Oklahoma mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Oklahoma mechanics lien deadlines in plain English, with the law behind each rule.

Oklahoma mechanics lien deadlines and how to file

Quick answer: Oklahoma mechanics lien deadlines

Prime 4 months; others 90 days after last furnishing (§§ 142, 143).

Last updated: November 23, 2026

This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Oklahoma statute (42 O.S. §§ 141–143.4, 171–178) in November 2026. Read the current law or ask a Oklahoma construction attorney before you file.

Oklahoma lien law at a glance

"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.

RuleWhat Oklahoma requiresLaw
Preliminary notice: prime contractorNone. The pre-lien notice duty applies only to claimants other than the original contractor. A 'Homeowner Notice' before work, claimed by Levelset and Billd, was REPEALED effective 2011-11-01 (former 42 O.S. 142.1, 142.3, 142.5).42 O.S. 142.6(A); Laws 2011, c. 23
Preliminary notice: subcontractorPre-lien notice to the original contractor and the owner, no later than 75 days after the last date of supply of material, services, labor or equipment. Only one notice per project; none needed for agreed retainage. Exempt: an aggregate claim under $10,000, and residential projects of 4 or fewer units where none is owner-occupied. The exemptions do not apply to property occupied as a dwelling by an owner, where the notice is always required. Service: hand delivery with a delivery confirmation receipt, automated transaction (12A O.S. 15-115), or certified mail RRR (effective on mailing). A notarized compliance affidavit is filed with the lien statement.42 O.S. 142.6(B)(1)-(6),(C)
Preliminary notice: supplierSame as sub (any claimant other than the original contractor).42 O.S. 142.6
Notice of intent to lienNo separate notice of intent. The 75-day pre-lien notice is the only pre-filing notice.42 O.S. 142.6
Lien filing deadline: prime contractorFile the lien statement with the county clerk of the county where the land lies within 4 months after the date material or equipment was last furnished or labor last performed.42 O.S. 142
Lien filing deadline: subcontractor and supplierA sub or supplier under the original contractor files a verified statement with the county clerk within 90 days after material or equipment was last furnished or labor last performed under the subcontract.42 O.S. 143
Residential projectsSame 4 months / 90 days. Owner-occupied dwellings make the 75-day pre-lien notice mandatory for non-primes regardless of amount.42 O.S. 142, 143, 142.6(B)(1)
Notice of completion: does it shorten the deadline?No completion or commencement notice shortens deadlines.42 O.S. 141-143.4
Serving the owner after you fileUnchanged from wave 2 (143.1 was not re-fetched this session). The claimant gives the addresses and pays the fee; the clerk mails notice of the lien by certified mail within 5 business days. If the owner cannot be found, serve the occupant or post the property, by affidavit, within 60 days of filing.42 O.S. 143.1
Deadline to sue (enforce the lien)Civil action in the district court of the county within 1 year from filing the lien with the county clerk.42 O.S. 172

Oklahoma lien deadlines by role

Here is each deadline for prime contractors, subcontractors and suppliers on a commercial job. "Prime" means you have a contract with the owner. Some deadlines change if the owner records a notice, so check the full rules below.

StepPrime contractorSubcontractorSupplier
Preliminary noticeNot requiredOnly in some cases: Within 75 days after your last day of work or delivery.Only in some cases: Within 75 days after your last day of work or delivery.
Notice of intent to lienNot requiredNot requiredNot required
File the lienWithin 4 months after your last day of work or delivery.Within 90 days after your last day of work or delivery.Within 90 days after your last day of work or delivery.
Serve a copy of the lienOnly in some cases: Within 60 days after you file the lien.Only in some cases: Within 60 days after you file the lien.Only in some cases: Within 60 days after you file the lien.
Sue to enforce the lienWithin 1 year after you file the lien.Within 1 year after you file the lien.Within 1 year after you file the lien.

Get your exact Oklahoma dates

Enter your first and last day of work. Our free calculator shows the last day to send each notice, file your lien and sue.

Open the Oklahoma lien calculator

Oklahoma mechanics lien rules for homes and homeowners

Roofing, restoration and remodeling work on homes often has extra rules. In Oklahoma:

Owner-occupied dwelling (any size): a non-prime's lien is invalid without the 75-day pre-lien notice, even under $10,000. Non-owner-occupied residential of 4 or fewer units: exempt. No prime homeowner notice (repealed 2011). The homestead exemption does not bar liens for improvement work (31 O.S. 5). Equipment lessors are excluded on homestead or agricultural land (143.3, per Levelset).

Same 4 months / 90 days. Owner-occupied dwellings make the 75-day pre-lien notice mandatory for non-primes regardless of amount.

How to file a mechanics lien in Oklahoma, step by step

  1. Check the notice rules before you start. Look at the preliminary notice rows above for your role. Send any required notice early, by a method you can prove (like certified mail).
  2. Keep a job file from day one. Save the contract, change orders, invoices, delivery tickets, photos, and your first and last day of work. Most Oklahoma deadlines count from one of those dates.
  3. Follow up on every unpaid invoice. Send friendly reminders, then firm ones. Most customers pay before it ever gets to a lien.
  4. Send a warning before you file. No separate notice of intent. The 75-day pre-lien notice is the only pre-filing notice.
  5. File the lien on time and serve the owner. Prime: 4 months after your last day of work or materials. Subs and suppliers: 90 days after your last day of work or materials. Then serve the owner as the table explains.
  6. Enforce it or release it. Sue within 1 year after the lien is filed. If you get paid, release the lien right away.

Example: A subcontractor's last day of work on a Oklahoma job was Monday, March 2, 2026. With a 90-day deadline from the last day of work, count 90 days forward: the lien must be filed by Sunday, May 31, 2026. Don't wait for the last day. Set a reminder a few weeks earlier, and check whether a notice of completion or other rule in the table above changes your clock.

Watch: how to send a notice of intent to lien (3 minutes)

Oklahoma prompt payment act: how fast you must be paid

A prompt payment act sets how fast you must be paid. Before a lien, it is your first tool when a pay app is late. Here are the Oklahoma rules.

RulePrivate jobsPublic jobs
Owner pays the prime28 days after billing or per contract30 days after invoice
Prime pays the sub10 days after prime is paid or per contract10 days after prime is paid
Late interestNo ruleSee statute; 1.5% if prime pays sub late

Law: private: Okla. Stat. tit. 15 sec. 820; public: Okla. Stat. tit. 61 sec. 221 to 227. Limits: Some rules only for jobs over 4 homes. Our plain-English summary of the ASA and Kegler Brown 2024 prompt pay chart. Check the statute before you rely on it.

See every state side by side in our prompt payment act rules by state.

Before you file a lien in Oklahoma: try to get paid first

A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:

Oklahoma lien laws and forms: read the statute

Tools and related guides

Official law and forms: Many states print the lien form or notice wording right in the law. Read the Oklahoma lien law and use the state form if it has one.

Frequently asked questions

What is the deadline to file a mechanics lien in Oklahoma?

Prime contractors: File the lien statement with the county clerk of the county where the land lies within 4 months after the date material or equipment was last furnished or labor last performed. Subcontractors and suppliers: A sub or supplier under the original contractor files a verified statement with the county clerk within 90 days after material or equipment was last furnished or labor last performed under the subcontract.

How do I file a mechanics lien in Oklahoma?

Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 4 months after your last day of work or materials. Subcontractors and suppliers: 90 days after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.

Do subcontractors need to send a preliminary notice in Oklahoma?

Pre-lien notice to the original contractor and the owner, no later than 75 days after the last date of supply of material, services, labor or equipment. Only one notice per project; none needed for agreed retainage. Exempt: an aggregate claim under $10,000, and residential projects of 4 or fewer units where none is owner-occupied. The exemptions do not apply to property occupied as a dwelling by an owner, where the notice is always required. Service: hand delivery with a delivery confirmation receipt, automated transaction (12A O.S. 15-115), or certified mail RRR (effective on mailing). A notarized compliance affidavit is filed with the lien statement.

Do I need to send a notice of intent to lien in Oklahoma?

No separate notice of intent. The 75-day pre-lien notice is the only pre-filing notice.

Are there special lien rules for homes in Oklahoma?

Owner-occupied dwelling (any size): a non-prime's lien is invalid without the 75-day pre-lien notice, even under $10,000. Non-owner-occupied residential of 4 or fewer units: exempt. No prime homeowner notice (repealed 2011). The homestead exemption does not bar liens for improvement work (31 O.S. 5). Equipment lessors are excluded on homestead or agricultural land (143.3, per Levelset).

How long do I have to enforce a mechanics lien in Oklahoma?

Civil action in the district court of the county within 1 year from filing the lien with the county clerk.

Does Oklahoma have a prompt payment act?

On private jobs: owner pays the prime: 28 days after billing or per contract; prime pays the sub: 10 days after prime is paid or per contract. On public jobs: owner pays the prime: 30 days after invoice; prime pays the sub: 10 days after prime is paid. Check the statute for exceptions.

Mechanics lien deadlines in nearby states

See mechanics lien deadlines for all 50 states

Get paid before it gets to a lien.

AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.

Book a demo

Sam Frenzley
About the authorSam Frenzley

Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.

You did the work. Let AI chase the money.

AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.

  • Keep QuickBooks
  • Start with one invoice
  • Stay in control