South Carolina mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the South Carolina mechanics lien deadlines in plain English, with the law behind each rule.

South Carolina mechanics lien deadlines and how to file

Quick answer: South Carolina mechanics lien deadlines

Sworn statement filed and served within 90 days after last furnishing (§ 29-5-90).

Last updated: November 23, 2026

This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the South Carolina statute (S.C. Code §§ 29-5-10 to -440) in November 2026. Read the current law or ask a South Carolina construction attorney before you file.

South Carolina lien law at a glance

"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.

RuleWhat South Carolina requiresLaw
Preliminary notice: prime contractorNone. Prime may (optionally) file a Notice of Project Commencement within 15 days of commencement of work.S.C. Code § 29-5-23
Preliminary notice: subcontractorFirst-tier sub (employed by contractor, not owner): must give written notice to owner of the furnishing for the lien to attach against the owner (§ 29-5-40); no fixed deadline (Ferguson Fire 2014: any time), but lien is capped at owner's unpaid balance at notice. Sub-subs and suppliers to subs: if a NOPC was filed, send notice of furnishing to the CONTRACTOR by certified/registered mail (§ 29-5-20(B)) to avoid being capped at what the contractor owes the sub.S.C. Code §§ 29-5-20(B), 29-5-23, 29-5-40
Preliminary notice: supplierSame as sub: § 29-5-40 owner notice; § 29-5-20(B) notice of furnishing to contractor when NOPC filed. No fixed deadline; send at first furnishing.S.C. Code §§ 29-5-20(B), 29-5-40
Notice of intent to lienNone.S.C. Code ch. 29-5
Lien filing deadline: prime contractorServe on owner (or person in possession) and file certificate of lien with register of deeds/clerk within 90 days after ceasing to furnish labor or materials.S.C. Code § 29-5-90
Lien filing deadline: subcontractor and supplierSame 90 days from that claimant's own last furnishing.S.C. Code § 29-5-90
Residential projectsSame 90 days; no residential exception except real-estate licensees under § 29-5-21(B)(3).S.C. Code § 29-5-90
Notice of completion: does it shorten the deadline?No completion notice. NOPC does not shorten any deadline; it only activates the § 29-5-20(B) notice-of-furnishing regime and § 29-5-60(B).S.C. Code § 29-5-23
Serving the owner after you fileServe owner (or person in possession if owner can't be found) within the same 90 days as filing.S.C. Code § 29-5-90
Deadline to sue (enforce the lien)Commence suit AND record notice of pendency (lis pendens) within 6 months after ceasing to furnish; otherwise lien dissolved. Release by court order or attorney affidavit after 6 months with no suit/lis pendens (§ 29-5-120(B)).S.C. Code § 29-5-120

South Carolina lien deadlines by role

Here is each deadline for prime contractors, subcontractors and suppliers on a commercial job. "Prime" means you have a contract with the owner. Some deadlines change if the owner records a notice, so check the full rules below.

StepPrime contractorSubcontractorSupplier
Preliminary noticeNot requiredOnly in some cases: Notify owner in writing of the labor/materials furnished and value. No deadline.Only in some cases: Notify owner in writing of the labor/materials furnished and value. No deadline.
Notice of intent to lienNot requiredNot requiredNot required
File the lienWithin 90 days after your last day of work or delivery.Within 90 days after your last day of work or delivery.Within 90 days after your last day of work or delivery.
Serve a copy of the lienNot requiredNot requiredNot required
Sue to enforce the lienWithin 6 months after your last day of work or delivery.Within 6 months after your last day of work or delivery.Within 6 months after your last day of work or delivery.

Get your exact South Carolina dates

Enter your first and last day of work. Our free calculator shows the last day to send each notice, file your lien and sue.

Open the South Carolina lien calculator

South Carolina mechanics lien rules for homes and homeowners

Roofing, restoration and remodeling work on homes often has extra rules. In South Carolina:

No separate lien track. Prevailing-party attorney fees + costs capped at lien amount (§ 29-5-10(a)). Prompt-pay interest § 29-6-60 does not apply to residential improvements of 16 or fewer units (Clement Rivers). Residential defect claims have 90-day pre-suit notice (§ 40-59-840) relevant to counterclaims.

Same 90 days; no residential exception except real-estate licensees under § 29-5-21(B)(3).

How to file a mechanics lien in South Carolina, step by step

  1. Check the notice rules before you start. Look at the preliminary notice rows above for your role. Send any required notice early, by a method you can prove (like certified mail).
  2. Keep a job file from day one. Save the contract, change orders, invoices, delivery tickets, photos, and your first and last day of work. Most South Carolina deadlines count from one of those dates.
  3. Follow up on every unpaid invoice. Send friendly reminders, then firm ones. Most customers pay before it ever gets to a lien.
  4. Send a warning before you file. None.
  5. File the lien on time and serve the owner. Prime: 90 days after your last day of work or materials. Subs and suppliers: 90 days after your last day of work or materials. Then serve the owner as the table explains.
  6. Enforce it or release it. Sue within 6 months after your last day of work or materials. If you get paid, release the lien right away.

Example: A subcontractor's last day of work on a South Carolina job was Monday, March 2, 2026. With a 90-day deadline from the last day of work, count 90 days forward: the lien must be filed by Sunday, May 31, 2026. Don't wait for the last day. Set a reminder a few weeks earlier, and check whether a notice of completion or other rule in the table above changes your clock.

Watch: how to send a notice of intent to lien (3 minutes)

South Carolina prompt payment act: how fast you must be paid

A prompt payment act sets how fast you must be paid. Before a lien, it is your first tool when a pay app is late. Here are the South Carolina rules.

RulePrivate jobsPublic jobs
Owner pays the prime21 days after invoice21 days after invoice
Prime pays the sub7 days after prime is paid7 days after prime is paid
Late interest1% per month if noted on invoice1% per month if noted on invoice

Law: private: S.C. Code 29-6-10 et seq.; public: S.C. Code 29-6-10 et seq.. Limits: Not homebuilders; not 16 units or fewer. Our plain-English summary of the ASA and Kegler Brown 2024 prompt pay chart. Check the statute before you rely on it.

See every state side by side in our prompt payment act rules by state.

Before you file a lien in South Carolina: try to get paid first

A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:

South Carolina lien laws and forms: read the statute

Tools and related guides

Official law and forms: Many states print the lien form or notice wording right in the law. Read the South Carolina lien law and use the state form if it has one.

Frequently asked questions

What is the deadline to file a mechanics lien in South Carolina?

Prime contractors: Serve on owner (or person in possession) and file certificate of lien with register of deeds/clerk within 90 days after ceasing to furnish labor or materials. Subcontractors and suppliers: Same 90 days from that claimant's own last furnishing.

How do I file a mechanics lien in South Carolina?

Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 90 days after your last day of work or materials. Subcontractors and suppliers: 90 days after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.

Do subcontractors need to send a preliminary notice in South Carolina?

First-tier sub (employed by contractor, not owner): must give written notice to owner of the furnishing for the lien to attach against the owner (§ 29-5-40); no fixed deadline (Ferguson Fire 2014: any time), but lien is capped at owner's unpaid balance at notice. Sub-subs and suppliers to subs: if a NOPC was filed, send notice of furnishing to the CONTRACTOR by certified/registered mail (§ 29-5-20(B)) to avoid being capped at what the contractor owes the sub.

Do I need to send a notice of intent to lien in South Carolina?

None.

Are there special lien rules for homes in South Carolina?

No separate lien track. Prevailing-party attorney fees + costs capped at lien amount (§ 29-5-10(a)). Prompt-pay interest § 29-6-60 does not apply to residential improvements of 16 or fewer units (Clement Rivers). Residential defect claims have 90-day pre-suit notice (§ 40-59-840) relevant to counterclaims.

How long do I have to enforce a mechanics lien in South Carolina?

Commence suit AND record notice of pendency (lis pendens) within 6 months after ceasing to furnish; otherwise lien dissolved. Release by court order or attorney affidavit after 6 months with no suit/lis pendens (§ 29-5-120(B)).

Does South Carolina have a prompt payment act?

On private jobs: owner pays the prime: 21 days after invoice; prime pays the sub: 7 days after prime is paid. On public jobs: owner pays the prime: 21 days after invoice; prime pays the sub: 7 days after prime is paid. Check the statute for exceptions.

Mechanics lien deadlines in nearby states

See mechanics lien deadlines for all 50 states

Get paid before it gets to a lien.

AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.

Book a demo

Sam Frenzley
About the authorSam Frenzley

Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.

You did the work. Let AI chase the money.

AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.

  • Keep QuickBooks
  • Start with one invoice
  • Stay in control