Rhode Island mechanics lien laws: deadlines for primes, subs and suppliers, notice rules, home rules and how to file. Free deadline calculator.
Rhode Island mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Rhode Island mechanics lien deadlines in plain English, with the law behind each rule.

Quick answer: Rhode Island mechanics lien deadlines
Look-back window: the lien is perfected only for work and materials furnished during the 200 days before filing. Earlier work is lost, except unpaid retainage (J.D. Cement Works, 2010, per ALFA). Engineering rule: (a) the hard outer deadline is 200 days after last furnishing; (b) for full coverage, the deadline is 200 days after the earliest unpaid, non-retainage furnishing. The day of filing counts as day 0: Element5 (2024) counted 200 days back from a Feb 9, 2024 filing to Jul 24, 2023 inclusive. (R.I. Gen. Laws 34-28-4(a))
Last updated: November 23, 2026
This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Rhode Island statute (R.I. Gen. Laws §§ 34-28-1 to -37) in November 2026. Read the current law or ask a Rhode Island construction attorney before you file.
"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.
| Rule | What Rhode Island requires | Law |
|---|---|---|
| Preliminary notice: prime contractor | Anyone contracting directly with the owner, lessee or tenant (material suppliers excepted) must give a 'Notice of Possible Mechanic's Lien' at any time before commencing work or delivering materials. The notice is either incorporated conspicuously in the written contract or sent by certified mail RRR. If not given, that contractor has no lien and must indemnify the owner against lower-tier liens (unless the owner has not paid it). | R.I. Gen. Laws 34-28-4.1 |
| Preliminary notice: subcontractor | None. A prime's failure to give notice does not affect others' lien rights. | R.I. Gen. Laws 34-28-4.1 |
| Preliminary notice: supplier | None. Material suppliers are excluded even when contracting directly with the owner. | R.I. Gen. Laws 34-28-4.1 |
| Notice of intent to lien | The Notice of Intention is the lien. Mail it to the owner of record by prepaid registered or certified mail RRR AND file a copy in the land evidence records, before or within 200 days after the work or materials. If the mailed notice is returned undelivered, file it with the envelope within 30 days after its return, and in no event more than 200 days after mailing. | R.I. Gen. Laws 34-28-4(a) |
| Lien filing deadline: prime contractor | Look-back window: the lien is perfected only for work and materials furnished during the 200 days before filing. Earlier work is lost, except unpaid retainage (J.D. Cement Works, 2010, per ALFA). Engineering rule: (a) the hard outer deadline is 200 days after last furnishing; (b) for full coverage, the deadline is 200 days after the earliest unpaid, non-retainage furnishing. The day of filing counts as day 0: Element5 (2024) counted 200 days back from a Feb 9, 2024 filing to Jul 24, 2023 inclusive. | R.I. Gen. Laws 34-28-4(a) |
| Lien filing deadline: subcontractor and supplier | Same 200-day look-back. Architects and engineers: special 34-28-7 timing (later of 200 days or 10 days after visible commencement, per prior research; not re-fetched). | R.I. Gen. Laws 34-28-4(a), 34-28-7 |
| Residential projects | Same 200 days. There is no residential variant in ch. 34-28. | R.I. Gen. Laws ch. 34-28 |
| Notice of completion: does it shorten the deadline? | None. No commencement or completion notice shortens deadlines. The owner may discharge the lien by paying into court or substituting a bond (34-28-17) or by seeking summary discharge (34-28-17.1). | R.I. Gen. Laws ch. 34-28 |
| Serving the owner after you file | Registered or certified mail RRR to the owner of record at the last known residence or place of business, plus recording, both within the 200 days. If mail is returned: re-file with the envelope within 30 days of return and no more than 200 days after mailing. | R.I. Gen. Laws 34-28-4(a) |
| Deadline to sue (enforce the lien) | Within 40 days of recording the notice of intention, file BOTH a complaint in Superior Court and a notice of lis pendens. The complaint must be filed the same day as the lis pendens or within 7 days after it. If missed, the lien is void. | R.I. Gen. Laws 34-28-10(a) |
Here is each deadline for prime contractors, subcontractors and suppliers on a commercial job. Homes have some different rules in Rhode Island. See the home rules below. "Prime" means you have a contract with the owner. Some deadlines change if the owner records a notice, so check the full rules below.
| Step | Prime contractor | Subcontractor | Supplier |
|---|---|---|---|
| Preliminary notice | Before your first day of work or delivery. | Not required | Not required |
| Notice of intent to lien | Not required | Not required | Not required |
| File the lien | Within 200 days after your last day of work or delivery. | Within 200 days after your last day of work or delivery. | Within 200 days after your last day of work or delivery. |
| Serve a copy of the lien | Only in some cases: If the mailed notice comes back, file it with the envelope within 30 days. See details below. | Only in some cases: If the mailed notice comes back, file it with the envelope within 30 days. See details below. | Only in some cases: If the mailed notice comes back, file it with the envelope within 30 days. See details below. |
| Sue to enforce the lien | Within 40 days after the lien is recorded. | Within 40 days after the lien is recorded. | Within 40 days after the lien is recorded. |
Get your exact Rhode Island dates
Enter your first and last day of work. Our free calculator shows the last day to send each notice, file your lien and sue.
Roofing, restoration and remodeling work on homes often has extra rules. In Rhode Island:
(1) 5-65-3 (2014 text, subsec. (o)): work over $1,000 incl. labor and materials must have a written contract, which must include notice that the contractor and others may file a mechanic's lien on nonpayment. Subsec. (p): the contract must contain a notice of the right of rescission. (2) 5-65-27: an elderly consumer (defined by reference to 42-66-4.1) may cancel an in-home solicitation contract for contractor services within 3 days, except in emergencies. Notice of Cancellation form required; deposit refund within 20 days. (3) 34-28-4.1 Notice of Possible Mechanic's Lien before work applies to all owner-direct contracts, not only residential. (4) 5-65-18 lien-rights statement in contract (prior research).
Same 200 days. There is no residential variant in ch. 34-28.
Example: A subcontractor's last day of work on a Rhode Island job was Monday, March 2, 2026. With a 200-day deadline from the last day of work, count 200 days forward: the lien must be filed by Friday, September 18, 2026. Don't wait for the last day. Set a reminder a few weeks earlier, and check whether a notice of completion or other rule in the table above changes your clock.
A prompt payment act sets how fast you must be paid. Before a lien, it is your first tool when a pay app is late. Here are the Rhode Island rules. Rhode Island has no general prompt pay law for private jobs, so your contract sets the terms there.
| Rule | Private jobs | Public jobs |
|---|---|---|
| Owner pays the prime | No general law | 30 days after good invoice |
| Prime pays the sub | No general law | 10 days after prime is paid |
| Late interest | None stated | Prime rate (to prime only) |
Law: public: R.I. Gen. Laws 42-11.1-1 to 42-11.1-16. Our plain-English summary of the ASA and Kegler Brown 2024 prompt pay chart. Check the statute before you rely on it.
See every state side by side in our prompt payment act rules by state.
A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:
Tools and related guides
Official law and forms: Many states print the lien form or notice wording right in the law. Read the Rhode Island lien law and use the state form if it has one.
Prime contractors: Look-back window: the lien is perfected only for work and materials furnished during the 200 days before filing. Earlier work is lost, except unpaid retainage (J.D. Cement Works, 2010, per ALFA). Engineering rule: (a) the hard outer deadline is 200 days after last furnishing; (b) for full coverage, the deadline is 200 days after the earliest unpaid, non-retainage furnishing. The day of filing counts as day 0: Element5 (2024) counted 200 days back from a Feb 9, 2024 filing to Jul 24, 2023 inclusive. Subcontractors and suppliers: Same 200-day look-back. Architects and engineers: special 34-28-7 timing (later of 200 days or 10 days after visible commencement, per prior research; not re-fetched).
Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 200 days after your last day of work or materials. Subcontractors and suppliers: 200 days after your last day of work or materials. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.
None. A prime's failure to give notice does not affect others' lien rights.
The Notice of Intention is the lien. Mail it to the owner of record by prepaid registered or certified mail RRR AND file a copy in the land evidence records, before or within 200 days after the work or materials. If the mailed notice is returned undelivered, file it with the envelope within 30 days after its return, and in no event more than 200 days after mailing.
(1) 5-65-3 (2014 text, subsec. (o)): work over $1,000 incl. labor and materials must have a written contract, which must include notice that the contractor and others may file a mechanic's lien on nonpayment. Subsec. (p): the contract must contain a notice of the right of rescission. (2) 5-65-27: an elderly consumer (defined by reference to 42-66-4.1) may cancel an in-home solicitation contract for contractor services within 3 days, except in emergencies. Notice of Cancellation form required; deposit refund within 20 days. (3) 34-28-4.1 Notice of Possible Mechanic's Lien before work applies to all owner-direct contracts, not only residential. (4) 5-65-18 lien-rights statement in contract (prior research).
Within 40 days of recording the notice of intention, file BOTH a complaint in Superior Court and a notice of lis pendens. The complaint must be filed the same day as the lis pendens or within 7 days after it. If missed, the lien is void.
On private jobs: owner pays the prime: no general law; prime pays the sub: no general law. On public jobs: owner pays the prime: 30 days after good invoice; prime pays the sub: 10 days after prime is paid. Check the statute for exceptions.
See mechanics lien deadlines for all 50 states
Get paid before it gets to a lien.
AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.
Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.
AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.