Florida mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Florida mechanics lien deadlines in plain English, with the law behind each rule.

Florida mechanics lien deadlines and how to file

Quick answer: Florida mechanics lien deadlines

90 days after final furnishing; if the contract is terminated, the earlier of 90 days after termination or after final furnishing (§ 713.08(5)).

Last updated: November 23, 2026

This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Florida statute (Fla. Stat. §§ 713.001–713.37) in November 2026. Read the current law or ask a Florida construction attorney before you file.

Florida lien law at a glance

"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.

RuleWhat Florida requiresLaw
Preliminary notice: prime contractorNo notice to owner for the prime (in privity). The direct contract for 1-4 family dwellings over $2,500 must contain the § 713.015 statutory disclosure (12-pt bold caps, front page or separate page signed and dated by owner). Failure does not bar the lien against an owner who was not adversely affected.Fla. Stat. § 713.015; § 713.06(1)-(2)(a)
Preliminary notice: subcontractorAll lienors not in privity with the owner, except laborers, must serve a Notice to Owner before commencing or not later than 45 days after commencing to furnish, and before the owner's final payment after the contractor's final payment affidavit. Sub-subs and suppliers to subs also serve a copy on the contractor; a supplier to a sub-sub serves the subcontractor too. Failure is a complete defense to the lien.Fla. Stat. § 713.06(2)(a)
Preliminary notice: supplierSame as sub: NTO within 45 days after first furnishing, copy to contractor (and to the subcontractor if supplying a sub-sub). Certified/registered/Global Express Guaranteed mail within 40 days after first furnishing is effective on mailing.Fla. Stat. §§ 713.06(2)(a), 713.18(2)
Notice of intent to lienNo pre-lien notice of intent for construction liens. Prime (contractor in privity) must deliver the contractor's final payment affidavit to the owner at least 5 days before instituting an action to enforce the lien; a contractor in default of this has no lien or right of action against the owner. Statute text sets no 90-day deadline for the affidavit; it must simply precede suit by 5 days (and suit must be within the 1-year lien life).Fla. Stat. § 713.06(3)(d)1.; A. Alexis Varela, Inc. v. Pagio, No. 5D21-2077 (Fla. 5th DCA May 20, 2022)
Lien filing deadline: prime contractorRecord claim of lien not later than 90 days after the lienor's final furnishing; if the contract is terminated/contractor defaults (§ 713.07(4)), not later than 90 days after termination or final furnishing, whichever occurs first.Fla. Stat. § 713.08(5)
Lien filing deadline: subcontractor and supplierSame as prime: 90 days after that lienor's own final furnishing (earlier of termination date + 90 if contract terminated).Fla. Stat. § 713.08(5); § 713.01(12)
Residential projectsSame 90 days. No residential-specific recording deadline.Fla. Stat. § 713.08(5)
Notice of completion: does it shorten the deadline?No notice of completion. Notice of Commencement does not change the 45/90-day clocks (NOC gives constructive notice and governs priority/proper payment; void if work not commenced within 90 days of recording; expires 1 year after recording unless stated). Owner's recorded Notice of Contest: lien extinguished automatically unless suit filed within 60 days after clerk's service. Order to show cause: lienor must show cause within 20 days after service of summons or lien is cancelled.Fla. Stat. §§ 713.13(2),(3),(6); 713.22(2); 713.21(4)
Serving the owner after you fileServe claim of lien on owner per § 713.18 before recording or within 15 days after recording; failure renders lien voidable only to the extent prejudicial.Fla. Stat. § 713.08(4)(c)
Deadline to sue (enforce the lien)Suit within 1 year after recording the claim of lien (or 1 year after recording an amended claim showing a later final furnishing date). Shortened to 60 days after service of Notice of Contest, or 20 days after service of order-to-show-cause summons. Lis pendens needed for the lien to bind creditors/subsequent purchasers without notice.Fla. Stat. § 713.22(1)-(2); § 713.21(4)

Florida lien deadlines by role

Here is each deadline for prime contractors, subcontractors and suppliers on a commercial job. Homes have some different rules in Florida. See the home rules below. "Prime" means you have a contract with the owner. Some deadlines change if the owner records a notice, so check the full rules below.

StepPrime contractorSubcontractorSupplier
Preliminary noticeNot requiredWithin 45 days after your first day of work or delivery.Within 45 days after your first day of work or delivery.
Notice of intent to lienNot requiredNot requiredNot required
File the lienWithin 90 days after your last day of work or delivery.Within 90 days after your last day of work or delivery.Within 90 days after your last day of work or delivery.
Serve a copy of the lienWithin 15 days after the lien is recorded.Within 15 days after the lien is recorded.Within 15 days after the lien is recorded.
Sue to enforce the lienWithin 1 year after the lien is recorded.Within 1 year after the lien is recorded.Within 1 year after the lien is recorded.

Get your exact Florida dates

Enter your first and last day of work. Our free calculator shows the last day to send each notice, file your lien and sue.

Open the Florida lien calculator

Florida mechanics lien rules for homes and homeowners

Roofing, restoration and remodeling work on homes often has extra rules. In Florida:

§ 713.015 disclosure for 1-4 family direct contracts > $2,500 (prime only; failure bars lien only vs. adversely affected owner). Direct contracts of $2,500 or less are exempt from Part I except § 713.05 (lien right kept; NTO/NOC etc. not required) per wave 3. Unlicensed contractors/subs have no lien (§ 713.02(7)). NOC required before first inspection for direct contracts > $5,000 (§ 713.135, as amended 2023).

Same 90 days. No residential-specific recording deadline.

How to file a mechanics lien in Florida, step by step

  1. Check the notice rules before you start. Look at the preliminary notice rows above for your role. Send any required notice early, by a method you can prove (like certified mail).
  2. Keep a job file from day one. Save the contract, change orders, invoices, delivery tickets, photos, and your first and last day of work. Most Florida deadlines count from one of those dates.
  3. Follow up on every unpaid invoice. Send friendly reminders, then firm ones. Most customers pay before it ever gets to a lien.
  4. Send a warning before you file. No pre-lien notice of intent for construction liens. Prime (contractor in privity) must deliver the contractor's final payment affidavit to the owner at least 5 days before instituting an action to enforce the lien; a contractor in default of this has no lien or right of action against the owner. Statute text sets no 90-day deadline for the affidavit; it must simply precede suit by 5 days (and sui
  5. File the lien on time and serve the owner. Prime: 90 days after your last day of work or materials. Subs and suppliers: 90 days after your last day of work or materials. Then serve the owner as the table explains.
  6. Enforce it or release it. Sue within 1 year after the lien is filed. If you get paid, release the lien right away.

Example: A subcontractor's last day of work on a Florida job was Monday, March 2, 2026. With a 90-day deadline from the last day of work, count 90 days forward: the lien must be filed by Sunday, May 31, 2026. Don't wait for the last day. Set a reminder a few weeks earlier, and check whether a notice of completion or other rule in the table above changes your clock.

Watch: how to send a notice of intent to lien (3 minutes)

Florida prompt payment act: how fast you must be paid

A prompt payment act sets how fast you must be paid. Before a lien, it is your first tool when a pay app is late. Here are the Florida rules.

RulePrivate jobsPublic jobs
Owner pays the primePer contract; final pay 14 days after doneState: 30 days after OK; local: 25 days
Prime pays the subPer contract; or 30 days after prime is paid30 days after work or 10 days after prime is paid
Late interestContract rate or state CFO rate if higher2% per month

Law: private: Fla. Stat. 715.12; 713.346(2); public: Fla. Stat. 215.44; 218.735; 255.073; 255.076; 337.141. Our plain-English summary of the ASA and Kegler Brown 2024 prompt pay chart. Check the statute before you rely on it.

See every state side by side in our prompt payment act rules by state.

Before you file a lien in Florida: try to get paid first

A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:

Florida lien laws and forms: read the statute

Tools and related guides

Official law and forms: Many states print the lien form or notice wording right in the law. Read the Florida lien law and use the state form if it has one.

Frequently asked questions

What is the deadline to file a mechanics lien in Florida?

Prime contractors: Record claim of lien not later than 90 days after the lienor's final furnishing; if the contract is terminated/contractor defaults (§ 713.07(4)), not later than 90 days after termination or final furnishing, whichever occurs first. Subcontractors and suppliers: Same as prime: 90 days after that lienor's own final furnishing (earlier of termination date + 90 if contract terminated).

How do I file a mechanics lien in Florida?

Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 90 days after your last day of work or materials. Subcontractors and suppliers: 90 days after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.

Do subcontractors need to send a preliminary notice in Florida?

All lienors not in privity with the owner, except laborers, must serve a Notice to Owner before commencing or not later than 45 days after commencing to furnish, and before the owner's final payment after the contractor's final payment affidavit. Sub-subs and suppliers to subs also serve a copy on the contractor; a supplier to a sub-sub serves the subcontractor too. Failure is a complete defense to the lien.

Do I need to send a notice of intent to lien in Florida?

No pre-lien notice of intent for construction liens. Prime (contractor in privity) must deliver the contractor's final payment affidavit to the owner at least 5 days before instituting an action to enforce the lien; a contractor in default of this has no lien or right of action against the owner. Statute text sets no 90-day deadline for the affidavit; it must simply precede suit by 5 days (and suit must be within the 1-year lien life).

Are there special lien rules for homes in Florida?

§ 713.015 disclosure for 1-4 family direct contracts > $2,500 (prime only; failure bars lien only vs. adversely affected owner). Direct contracts of $2,500 or less are exempt from Part I except § 713.05 (lien right kept; NTO/NOC etc. not required) per wave 3. Unlicensed contractors/subs have no lien (§ 713.02(7)). NOC required before first inspection for direct contracts > $5,000 (§ 713.135, as amended 2023).

How long do I have to enforce a mechanics lien in Florida?

Suit within 1 year after recording the claim of lien (or 1 year after recording an amended claim showing a later final furnishing date). Shortened to 60 days after service of Notice of Contest, or 20 days after service of order-to-show-cause summons. Lis pendens needed for the lien to bind creditors/subsequent purchasers without notice.

Does Florida have a prompt payment act?

On private jobs: owner pays the prime: per contract; final pay 14 days after done; prime pays the sub: per contract; or 30 days after prime is paid. On public jobs: owner pays the prime: state: 30 days after OK; local: 25 days; prime pays the sub: 30 days after work or 10 days after prime is paid. Check the statute for exceptions.

Mechanics lien deadlines in nearby states

See mechanics lien deadlines for all 50 states

Get paid before it gets to a lien.

AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.

Book a demo

Sam Frenzley
About the authorSam Frenzley

Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.

You did the work. Let AI chase the money.

AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.

  • Keep QuickBooks
  • Start with one invoice
  • Stay in control