Illinois mechanics lien laws in plain English: deadlines for primes, subs and suppliers, notice rules, home rules and how to file. Free deadline calculator.
Illinois mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Illinois mechanics lien deadlines in plain English, with the law behind each rule.

Quick answer: Illinois mechanics lien deadlines
Record within 4 months after completion (subs: their own last furnishing) to bind third parties; up to 2 years against the owner (§ 7(a)).
Last updated: November 23, 2026
This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Illinois statute (770 ILCS 60 (Mechanics Lien Act)) in November 2026. Read the current law or ask a Illinois construction attorney before you file.
"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.
| Rule | What Illinois requires | Law |
|---|---|---|
| Preliminary notice: prime contractor | None. A direct contractor serves no preliminary notice. It must give the owner a sworn statement of subs and suppliers (Sec. 5) when asked and before being paid. Owner-occupied single-family work adds a 10-day post-recording notice from the contractor (see lien_deadline_residential). | 770 ILCS 60/5; 60/7(d) |
| Preliminary notice: subcontractor | REQUIRED on all private projects for every claimant without a contract with the owner: the Sec. 24 notice, served on the owner of record (or the owner's agent, architect or superintendent) and on the lender if known, within 90 days after the claimant's OWN completion (extras: 90 days after the extra work or final delivery). Existing owner-occupied single-family residence: ALSO a 60-day notice to the occupant within 60 days after FIRST furnishing (Sec. 21(c)). The 60-day notice does not replace the 90-day notice. | 770 ILCS 60/24(a); 60/21(c) |
| Preliminary notice: supplier | Same as subs. Sec. 24 covers anyone furnishing labor, services, material, fixtures, apparatus, machinery, or forms or form work under a contract with the contractor or a sub, including equipment lessors. Sec. 21(c) 60-day notice applies on existing owner-occupied single-family work. Sub-sub and supplier-to-sub liens are limited to what the owner still owes when notice is served. | 770 ILCS 60/21, 60/24 |
| Notice of intent to lien | No separate notice of intent. The Sec. 24 90-day notice does that job. Accepted delivery: registered or certified mail with return receipt requested; a nationally recognized delivery company with tracking (from 1-1-2025); or personal service. Served when placed in the mail or handed to the carrier. The old 'delivery limited to addressee only' requirement is gone from the current text. | 770 ILCS 60/24(a) as amended by P.A. 103-827 |
| Lien filing deadline: prime contractor | Record a claim (or sue) within 4 months after completion of the contract, or after completion of extra work or final delivery of extra material, to bind other creditors, incumbrancers and purchasers. A claim filed later, but within 2 years after completion, binds only the owner. | 770 ILCS 60/7(a) |
| Lien filing deadline: subcontractor and supplier | 4 months after the claimant's OWN last furnishing (not project completion) to bind third parties. Sec. 28 applies the Sec. 7 and Secs. 9-20 time limits to subs. The Sec. 24 90-day notice is a separate prerequisite with an earlier deadline. | 770 ILCS 60/7, 60/28, 60/24 |
| Residential projects | Same 4 months. Sec. 7(d) is confirmed: a CONTRACTOR improving an owner-occupied single-family residence must give the owner written notice within 10 days after recording. It does NOT apply to subcontractors. If the notice is late, the lien is lost only to the extent of damages the owner suffered before receiving notice; recording alone is not damages. It applies to contracts entered into on or after 1-1-2010. | 770 ILCS 60/7(d) |
| Notice of completion: does it shorten the deadline? | Illinois has no notice-of-completion procedure. The only owner tool that shortens a deadline is the Sec. 34 written demand, which forces suit within 30 days. | 770 ILCS 60/34 |
| Serving the owner after you file | Subs and suppliers: the Sec. 24 notice to the owner AND the lender (if known) is the required owner service on every private project. A recorded mortgagee counts as known (constructive notice). Missing the lender makes the lien unenforceable against the lender only. Owner-occupied single-family: the 10-day post-recording notice is the CONTRACTOR's duty only (Sec. 7(d)). The Act has no general rule requiring a copy of the recorded claim to be served. | 770 ILCS 60/24; 60/7(d) |
| Deadline to sue (enforce the lien) | Suit (or counterclaim) within 2 years after completion of the contract, or of extra work or delivery of extra material. Subs: the same limit, measured from their own completion (Sec. 28). An owner's written demand (registered or certified mail, or personal service) requires suit or answer within 30 days, or the lien is forfeited. A sub may sue once 10 days pass after its notice without payment. | 770 ILCS 60/9, 60/28, 60/34 |
Here is each deadline for prime contractors, subcontractors and suppliers on a commercial job. Homes have some different rules in Illinois. See the home rules below. "Prime" means you have a contract with the owner. Some deadlines change if the owner records a notice, so check the full rules below.
| Step | Prime contractor | Subcontractor | Supplier |
|---|---|---|---|
| Preliminary notice | Not required | Within 90 days after your last day of work or delivery. | Within 90 days after your last day of work or delivery. |
| Notice of intent to lien | Not required | Not required | Not required |
| File the lien | Within 4 months after the project is finished. | Within 4 months after your last day of work or delivery. | Within 4 months after your last day of work or delivery. |
| Serve a copy of the lien | Not required | Not required | Not required |
| Sue to enforce the lien | Within 2 years after the project is finished. | Within 2 years after your last day of work or delivery. | Within 2 years after your last day of work or delivery. |
Get your exact Illinois dates
Enter your first and last day of work. Our free calculator shows the last day to send each notice, file your lien and sue.
Roofing, restoration and remodeling work on homes often has extra rules. In Illinois:
Existing owner-occupied single-family residence: (1) Subs and suppliers give the occupant a notice within 60 days after first furnishing, by personal delivery or certified mail with return receipt (served at mailing), with the NOTICE TO OWNER warning in 10-pt bold. A late notice still preserves the lien, but only to the extent the owner was not prejudiced by payments made before receiving it (Sec. 21(c)). (2) The Sec. 24 90-day notice is still required. (3) The direct contractor gives the owner notice within 10 days after recording (Sec. 7(d)); late notice reduces the lien only by the owner's damages. (4) Sec. 5 sworn statement before payment. P.A. 103-827 removed the duplicate sub-notice language from Sec. 5(b)(ii)-(iii), now marked '(Blank)', leaving Sec. 21(c) as the sole home of the 60-day notice.
Same 4 months. Sec. 7(d) is confirmed: a CONTRACTOR improving an owner-occupied single-family residence must give the owner written notice within 10 days after recording. It does NOT apply to subcontractors. If the notice is late, the lien is lost only to the extent of damages the owner suffered before receiving notice; recording alone is not damages. It applies to contracts entered into on or after 1-1-2010.
A prompt payment act sets how fast you must be paid. Before a lien, it is your first tool when a pay app is late. Here are the Illinois rules.
| Rule | Private jobs | Public jobs |
|---|---|---|
| Owner pays the prime | 40 days after invoice | 90 days after invoice |
| Prime pays the sub | 15 days after prime is paid | 15 days after prime is paid |
| Late interest | 10% per year | 1% per month to prime; 2% per month to subs |
Law: private: 815 ILCS 603; public: 50 ILCS 505; 30 ILCS 540. Our plain-English summary of the ASA and Kegler Brown 2024 prompt pay chart. Check the statute before you rely on it.
See every state side by side in our prompt payment act rules by state.
A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:
Tools and related guides
Official law and forms: Many states print the lien form or notice wording right in the law. Read the Illinois lien law and use the state form if it has one.
Prime contractors: Record a claim (or sue) within 4 months after completion of the contract, or after completion of extra work or final delivery of extra material, to bind other creditors, incumbrancers and purchasers. A claim filed later, but within 2 years after completion, binds only the owner. Subcontractors and suppliers: 4 months after the claimant's OWN last furnishing (not project completion) to bind third parties. Sec. 28 applies the Sec. 7 and Secs. 9-20 time limits to subs. The Sec. 24 90-day notice is a separate prerequisite with an earlier deadline.
Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 4 months after completion of the project. Subcontractors and suppliers: 4 months after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.
REQUIRED on all private projects for every claimant without a contract with the owner: the Sec. 24 notice, served on the owner of record (or the owner's agent, architect or superintendent) and on the lender if known, within 90 days after the claimant's OWN completion (extras: 90 days after the extra work or final delivery). Existing owner-occupied single-family residence: ALSO a 60-day notice to the occupant within 60 days after FIRST furnishing (Sec. 21(c)). The 60-day notice does not replace the 90-day notice.
No separate notice of intent. The Sec. 24 90-day notice does that job. Accepted delivery: registered or certified mail with return receipt requested; a nationally recognized delivery company with tracking (from 1-1-2025); or personal service. Served when placed in the mail or handed to the carrier. The old 'delivery limited to addressee only' requirement is gone from the current text.
Existing owner-occupied single-family residence: (1) Subs and suppliers give the occupant a notice within 60 days after first furnishing, by personal delivery or certified mail with return receipt (served at mailing), with the NOTICE TO OWNER warning in 10-pt bold. A late notice still preserves the lien, but only to the extent the owner was not prejudiced by payments made before receiving it (Sec. 21(c)). (2) The Sec. 24 90-day notice is still required. (3) The direct contractor gives the owner notice within 10 days after recording (Sec. 7(d)); late notice reduces the lien only by the owner's damages. (4) Sec. 5 sworn statement before payment. P.A. 103-827 removed the duplicate sub-notice language from Sec. 5(b)(ii)-(iii), now marked '(Blank)', leaving Sec. 21(c) as the sole home of the 60-day notice.
Suit (or counterclaim) within 2 years after completion of the contract, or of extra work or delivery of extra material. Subs: the same limit, measured from their own completion (Sec. 28). An owner's written demand (registered or certified mail, or personal service) requires suit or answer within 30 days, or the lien is forfeited. A sub may sue once 10 days pass after its notice without payment.
On private jobs: owner pays the prime: 40 days after invoice; prime pays the sub: 15 days after prime is paid. On public jobs: owner pays the prime: 90 days after invoice; prime pays the sub: 15 days after prime is paid. Check the statute for exceptions.
See mechanics lien deadlines for all 50 states
Get paid before it gets to a lien.
AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.
Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.
AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.