AR Workflow Blog/Collections tips

Hawaii Mechanics Lien: Deadlines and How to File

Hawaii mechanics lien laws in plain English: deadlines for primes, subs and suppliers, notice rules, home rules and how to file. Free deadline calculator.

Sam Frenzley
Founder, AR Workflow
11 min read

Hawaii mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Hawaii mechanics lien deadlines in plain English, with the law behind each rule.

Hawaii mechanics lien deadlines and how to file

Quick answer: Hawaii mechanics lien deadlines

Application for lien filed in circuit court and served within 45 days after date of completion. If no notice of completion is published, completion is deemed 1 year after actual completion (§ 507-43).

Last updated: November 23, 2026

This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Hawaii statute (Haw. Rev. Stat. §§ 507-41 to -49) in November 2026. Read the current law or ask a Hawaii construction attorney before you file.

Hawaii lien law at a glance

"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.

RuleWhat Hawaii requiresLaw
Preliminary notice: prime contractorNone.HRS §§ 507-42, 507-43
Preliminary notice: subcontractorNone. Siteline's 'Y' is wrong.HRS §§ 507-42, 507-43
Preliminary notice: supplierNone. Note: on dwellings, a supplier has no lien for materials furnished to an unlicensed contractor or on unreasonable credit (§ 507-49(a), per wave 2).HRS §§ 507-42, 507-49(a)
Notice of intent to lienNone. The lien is sought by filing an Application for Mechanic's and Materialman's Lien, with a Notice of Lien, in circuit court. The lien attaches only when the court enters an Order Directing Lien to Attach after a probable-cause hearing.HRS § 507-43(a)
Lien filing deadline: prime contractorFile the Application and Notice in circuit court within 45 days after the 'date of completion' of the improvement. That date is set by publication of a notice of completion; if no valid notice is published and filed within 1 year after actual completion, completion is deemed 1 year after actual completion or abandonment.HRS § 507-43(b),(f),(g)
Lien filing deadline: subcontractor and supplierSame as prime: 45 days after the date of completion.HRS § 507-43(b)
Residential projectsSame 45 days. But a prime contractor dealing with a homeowner has no lien at all if it did not comply with § 444-25.5 (see residential_rules).HRS §§ 507-43(b), 444-25.5
Notice of completion: does it shorten the deadline?The owner (or the GC, after a written demand that the owner publish and 5 days of owner inaction) publishes a notice of completion or abandonment twice, 7 days apart, in a newspaper of general circulation. The newspaper files the affidavit of publication with the circuit court clerk. The date of completion is when publication is complete, which starts the 45-day clock. If no valid notice is published and filed within 1 year after actual completion, completion is deemed 1 year after actual completion, so the outer deadline is about 1 year + 45 days. In practice the notice sets, rather than shortens, the clock: without it, the clock starts much later.HRS § 507-43(f),(g)
Serving the owner after you fileServe a copy of the Application and Notice 'in the manner prescribed by law' (like a summons) on the owner, any person with an interest, and the party that contracted for the improvement. If service cannot be made, post on the improvement (wave 2). The return date is 3-10 days after service. For Land Court property, file a certified copy of the attachment order with the assistant registrar within 7 days (wave 2).HRS § 507-43(a)-(d)
Deadline to sue (enforce the lien)The lien expires 3 months after entry of the Order Directing Lien to Attach unless proceedings to enforce it start within that time.HRS § 507-43(e)

Hawaii lien deadlines by role

Here is each deadline for prime contractors, subcontractors and suppliers on a commercial job. Homes have some different rules in Hawaii. See the home rules below. "Prime" means you have a contract with the owner. Some deadlines change if the owner records a notice, so check the full rules below.

StepPrime contractorSubcontractorSupplier
Preliminary noticeNot requiredNot requiredNot required
Notice of intent to lienNot requiredNot requiredNot required
File the lienWithin 45 days after the owner records a notice of completion.Within 45 days after the owner records a notice of completion.Within 45 days after the owner records a notice of completion.
Serve a copy of the lienServe the Application and Notice like a summons on the owner, each person with an interest, and the contracting party.Serve the Application and Notice like a summons on the owner, each person with an interest, and the contracting party.Serve the Application and Notice like a summons on the owner, each person with an interest, and the contracting party.
Sue to enforce the lienStart enforcement (foreclosure) proceedings within 3 calendar months after entry of the Order Directing Lien to Attach.Start enforcement (foreclosure) proceedings within 3 calendar months after entry of the Order Directing Lien to Attach.Start enforcement (foreclosure) proceedings within 3 calendar months after entry of the Order Directing Lien to Attach.

Get your exact Hawaii dates

Enter your first and last day of work. Our free calculator shows the last day to send each notice, file your lien and sue.

Open the Hawaii lien calculator

Hawaii mechanics lien rules for homes and homeowners

Roofing, restoration and remodeling work on homes often has extra rules. In Hawaii:

A licensed contractor contracting with a 'homeowner' (owner or lessee of residential real property, including condo and co-op owners) must: (a) before or at signing, explain verbally and in detail the lien rights of all parties and the homeowner's option to demand bonding, with its approximate cost; and (b) give a written contract containing that information and the § 672E-11 notice of the right to repair construction defects, signed by both parties before any work starts. There is no dollar threshold. Noncompliance is an unfair or deceptive practice, the contract is void, and no § 507-42 lien is available; recovery is limited to quantum meruit. Courts treat the requirements as mandatory and reject substantial compliance (808 Development v. Murakami, 2006; Hiraga v. Baldonado, 2001; Cavalier Construction v. Rice, ICA 2024). Unlicensed GC or sub: no lien for it or for subs under it (§ 507-49(b)).

Same 45 days. But a prime contractor dealing with a homeowner has no lien at all if it did not comply with § 444-25.5 (see residential_rules).

How to file a mechanics lien in Hawaii, step by step

  1. Check the notice rules before you start. Look at the preliminary notice rows above for your role. Send any required notice early, by a method you can prove (like certified mail).
  2. Keep a job file from day one. Save the contract, change orders, invoices, delivery tickets, photos, and your first and last day of work. Most Hawaii deadlines count from one of those dates.
  3. Follow up on every unpaid invoice. Send friendly reminders, then firm ones. Most customers pay before it ever gets to a lien.
  4. Send a warning before you file. None. The lien is sought by filing an Application for Mechanic's and Materialman's Lien, with a Notice of Lien, in circuit court. The lien attaches only when the court enters an Order Directing Lien to Attach after a probable-cause hearing.
  5. File the lien on time and serve the owner. Prime: 45 days after completion of the project. Subs and suppliers: 45 days after completion of the project. Then serve the owner as the table explains.
  6. Enforce it or release it. Sue within 3 months after a court order. If you get paid, release the lien right away.

Watch: how to send a notice of intent to lien (3 minutes)

Hawaii prompt payment act: how fast you must be paid

A prompt payment act sets how fast you must be paid. Before a lien, it is your first tool when a pay app is late. Here are the Hawaii rules.

RulePrivate jobsPublic jobs
Owner pays the primeNo rule30 days after invoice
Prime pays the sub10 days after prime gets sub invoice10 days after prime is paid
Late interest1.5% per monthPrime rate plus 2%

Law: private: HRS 444-25; public: HRS 103-10; 103-10.5. Our plain-English summary of the ASA and Kegler Brown 2024 prompt pay chart. Check the statute before you rely on it.

See every state side by side in our prompt payment act rules by state.

Before you file a lien in Hawaii: try to get paid first

A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:

Hawaii lien laws and forms: read the statute

Tools and related guides

Official law and forms: Many states print the lien form or notice wording right in the law. Read the Hawaii lien law and use the state form if it has one.

Frequently asked questions

What is the deadline to file a mechanics lien in Hawaii?

Prime contractors: File the Application and Notice in circuit court within 45 days after the 'date of completion' of the improvement. That date is set by publication of a notice of completion; if no valid notice is published and filed within 1 year after actual completion, completion is deemed 1 year after actual completion or abandonment. Subcontractors and suppliers: Same as prime: 45 days after the date of completion.

How do I file a mechanics lien in Hawaii?

Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 45 days after completion of the project. Subcontractors and suppliers: 45 days after completion of the project. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.

Do subcontractors need to send a preliminary notice in Hawaii?

None. Siteline's 'Y' is wrong.

Do I need to send a notice of intent to lien in Hawaii?

None. The lien is sought by filing an Application for Mechanic's and Materialman's Lien, with a Notice of Lien, in circuit court. The lien attaches only when the court enters an Order Directing Lien to Attach after a probable-cause hearing.

Are there special lien rules for homes in Hawaii?

A licensed contractor contracting with a 'homeowner' (owner or lessee of residential real property, including condo and co-op owners) must: (a) before or at signing, explain verbally and in detail the lien rights of all parties and the homeowner's option to demand bonding, with its approximate cost; and (b) give a written contract containing that information and the § 672E-11 notice of the right to repair construction defects, signed by both parties before any work starts. There is no dollar threshold. Noncompliance is an unfair or deceptive practice, the contract is void, and no § 507-42 lien is available; recovery is limited to quantum meruit. Courts treat the requirements as mandatory and reject substantial compliance (808 Development v. Murakami, 2006; Hiraga v. Baldonado, 2001; Cavalier Construction v. Rice, ICA 2024). Unlicensed GC or sub: no lien for it or for subs under it (§ 507-49(b)).

How long do I have to enforce a mechanics lien in Hawaii?

The lien expires 3 months after entry of the Order Directing Lien to Attach unless proceedings to enforce it start within that time.

Does Hawaii have a prompt payment act?

On private jobs: owner pays the prime: no rule; prime pays the sub: 10 days after prime gets sub invoice. On public jobs: owner pays the prime: 30 days after invoice; prime pays the sub: 10 days after prime is paid. Check the statute for exceptions.

Mechanics lien deadlines in nearby states

See mechanics lien deadlines for all 50 states

Get paid before it gets to a lien.

AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.

Book a demo

Sam Frenzley
About the authorSam Frenzley

Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.

You did the work. Let AI chase the money.

AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.

  • Keep QuickBooks
  • Start with one invoice
  • Stay in control