Vermont mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Vermont mechanics lien deadlines in plain English, with the law behind each rule.

Vermont mechanics lien deadlines and how to file

Quick answer: Vermont mechanics lien deadlines

Memorandum recorded with town clerk within 180 days after payment became due for last labor/materials (§ 1921(c)).

Last updated: November 23, 2026

This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Vermont statute (9 V.S.A. §§ 1921–1928) in November 2026. Read the current law or ask a Vermont construction attorney before you file.

Vermont lien law at a glance

"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.

RuleWhat Vermont requiresLaw
Preliminary notice: prime contractorNone. A party contracting with the owner has a lien without notice.9 V.S.A. § 1921(a)
Preliminary notice: subcontractorRequired. A claimant hired by the owner's agent, contractor or sub gets a lien only by giving written notice to the owner, or the owner's agent in charge of the property, that it will claim a lien. The notice must state the payment due date, if known. No statutory deadline. The lien reaches only the contract price still unpaid when the owner receives the notice. Send it early. It must be sent before the lien memorandum is recorded.9 V.S.A. § 1921(b)
Preliminary notice: supplierSame as subs: § 1921(b) applies to anyone who 'performs labor or furnishes materials' under a contract with the owner's agent, contractor or sub.9 V.S.A. § 1921(b)
Notice of intent to lienNo separate notice of intent. The § 1921(b) owner notice is the only pre-lien notice.9 V.S.A. §§ 1921-1928
Lien filing deadline: prime contractorRecord a signed written memorandum in the town clerk's office (land records) within 180 days from when payment became due for the claimant's OWN last labor or materials.9 V.S.A. §§ 1921(c), 1923
Lien filing deadline: subcontractor and supplierSame: 180 days from the claimant's own payment due date for its last labor or materials. The trigger question is resolved in resolved_open_questions.9 V.S.A. § 1921(c)
Residential projectsSame. There is no residential deadline. The subchapter applies to homestead property.9 V.S.A. § 1927
Notice of completion: does it shorten the deadline?The chapter has no notice of completion or commencement, and no owner demand to sue.9 V.S.A. §§ 1921-1928
Serving the owner after you fileIndirect claimants give the § 1921(b) written owner notice before recording. No statute requires service of the recorded memorandum. After the notice, an owner who conveys or mortgages the property must disclose the claim or face damages (§ 1922).9 V.S.A. §§ 1921(b), 1922
Deadline to sue (enforce the lien)Start suit and obtain an attachment within 180 days after recording the memorandum. If payment was not yet due at recording, the 180 days run from the date it becomes due. Record a certified copy of the judgment with the town clerk within 5 months after judgment.9 V.S.A. §§ 1924, 1925

Vermont lien deadlines by role

Here is each deadline for prime contractors, subcontractors and suppliers on a commercial job. "Prime" means you have a contract with the owner. Some deadlines change if the owner records a notice, so check the full rules below.

StepPrime contractorSubcontractorSupplier
Preliminary noticeNot requiredGive written notice to the owner (or the owner's agent in charge) that a lien will be claimed, stating the payment due date if known.Give written notice to the owner (or the owner's agent in charge) that a lien will be claimed, stating the payment due date if known.
Notice of intent to lienNot requiredNot requiredNot required
File the lienWithin 180 days after payment was due.Within 180 days after payment was due.Within 180 days after payment was due.
Serve a copy of the lienNot requiredNot requiredNot required
Sue to enforce the lienWithin 180 days after the lien is recorded.Within 180 days after the lien is recorded.Within 180 days after the lien is recorded.

Get your exact Vermont dates

Enter your first and last day of work. Our free calculator shows the last day to send each notice, file your lien and sue.

Open the Vermont lien calculator

Vermont mechanics lien rules for homes and homeowners

Roofing, restoration and remodeling work on homes often has extra rules. In Vermont:

No residential track. The lien applies to homestead property (§ 1927). Advance lien waivers are unenforceable (§ 1921(f)). Residential contractor registration (26 V.S.A. ch. 106) was not verified for its effect on liens.

Same. There is no residential deadline. The subchapter applies to homestead property.

How to file a mechanics lien in Vermont, step by step

  1. Check the notice rules before you start. Look at the preliminary notice rows above for your role. Send any required notice early, by a method you can prove (like certified mail).
  2. Keep a job file from day one. Save the contract, change orders, invoices, delivery tickets, photos, and your first and last day of work. Most Vermont deadlines count from one of those dates.
  3. Follow up on every unpaid invoice. Send friendly reminders, then firm ones. Most customers pay before it ever gets to a lien.
  4. Send a warning before you file. No separate notice of intent. The § 1921(b) owner notice is the only pre-lien notice.
  5. File the lien on time and serve the owner. Prime: 180 days after the date payment was due. Subs and suppliers: 180 days after the date payment was due. Then serve the owner as the table explains.
  6. Enforce it or release it. Sue within 180 days after the lien is filed. If you get paid, release the lien right away.

Watch: how to send a notice of intent to lien (3 minutes)

Vermont prompt payment act: how fast you must be paid

A prompt payment act sets how fast you must be paid. Before a lien, it is your first tool when a pay app is late. Here are the Vermont rules.

RulePrivate jobsPublic jobs
Owner pays the prime20 days after billing period or invoice20 days after billing period or invoice
Prime pays the sub7 days after prime is paid7 days after prime is paid
Late interest12% per year12% per year

Law: private: Vt. Stat. tit. 9 sec. 4001 to 4009; public: Vt. Stat. tit. 9 sec. 4001 to 4009. Our plain-English summary of the ASA and Kegler Brown 2024 prompt pay chart. Check the statute before you rely on it.

See every state side by side in our prompt payment act rules by state.

Before you file a lien in Vermont: try to get paid first

A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:

Vermont lien laws and forms: read the statute

Tools and related guides

Official law and forms: Many states print the lien form or notice wording right in the law. Read the Vermont lien law and use the state form if it has one.

Frequently asked questions

What is the deadline to file a mechanics lien in Vermont?

Prime contractors: Record a signed written memorandum in the town clerk's office (land records) within 180 days from when payment became due for the claimant's OWN last labor or materials. Subcontractors and suppliers: Same: 180 days from the claimant's own payment due date for its last labor or materials. The trigger question is resolved in resolved_open_questions.

How do I file a mechanics lien in Vermont?

Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 180 days after the date payment was due. Subcontractors and suppliers: 180 days after the date payment was due. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.

Do subcontractors need to send a preliminary notice in Vermont?

Required. A claimant hired by the owner's agent, contractor or sub gets a lien only by giving written notice to the owner, or the owner's agent in charge of the property, that it will claim a lien. The notice must state the payment due date, if known. No statutory deadline. The lien reaches only the contract price still unpaid when the owner receives the notice. Send it early. It must be sent before the lien memorandum is recorded.

Do I need to send a notice of intent to lien in Vermont?

No separate notice of intent. The § 1921(b) owner notice is the only pre-lien notice.

Are there special lien rules for homes in Vermont?

No residential track. The lien applies to homestead property (§ 1927). Advance lien waivers are unenforceable (§ 1921(f)). Residential contractor registration (26 V.S.A. ch. 106) was not verified for its effect on liens.

How long do I have to enforce a mechanics lien in Vermont?

Start suit and obtain an attachment within 180 days after recording the memorandum. If payment was not yet due at recording, the 180 days run from the date it becomes due. Record a certified copy of the judgment with the town clerk within 5 months after judgment.

Does Vermont have a prompt payment act?

On private jobs: owner pays the prime: 20 days after billing period or invoice; prime pays the sub: 7 days after prime is paid. On public jobs: owner pays the prime: 20 days after billing period or invoice; prime pays the sub: 7 days after prime is paid. Check the statute for exceptions.

Mechanics lien deadlines in nearby states

See mechanics lien deadlines for all 50 states

Get paid before it gets to a lien.

AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.

Book a demo

Sam Frenzley
About the authorSam Frenzley

Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.

You did the work. Let AI chase the money.

AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.

  • Keep QuickBooks
  • Start with one invoice
  • Stay in control