it owes the contractor nothing or less than the lien amount. This limits sub, supplier and laborer liens to the unpaid prime balance. It does not cover multi-residence developers or builders except for their own primary residence. 'Dwelling' includes houses, apartments, mobile and modular homes, and adjacent outbuildings. Applies from 7/1/2015.
Same 100 days. No separate residential period.
Example: A subcontractor's last day of work on a West Virginia job was Monday, March 2, 2026. With a 100-day deadline from the last day of work, count 100 days forward: the lien must be filed by Wednesday, June 10, 2026. Don't wait for the last day. Set a reminder a few weeks earlier, and check whether a notice of completion or other rule in the table above changes your clock.
A prompt payment act sets how fast you must be paid. Before a lien, it is your first tool when a pay app is late. Here are the West Virginia rules. West Virginia has no general prompt pay law for private jobs, so your contract sets the terms there.
| Rule | Private jobs | Public jobs |
|---|---|---|
| Owner pays the prime | No general law | 60 days after invoice |
| Prime pays the sub | No general law | No rule |
| Late interest | None stated | Legal rate after 60 days |
Law: public: W. Va. Code 7-5-7; 8-13-22d. Our plain-English summary of the ASA and Kegler Brown 2024 prompt pay chart. Check the statute before you rely on it.
See every state side by side in our prompt payment act rules by state.
A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:
Tools and related guides
Official law and forms: Many states print the lien form or notice wording right in the law. Read the West Virginia lien law and use the state form if it has one.
Prime contractors: Record the notice of lien with the clerk of the county commission within 100 days after completion of the prime's work under its contract with the owner. The prime is not required to serve the owner. Subcontractors and suppliers: Subcontractor: within 100 days after completion of its subcontract, both serve the notice on the owner and record it with the county commission clerk. Materialmen: 100 days after ceasing to furnish (38-2-10, -11). Laborers: 100 days after ceasing work (38-2-13).
Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 100 days after completion of your contract. Subcontractors and suppliers: 100 days after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.
Optional pre-work notice to the owner under 38-2-20, available to 'any laborer or other person employed to do any work or furnish any materials'. It is not required to perfect a lien.
None.
For an existing single-family dwelling, a residence built under the owner's contract before occupancy as a primary residence, or a single-family owner-occupied dwelling, the owner has an affirmative defense (full or partial) that it owes the contractor nothing or less than the lien amount. This limits sub, supplier and laborer liens to the unpaid prime balance. It does not cover multi-residence developers or builders except for their own primary residence. 'Dwelling' includes houses, apartments, mobile and modular homes, and adjacent outbuildings. Applies from 7/1/2015.
Commence suit in circuit court within 6 months after the notice of lien is filed in the clerk's office, or the lien is discharged. A suit by one lienor preserves the liens of other lienors, who may intervene.
On private jobs: owner pays the prime: no general law; prime pays the sub: no general law. On public jobs: owner pays the prime: 60 days after invoice; prime pays the sub: no rule. Check the statute for exceptions.
See mechanics lien deadlines for all 50 states
Get paid before it gets to a lien.
AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.
Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.
AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.