District of Columbia mechanics lien laws: deadlines for primes, subs and suppliers, notice rules, home rules and how to file. Free deadline calculator.
District of Columbia mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the District of Columbia mechanics lien deadlines in plain English, with the law behind each rule.

Quick answer: District of Columbia mechanics lien deadlines
Record during construction or within 90 days after earlier of completion or termination (§ 40-301.02).
Last updated: November 23, 2026
This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the District of Columbia statute (D.C. Code §§ 40-301.01 to 40-303.20a) in November 2026. Read the current law or ask a District of Columbia construction attorney before you file.
"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.
| Rule | What District of Columbia requires | Law |
|---|---|---|
| Preliminary notice: prime contractor | None. | D.C. Code 40-301.02 |
| Preliminary notice: subcontractor | None required. OPTIONAL protective notice: a sub or supplier may send the owner written notice of the amount due while the owner still owes the GC. That notice is prima facie evidence against the owner's good faith in paying the GC later. | D.C. Code 40-303.02(b) (wave 2 statute read) |
| Preliminary notice: supplier | None required; the same optional 40-303.02(b) notice is available. | D.C. Code 40-303.01, 40-303.02 |
| Notice of intent to lien | The lien is perfected by RECORDING a notice of intent to hold a lien in the land records (Recorder of Deeds). There is no pre-lien notice. | D.C. Code 40-301.02(a)(1) |
| Lien filing deadline: prime contractor | Record during construction or within 90 days after the EARLIER of completion or termination of the PROJECT. This is project-level completion, not the claimant's own last work. If not recorded, the lien terminates when the 90 days expire. | D.C. Code 40-301.02(a)(1) |
| Lien filing deadline: subcontractor and supplier | Same 90 days from the earlier of project completion or termination. Only subs, suppliers and laborers contracting directly with the original contractor have lien rights. The sub lien is limited to the amount due or to become due to the original contractor. | D.C. Code 40-301.02(a)(1); 40-303.01; 40-303.02(a) |
| Residential projects | Same 90 days. On a home improvement contract, a copy of the contract must be attached to the notice. | D.C. Code 40-301.02(b) |
| Notice of completion: does it shorten the deadline? | None. DC has no notice of completion or commencement. | D.C. Code 40-301.01 et seq. |
| Serving the owner after you file | Within 5 business days after recording, mail a copy of the notice to the owner by certified mail, to the current address (or the last known address if none is in public records). If it is returned unclaimed or undelivered, post a copy on the property where it is generally visible from an entry point. | D.C. Code 40-301.02(a)(2) |
| Deadline to sue (enforce the lien) | File suit (under 40-303.08) within 180 days after the notice of intent is recorded, AND record a notice of pendency of action (42-1207(b)) within 10 days of filing suit. Missing either terminates the lien. | D.C. Code 40-303.13(a) |
Here is each deadline for prime contractors, subcontractors and suppliers on a commercial job. Homes have some different rules in District of Columbia. See the home rules below. "Prime" means you have a contract with the owner. Some deadlines change if the owner records a notice, so check the full rules below.
| Step | Prime contractor | Subcontractor | Supplier |
|---|---|---|---|
| Preliminary notice | Not required | Not required | Not required |
| Notice of intent to lien | Not required | Not required | Not required |
| File the lien | Within 90 days after the project is finished. | Within 90 days after the project is finished. | Within 90 days after the project is finished. |
| Serve a copy of the lien | Within 5 business days after the lien is recorded. | Within 5 business days after the lien is recorded. | Within 5 business days after the lien is recorded. |
| Sue to enforce the lien | Within 180 days after the lien is recorded. | Within 180 days after the lien is recorded. | Within 180 days after the lien is recorded. |
Get your exact District of Columbia dates
Enter your first and last day of work. Our free calculator shows the last day to send each notice, file your lien and sue.
Roofing, restoration and remodeling work on homes often has extra rules. In District of Columbia:
The notice is VOID unless it includes: the parties' names and addresses; the amount net of credits; work dates and material delivery dates; a legal description; for a DC entity, a current DC business license and a DLCP certificate of good standing issued within 180 days before filing; the home improvement contract, if any; and a notarized sworn statement. Home improvement: the owner's or occupant's proof of payment to the home improvement contractor voids any lien to the extent paid (47-2883.03). Subs effectively lose lien rights once the owner has paid.
Same 90 days. On a home improvement contract, a copy of the contract must be attached to the notice.
A prompt payment act sets how fast you must be paid. Before a lien, it is your first tool when a pay app is late. Here are the District of Columbia rules.
| Rule | Private jobs | Public jobs |
|---|---|---|
| Owner pays the prime | 7 days after contract pay date | 30 days after invoice |
| Prime pays the sub | 7 days after prime is paid | 7 days after prime is paid |
| Late interest | 1.5% per month | Rate set by mayor rule |
Law: private: D.C. Code 27-132 to 27-136; public: D.C. Code 2-221.01 to 2-221.06. Our plain-English summary of the ASA and Kegler Brown 2024 prompt pay chart. Check the statute before you rely on it.
See every state side by side in our prompt payment act rules by state.
A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:
Tools and related guides
Official law and forms: Many states print the lien form or notice wording right in the law. Read the District of Columbia lien law and use the state form if it has one.
Prime contractors: Record during construction or within 90 days after the EARLIER of completion or termination of the PROJECT. This is project-level completion, not the claimant's own last work. If not recorded, the lien terminates when the 90 days expire. Subcontractors and suppliers: Same 90 days from the earlier of project completion or termination. Only subs, suppliers and laborers contracting directly with the original contractor have lien rights. The sub lien is limited to the amount due or to become due to the original contractor.
Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 90 days after completion of the project. Subcontractors and suppliers: 90 days after completion of the project. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.
None required. OPTIONAL protective notice: a sub or supplier may send the owner written notice of the amount due while the owner still owes the GC. That notice is prima facie evidence against the owner's good faith in paying the GC later.
The lien is perfected by RECORDING a notice of intent to hold a lien in the land records (Recorder of Deeds). There is no pre-lien notice.
The notice is VOID unless it includes: the parties' names and addresses; the amount net of credits; work dates and material delivery dates; a legal description; for a DC entity, a current DC business license and a DLCP certificate of good standing issued within 180 days before filing; the home improvement contract, if any; and a notarized sworn statement. Home improvement: the owner's or occupant's proof of payment to the home improvement contractor voids any lien to the extent paid (47-2883.03). Subs effectively lose lien rights once the owner has paid.
File suit (under 40-303.08) within 180 days after the notice of intent is recorded, AND record a notice of pendency of action (42-1207(b)) within 10 days of filing suit. Missing either terminates the lien.
On private jobs: owner pays the prime: 7 days after contract pay date; prime pays the sub: 7 days after prime is paid. On public jobs: owner pays the prime: 30 days after invoice; prime pays the sub: 7 days after prime is paid. Check the statute for exceptions.
See mechanics lien deadlines for all 50 states
Get paid before it gets to a lien.
AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.
Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.
AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.