Delaware Mechanics Lien: Deadlines and How to File

Delaware mechanics lien laws in plain English: deadlines for primes, subs and suppliers, notice rules, home rules and how to file. Free deadline calculator.

Sam Frenzley
Founder, AR Workflow
13 min read

Delaware mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Delaware mechanics lien deadlines in plain English, with the law behind each rule.

Delaware mechanics lien deadlines and how to file

Quick answer: Delaware mechanics lien deadlines

Contractor with owner: 180 days after completion of the structure, and also deemed timely within 180 days of ANY of 9 alternative events (stated completion date, 90% paid, final invoice, certificate of occupancy, owner acceptance, architect's completion certificate, permanent financing, etc.). These expand the window; the app should default to the earliest known event because the claimant must plead and prove the event (§ 2711(a); Daystar Sills, Del. Super. 2007). Others: 120 days after their own last labor or delivery, or within 120 days of final payment (incl. retainage) being due to them, or of final payment to the prime they contracted with (§ 2711(b)). Statement of claim filed with the Superior Court Prothonotary.

Last updated: November 23, 2026

This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Delaware statute (Del. Code tit. 25, §§ 2701 et seq.) in November 2026. Read the current law or ask a Delaware construction attorney before you file.

Delaware lien law at a glance

"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.

RuleWhat Delaware requiresLaw
Preliminary notice: prime contractorNone. Separately, under § 2705, if the owner demands a list of everyone who furnished labor or material and the contractor or sub does not supply it within 10 days, it gets no further payments until it does and loses its ch. 27 lien rights.25 Del. C. § 2705
Preliminary notice: subcontractorNone. The § 2705 10-day claimant-list duty also binds subcontractors.25 Del. C. §§ 2705, 2711
Preliminary notice: supplierNone.25 Del. C. ch. 27
Notice of intent to lienNone. No presuit or pre-lien notice is required (ALFA/Morris James: 'No statute requires presuit notice').25 Del. C. §§ 2711-2716
Lien filing deadline: prime contractorA contractor in direct contract with the owner (including construction management services) files the statement of claim with the Superior Court Prothonotary in the county within 180 days after completion of the structure. Under § 2711(a)(2), the statement is ALSO 'deemed timely' if filed within 180 days of ANY of 9 events: (a) the contract's stated completion date; (b)-(c) the contract-set limitations start date for a phase or for the whole contract; (d) receipt of 90% of the contract price; (e) submission of the final invoice; (f) certificate of occupancy; (g) owner acceptance under the contract; (h) a completion certificate from the owner's architect, engineer or representative; (i) completion of permanent financing. These are alternatives that EXPAND the window (the latest qualifying event gives the most time). They are not an 'earliest controls' rule. The § 2712(b)(6) statement must name the completion date and the act or event relied on.25 Del. C. § 2711(a)(1)-(2); § 2712(b)(6)
Lien filing deadline: subcontractor and supplierAll other claimants (subs, sub-subs, suppliers) file within 120 days from completion of their labor or last delivery of their materials. The statement is also deemed timely within 120 days of either (1) the date final payment, including all retainage, is due to the claimant, or (2) the date final payment is made to the prime contractor that contracted with the owner and with whom the claimant has a contract.25 Del. C. § 2711(b), (b)(1)-(2)
Residential projectsThe deadlines are the same (180/120). For a structure used solely as the owner's residence, the substantive bar in § 2707 applies (see residential_rules).25 Del. C. §§ 2707, 2711
Notice of completion: does it shorten the deadline?There is no owner notice-of-completion mechanism. The listed § 2711(a)(2) events (CO, acceptance, architect certificate) can start an alternative 180-day window but never shorten the base deadline.25 Del. C. § 2711
Serving the owner after you fileThe claimant files the statement of claim, which may also serve as the complaint, with the Prothonotary. A writ of scire facias issues and is served like other such writs on the owner if found in the county. If the structure is occupied as a residence, a copy is left with a resident. If not, the sheriff affixes it to the door or front of the structure. The statute requires no claimant mailing.25 Del. C. §§ 2712(a), 2714, 2715
Deadline to sue (enforce the lien)There is no separate enforcement deadline. The statement of claim, labeled as a complaint, starts the scire facias action (§ 2712(a)). Default judgment is available unless the owner files an affidavit of defense (§ 2716). The judgment becomes a lien on the structure and ground that relates back to the start of work (§ 2718), and execution is by levari facias (§ 2719). Under the general statute, 10 Del. C. § 4711, the judgment lien lasts 10 years. It can be extended by written agreement filed with the Prothonotary (for a mechanic's-lien judgment, the terre-tenants must sign), or continued if a scire facias is pending at expiry.25 Del. C. §§ 2712(a), 2716, 2718, 2719; 10 Del. C. § 4711

Delaware lien deadlines by role

Here is each deadline for prime contractors, subcontractors and suppliers on a commercial job. Homes have some different rules in Delaware. See the home rules below. "Prime" means you have a contract with the owner. Some deadlines change if the owner records a notice, so check the full rules below.

StepPrime contractorSubcontractorSupplier
Preliminary noticeNot requiredNot requiredNot required
Notice of intent to lienNot requiredNot requiredNot required
File the lienWithin 180 days after the project is finished.Within 120 days after your last day of work or delivery.Within 120 days after your last day of work or delivery.
Serve a copy of the lienAfter the statement of claim is filed, a writ of scire facias issues and is served on the owner if found in the county.After the statement of claim is filed, a writ of scire facias issues and is served on the owner if found in the county.After the statement of claim is filed, a writ of scire facias issues and is served on the owner if found in the county.
Sue to enforce the lienNo separate enforcement deadline: the statement of claim, labeled as a complaint, starts the scire facias action.No separate enforcement deadline: the statement of claim, labeled as a complaint, starts the scire facias action.No separate enforcement deadline: the statement of claim, labeled as a complaint, starts the scire facias action.

Get your exact Delaware dates

Enter your first and last day of work. Our free calculator shows the last day to send each notice, file your lien and sue.

Open the Delaware lien calculator

Delaware mechanics lien rules for homes and homeowners

Roofing, restoration and remodeling work on homes often has extra rules. In Delaware:

For a structure used solely as the owner's residence, no lien arises if the owner has made full or final payment to the contractor in good faith. On or before final payment, the contractor must give either a notarized, verified certification that all labor and materials are paid, or a release of liens signed by all potential claimants. Failure to do so is grounds for suspending or revoking the contractor's licenses, and the owner may withhold final payment until it is provided. If the owner has not paid in full in good faith, liens are limited to the unpaid balance, paid pro rata among claimants who perfect liens. Payments made after service of process (§ 2715) are not in good faith.

The deadlines are the same (180/120). For a structure used solely as the owner's residence, the substantive bar in § 2707 applies (see residential_rules).

How to file a mechanics lien in Delaware, step by step

  1. Check the notice rules before you start. Look at the preliminary notice rows above for your role. Send any required notice early, by a method you can prove (like certified mail).
  2. Keep a job file from day one. Save the contract, change orders, invoices, delivery tickets, photos, and your first and last day of work. Most Delaware deadlines count from one of those dates.
  3. Follow up on every unpaid invoice. Send friendly reminders, then firm ones. Most customers pay before it ever gets to a lien.
  4. Send a warning before you file. None. No presuit or pre-lien notice is required (ALFA/Morris James: 'No statute requires presuit notice').
  5. File the lien on time and serve the owner. Prime: 180 days after completion of the project. Subs and suppliers: 120 days after your last day of work or materials. Then serve the owner as the table explains.
  6. Enforce it or release it. See the deadline to sue in the table. If you get paid, release the lien right away.

Example: A subcontractor's last day of work on a Delaware job was Monday, March 2, 2026. With a 120-day deadline from the last day of work, count 120 days forward: the lien must be filed by Tuesday, June 30, 2026. Don't wait for the last day. Set a reminder a few weeks earlier, and check whether a notice of completion or other rule in the table above changes your clock.

Watch: how to send a notice of intent to lien (3 minutes)

Delaware prompt payment act: how fast you must be paid

A prompt payment act sets how fast you must be paid. Before a lien, it is your first tool when a pay app is late. Here are the Delaware rules.

RulePrivate jobsPublic jobs
Owner pays the prime30 days after billing period or invoice21 days after work estimate is OK
Prime pays the sub30 days after prime is paid21 days after prime is paid
Late interestInterest; rate not setUp to prime rate plus 2%

Law: private: Del. Code tit. 6 sec. 3501 to 3509; public: Del. Code tit. 29 sec. 6516(f). Limits: Not 6 or fewer homes built at once; not own property. Our plain-English summary of the ASA and Kegler Brown 2024 prompt pay chart. Check the statute before you rely on it.

See every state side by side in our prompt payment act rules by state.

Before you file a lien in Delaware: try to get paid first

A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:

Delaware lien laws and forms: read the statute

Tools and related guides

Official law and forms: Many states print the lien form or notice wording right in the law. Read the Delaware lien law and use the state form if it has one.

Frequently asked questions

What is the deadline to file a mechanics lien in Delaware?

Prime contractors: A contractor in direct contract with the owner (including construction management services) files the statement of claim with the Superior Court Prothonotary in the county within 180 days after completion of the structure. Under § 2711(a)(2), the statement is ALSO 'deemed timely' if filed within 180 days of ANY of 9 events: (a) the contract's stated completion date; (b)-(c) the contract-set limitations start date for a phase or for the whole contract; (d) receipt of 90% of the contract price; (e) submission of the final invoice; (f) certificate of occupancy; (g) owner acceptance under the contract; (h) a completion certificate from the owner's architect, engineer or representative; (i) completion of permanent financing. These are alternatives that EXPAND the window (the latest qualifying event gives the most time). They are not an 'earliest controls' rule. The § 2712(b)(6) statement must name the completion date and the act or event relied on. Subcontractors and suppliers: All other claimants (subs, sub-subs, suppliers) file within 120 days from completion of their labor or last delivery of their materials. The statement is also deemed timely within 120 days of either (1) the date final payment, including all retainage, is due to the claimant, or (2) the date final payment is made to the prime contractor that contracted with the owner and with whom the claimant has a contract.

How do I file a mechanics lien in Delaware?

Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 180 days after completion of the project. Subcontractors and suppliers: 120 days after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.

Do subcontractors need to send a preliminary notice in Delaware?

None. The § 2705 10-day claimant-list duty also binds subcontractors.

Do I need to send a notice of intent to lien in Delaware?

None. No presuit or pre-lien notice is required (ALFA/Morris James: 'No statute requires presuit notice').

Are there special lien rules for homes in Delaware?

For a structure used solely as the owner's residence, no lien arises if the owner has made full or final payment to the contractor in good faith. On or before final payment, the contractor must give either a notarized, verified certification that all labor and materials are paid, or a release of liens signed by all potential claimants. Failure to do so is grounds for suspending or revoking the contractor's licenses, and the owner may withhold final payment until it is provided. If the owner has not paid in full in good faith, liens are limited to the unpaid balance, paid pro rata among claimants who perfect liens. Payments made after service of process (§ 2715) are not in good faith.

How long do I have to enforce a mechanics lien in Delaware?

There is no separate enforcement deadline. The statement of claim, labeled as a complaint, starts the scire facias action (§ 2712(a)). Default judgment is available unless the owner files an affidavit of defense (§ 2716). The judgment becomes a lien on the structure and ground that relates back to the start of work (§ 2718), and execution is by levari facias (§ 2719). Under the general statute, 10 Del. C. § 4711, the judgment lien lasts 10 years. It can be extended by written agreement filed with the Prothonotary (for a mechanic's-lien judgment, the terre-tenants must sign), or continued if a scire facias is pending at expiry.

Does Delaware have a prompt payment act?

On private jobs: owner pays the prime: 30 days after billing period or invoice; prime pays the sub: 30 days after prime is paid. On public jobs: owner pays the prime: 21 days after work estimate is OK; prime pays the sub: 21 days after prime is paid. Check the statute for exceptions.

Mechanics lien deadlines in nearby states

See mechanics lien deadlines for all 50 states

Get paid before it gets to a lien.

AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.

Book a demo

Sam Frenzley
About the authorSam Frenzley

Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.

You did the work. Let AI chase the money.

AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.

  • Keep QuickBooks
  • Start with one invoice
  • Stay in control