Mississippi mechanics lien laws: deadlines for primes, subs and suppliers, notice rules, home rules and how to file. Free deadline calculator.
Mississippi mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Mississippi mechanics lien deadlines in plain English, with the law behind each rule.

Quick answer: Mississippi mechanics lien deadlines
90 days after last furnishing, filed with the chancery clerk (§ 85-7-405). The lien must state the date the claim was due; dated invoices alone are not enough and the lien is unenforceable (Cuevas Machine v. Calgon Carbon, Miss. Oct. 15, 2026).
Last updated: November 23, 2026
This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Mississippi statute (Miss. Code §§ 85-7-401 to -433 (Construction Lien Law, SB 2622, Laws 2014 ch. 487, eff. 2014-04-11)) in November 2026. Read the current law or ask a Mississippi construction attorney before you file.
"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.
| Rule | What Mississippi requires | Law |
|---|---|---|
| Preliminary notice: prime contractor | None. If the owner asks in writing, the prime must furnish a list of subs and suppliers (s.85-7-407(1), not applicable to single-family). | Miss. Code s.85-7-407 |
| Preliminary notice: subcontractor | First-tier subs (privity with contractor): none. Anyone without privity with the contractor (2nd-tier subs, suppliers to subs) gives written notice to the contractor (or owner if no contractor) within 30 days after first delivery to the property. Methods: email with confirmed receipt, registered/certified mail, or statutory overnight delivery. Missing it forfeits the lien. Does not apply to single-family residential. | s.85-7-407(2),(4) |
| Preliminary notice: supplier | Same as prelim_sub. A supplier to the prime has privity: no notice. A supplier to a sub: 30-day notice (non-single-family). | s.85-7-407(2) |
| Notice of intent to lien | Single-family residential construction only. A claimant not in privity with the owner gives the owner a Pre-Lien Notice (form in s.85-7-433(5)) at least 10 days before filing the lien, by any reliable means. It is a condition precedent. Primes (in privity with the owner): none. | s.85-7-409(2),(3) |
| Lien filing deadline: prime contractor | 90 days after the claimant's own last work, labor, services or materials. File with the chancery clerk of the county where the property lies. The lien must expressly state the date the claim was due, which equals the last furnishing date (see Cuevas). | s.85-7-405(1)(b) |
| Lien filing deadline: subcontractor and supplier | Same: 90 days after the claimant's own last furnishing. | s.85-7-405(1)(b) |
| Residential projects | Same 90 days. On single-family work, a non-privity claimant must serve the 10-day pre-lien notice by day 80. | ss.85-7-405(1)(b), -409(2) |
| Notice of completion: does it shorten the deadline? | MS has no notice of completion, and nothing shortens the 90-day LIEN filing deadline. Set shortens_deadline=false for the filing deadline. Separately, the owner, contractor or their agent/attorney may record a Notice of Contest (form s.85-7-433(4)) with proof of delivery. A copy goes to the claimant by registered/certified mail or statutory overnight delivery, at the address on the lien, within 7 days of filing. Service is complete on mailing. The lien is extinguished at the earlier of 90 days after the contest is filed or 180 days after the lien is filed, unless a payment action is filed. Model this as an enforcement-deadline trigger. | s.85-7-423 |
| Serving the owner after you file | Within 2 business days after the lien is filed of record, send a copy by registered/certified mail or statutory overnight delivery to the owner. If the owner's address can't be found, send it to the contractor as the owner's agent. Non-prime claimants also send a copy to the contractor. 'Business day' excludes Saturday, Sunday and legal holidays. | ss.85-7-405(1)(b), -401(a) |
| Deadline to sue (enforce the lien) | Payment action in county, circuit or chancery court within 180 days of lien filing. File a lis pendens WITH the commencement of the action, with copies to owner and contractor. If a Notice of Contest is recorded: the earlier of contest + 90 days or lien + 180 days. If no payment action is possible (bankruptcy, death, pay-when-paid not yet due), bring the lien action within the same period (s.-405(1)(d)). | ss.85-7-405(1)(c)-(d), -421(1), -423 |
Here is each deadline for prime contractors, subcontractors and suppliers on a commercial job. Homes have some different rules in Mississippi. See the home rules below. "Prime" means you have a contract with the owner. Some deadlines change if the owner records a notice, so check the full rules below.
| Step | Prime contractor | Subcontractor | Supplier |
|---|---|---|---|
| Preliminary notice | Not required | Not required | Only in some cases: Within 30 days after your first day of work or delivery. |
| Notice of intent to lien | Not required | Not required | Not required |
| File the lien | Within 90 days after your last day of work or delivery. | Within 90 days after your last day of work or delivery. | Within 90 days after your last day of work or delivery. |
| Serve a copy of the lien | Within 2 business days after you file the lien. | Within 2 business days after you file the lien. | Within 2 business days after you file the lien. |
| Sue to enforce the lien | Within 180 days after you file the lien. | Within 180 days after you file the lien. | Within 180 days after you file the lien. |
Get your exact Mississippi dates
Enter your first and last day of work. Our free calculator shows the last day to send each notice, file your lien and sue.
Roofing, restoration and remodeling work on homes often has extra rules. In Mississippi:
'Residential property' is defined as 1-4 family, but ss.-407(4) and -409 say 'single-family residential construction' (undefined). Single-family: no 30-day notice. A 10-day pre-lien notice to the owner is required from non-privity claimants. The owner's payments to the privity contractor made before receiving the pre-lien notice are an absolute defense, up to the amount paid. 2-4 family: treat as non-single-family (30-day notice required), and recommend also sending the pre-lien notice.
Same 90 days. On single-family work, a non-privity claimant must serve the 10-day pre-lien notice by day 80.
Example: A subcontractor's last day of work on a Mississippi job was Monday, March 2, 2026. With a 90-day deadline from the last day of work, count 90 days forward: the lien must be filed by Sunday, May 31, 2026. Don't wait for the last day. Set a reminder a few weeks earlier, and check whether a notice of completion or other rule in the table above changes your clock.
A prompt payment act sets how fast you must be paid. Before a lien, it is your first tool when a pay app is late. Here are the Mississippi rules.
| Rule | Private jobs | Public jobs |
|---|---|---|
| Owner pays the prime | Final pay 30 days after job done | Per contract; final 45 days after done |
| Prime pays the sub | 15 days after prime is paid | 15 days after prime is paid |
| Late interest | 1% per month to prime; 0.5% per day to subs | 1% per month to prime; 0.5% per day to subs |
Law: private: Miss. Code 87-7-3; 87-7-5; public: Miss. Code 31-5-25; 31-5-27. Our plain-English summary of the ASA and Kegler Brown 2024 prompt pay chart. Check the statute before you rely on it.
See every state side by side in our prompt payment act rules by state.
A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:
Tools and related guides
Official law and forms: Many states print the lien form or notice wording right in the law. Read the Mississippi lien law and use the state form if it has one.
Prime contractors: 90 days after the claimant's own last work, labor, services or materials. File with the chancery clerk of the county where the property lies. The lien must expressly state the date the claim was due, which equals the last furnishing date (see Cuevas). Subcontractors and suppliers: Same: 90 days after the claimant's own last furnishing.
Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 90 days after your last day of work or materials. Subcontractors and suppliers: 90 days after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.
First-tier subs (privity with contractor): none. Anyone without privity with the contractor (2nd-tier subs, suppliers to subs) gives written notice to the contractor (or owner if no contractor) within 30 days after first delivery to the property. Methods: email with confirmed receipt, registered/certified mail, or statutory overnight delivery. Missing it forfeits the lien. Does not apply to single-family residential.
Single-family residential construction only. A claimant not in privity with the owner gives the owner a Pre-Lien Notice (form in s.85-7-433(5)) at least 10 days before filing the lien, by any reliable means. It is a condition precedent. Primes (in privity with the owner): none.
'Residential property' is defined as 1-4 family, but ss.-407(4) and -409 say 'single-family residential construction' (undefined). Single-family: no 30-day notice. A 10-day pre-lien notice to the owner is required from non-privity claimants. The owner's payments to the privity contractor made before receiving the pre-lien notice are an absolute defense, up to the amount paid. 2-4 family: treat as non-single-family (30-day notice required), and recommend also sending the pre-lien notice.
Payment action in county, circuit or chancery court within 180 days of lien filing. File a lis pendens WITH the commencement of the action, with copies to owner and contractor. If a Notice of Contest is recorded: the earlier of contest + 90 days or lien + 180 days. If no payment action is possible (bankruptcy, death, pay-when-paid not yet due), bring the lien action within the same period (s.-405(1)(d)).
On private jobs: owner pays the prime: final pay 30 days after job done; prime pays the sub: 15 days after prime is paid. On public jobs: owner pays the prime: per contract; final 45 days after done; prime pays the sub: 15 days after prime is paid. Check the statute for exceptions.
See mechanics lien deadlines for all 50 states
Get paid before it gets to a lien.
AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.
Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.
AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.