AR Workflow Blog/Collections tips

Louisiana Mechanics Lien: Deadlines and How to File

Louisiana mechanics lien laws in plain English: deadlines for primes, subs and suppliers, notice rules, home rules and how to file. Free deadline calculator.

Sam Frenzley
Founder, AR Workflow
13 min read

Louisiana mechanics lien law gives contractors, subcontractors and suppliers a way to get paid when a customer won't pay for work on a property. But a lien only works if you send the right notices and file on time. Miss one step and you can lose the lien. This guide explains the Louisiana mechanics lien deadlines in plain English, with the law behind each rule.

Louisiana mechanics lien deadlines and how to file

Quick answer: Louisiana mechanics lien deadlines

No notice of contract filed: all claimants 60 days after substantial completion or abandonment (§ 9:4822(A)). Notice of contract filed: subs/suppliers 30 days after a recorded notice of termination, or 6 months after substantial completion if none; GC 60 days after notice of termination, or 7 months if none (§ 9:4822(B),(C)). From Acts 2019 No. 325, eff. 2020-01-01.

Last updated: November 23, 2026

This is not legal advice. Rules differ by state and change over time. We checked each rule below against the text of the Louisiana statute (La. R.S. 9:4801 et seq. (Private Works Act)) in November 2026. Read the current law or ask a Louisiana construction attorney before you file.

Louisiana lien law at a glance

"Prime contractor" means you have a contract directly with the property owner. "Subcontractor" or "supplier" means you were hired by the prime contractor or by another sub. These rules are for private projects. Public projects use bond claims instead of liens.

RuleWhat Louisiana requiresLaw
Preliminary notice: prime contractorNo preliminary notice. Notice of contract (signed by owner and contractor; property description, parties/addresses, price, payment terms, work description) must be filed before the contractor begins work. If contract price exceeds $100,000 and the NOC is not timely filed, the contractor has no privilege and cannot file a statement of claim or privilege. Residential: also the 9:4852 Notice of Lien Rights to the owner (see residential_rules) but failure does not affect lien rights.La. R.S. 9:4811(A),(D)
Preliminary notice: subcontractorNo general preliminary notice for subcontractors. Special notices: professional consultants not engaged by owner - notice to owner within 30 days after engagement (9:4804(A)); lessors of movables - notice to contractor (and owner if NOC filed), late notice limits claim to rent after notice (9:4804(B)); sub with no contract with the GC - 30 days' notice to GC before suing GC/surety (9:4804(D)).La. R.S. 9:4804(A),(B),(D)
Preliminary notice: supplierOnly if a notice of contract was timely filed: seller of movables to a SUBCONTRACTOR must notify BOTH owner and contractor of nonpayment no later than 75 days after the last day of the calendar month in which the movable was delivered (seller/sub names and addresses, description, unpaid balance), or has no claim/privilege for that price. Sellers to the GC or owner: no such notice.La. R.S. 9:4804(C)
Notice of intent to lienNo mandatory notice of intent. Optional residential notice of nonpayment (9:4822(D)): only for residential work with NO timely NOC, only for 4801(3)/(4) or 4802 claimants (not the GC); given to owner before the 60-day period expires and at least 10 days before filing; extends period to 70 days after notice of termination or substantial completion/abandonment.La. R.S. 9:4822(D)
Lien filing deadline: prime contractorNo NOC: 60 days after filing of notice of termination, or if none, 60 days after substantial completion or abandonment (and no privilege at all if price > $100k). NOC filed: 60 days after notice of termination, or if none, 7 months after substantial completion or abandonment.La. R.S. 9:4822(A),(C); 9:4811(D)
Lien filing deadline: subcontractor and supplierNo NOC: 60 days after notice of termination or, if none, after substantial completion/abandonment. NOC properly and timely filed: 30 days after filing of notice of termination, or if none, 6 months after substantial completion/abandonment; must also deliver a copy of the statement to the owner if the owner's address is in the NOC.La. R.S. 9:4822(A),(B)
Residential projectsResidential work (9:4810(8): single- or double-family residence, occupied or designed to be; owner occupancy not required), no timely NOC: 4801(3)/(4) and 4802 claimants get 70 days after notice of termination or substantial completion/abandonment if notice of nonpayment reached owner before day 60 and >= 10 days before filing. GC: 60 days. If a NOC was filed on a residential job, the NOC rules (30 days/6 months; 60 days/7 months) apply instead.La. R.S. 9:4822(D); 9:4810(8)
Notice of completion: does it shorten the deadline?Owner-filed notice of termination (complete property description; signed by owner/representative/successor; certifies substantial completion, abandonment by owner, GC default, or contract termination; conclusive if in good faith) starts: 30 days for 4802 claimants ONLY if a NOC was filed; 60 days for GC (NOC or not) and for everyone when no NOC was filed (70 for qualifying residential claimants). Without it, the outside periods run from substantial completion/abandonment: 60 days (no NOC), 6 months (subs, NOC), 7 months (GC, NOC). Partial notices for a specified area allowed. Owner must file within 10 days of GC's request once work is substantially complete/abandoned, or GC may obtain summary judgment with same effect.La. R.S. 9:4822(A)-(C),(E),(F),(G)
Serving the owner after you fileNOC filed: 4802 claimant must deliver copy of statement to owner (if address in NOC) within the 30-day/6-month period. Without NOC: no statutory delivery requirement to owner (residential claimants using 70-day rule must have given the nonpayment notice). Claim against contractor/surety preserved if a statement is delivered to the contractor within the filing period even if not filed (9:4823(B)). Sub-sub: 30 days' notice to GC before suing GC/surety (9:4804(D)).La. R.S. 9:4822(B); 9:4823(B); 9:4804(D)
Deadline to sue (enforce the lien)Suit against owner within 1 year after filing the statement of claim or privilege, or claim/privilege is extinguished (9:4823(A)(2)). Claim vs contractor/surety: suit within 1 year after expiration of the 9:4822 filing period (9:4823(B)). Separately, a notice of pendency of action (lis pendens) must be filed within 1 year after filing the statement, or the statement's effect as to third persons ceases and it can be cancelled (9:4833(E)).La. R.S. 9:4823(A)(2),(B); 9:4833(E)

Louisiana lien deadlines by role

Here is each deadline for prime contractors, subcontractors and suppliers on a commercial job. Homes have some different rules in Louisiana. See the home rules below. "Prime" means you have a contract with the owner. Some deadlines change if the owner records a notice, so check the full rules below.

StepPrime contractorSubcontractorSupplier
Preliminary noticeNot requiredOnly in some cases: Within 30 days after the contract is signed.Only in some cases: Send a notice of nonpayment to the owner and the contractor within 75 days after the end of the month you delivered.
Notice of intent to lienNot requiredNot requiredNot required
File the lienWithin 60 days after the project is substantially finished.Within 60 days after the project is substantially finished.Within 60 days after the project is substantially finished.
Serve a copy of the lienNot requiredOnly in some cases: Within the same filing period (30 days after NOT, or 6 months after substantial completion), deliver a copy of the statement to the owner.Only in some cases: Within the same filing period (30 days after NOT, or 6 months after substantial completion), deliver a copy of the statement to the owner.
Sue to enforce the lienWithin 1 year after you file the lien.Within 1 year after you file the lien.Within 1 year after you file the lien.

Get your exact Louisiana dates

Enter your first and last day of work. Our free calculator shows the last day to send each notice, file your lien and sue.

Open the Louisiana lien calculator

Louisiana mechanics lien rules for homes and homeowners

Roofing, restoration and remodeling work on homes often has extra rules. In Louisiana:

Two separate residential regimes: (1) Residential Truth in Construction Act, 9:4851-4855 - applies to residential home improvements on property occupied by the owner principally as a single-family dwelling; contractor must give owner the statutory Notice of Lien Rights for signature prior to or at contracting (9:4852(A)); not a condition of the contract (9:4852(B)); signed copy to owner and to potential lien claimants on request (9:4853); failure does NOT impair anyone's lien rights (9:4854); if liens are perfected and contractor failed to comply, owner has civil action for reasonable damages and attorney fees, unless contractor/sub bonds the lien under 9:4841 or reimburses owner with written acknowledgment (9:4855). (2) Private Works Act residential work (9:4810(8), single/double family, occupancy not required): 70-day extension under 9:4822(D).

Residential work (9:4810(8): single- or double-family residence, occupied or designed to be; owner occupancy not required), no timely NOC: 4801(3)/(4) and 4802 claimants get 70 days after notice of termination or substantial completion/abandonment if notice of nonpayment reached owner before day 60 and >= 10 days before filing. GC: 60 days. If a NOC was filed on a residential job, the NOC rules (30 days/6 months; 60 days/7 months) apply instead.

How to file a mechanics lien in Louisiana, step by step

  1. Check the notice rules before you start. Look at the preliminary notice rows above for your role. Send any required notice early, by a method you can prove (like certified mail).
  2. Keep a job file from day one. Save the contract, change orders, invoices, delivery tickets, photos, and your first and last day of work. Most Louisiana deadlines count from one of those dates.
  3. Follow up on every unpaid invoice. Send friendly reminders, then firm ones. Most customers pay before it ever gets to a lien.
  4. Send a warning before you file. No mandatory notice of intent. Optional residential notice of nonpayment (9:4822(D)): only for residential work with NO timely NOC, only for 4801(3)/(4) or 4802 claimants (not the GC); given to owner before the 60-day period expires and at least 10 days before filing; extends period to 70 days after notice of termination or substantial completion/abandonment.
  5. File the lien on time and serve the owner. Prime: 60 days after completion of the project. Subs and suppliers: 60 days after completion of the project. Then serve the owner as the table explains.
  6. Enforce it or release it. Sue within 1 year after the lien is filed. If you get paid, release the lien right away.

Watch: how to send a notice of intent to lien (3 minutes)

Louisiana prompt payment act: how fast you must be paid

A prompt payment act sets how fast you must be paid. Before a lien, it is your first tool when a pay app is late. Here are the Louisiana rules.

RulePrivate jobsPublic jobs
Owner pays the primeNo set deadline45 days after certified pay request
Prime pays the sub14 days after prime is paid14 days after prime is paid
Late interest0.5% per day penalty; 15% max0.5% per day; 15% max

Law: private: La. Rev. Stat. 9:2784; public: La. Rev. Stat. 9:2784; 38:2191. Our plain-English summary of the ASA and Kegler Brown 2024 prompt pay chart. Check the statute before you rely on it.

See every state side by side in our prompt payment act rules by state.

Before you file a lien in Louisiana: try to get paid first

A lien is a last resort. It costs time and money, and it can end the customer relationship. Most contractors get paid sooner with a clear follow-up plan:

Louisiana lien laws and forms: read the statute

Tools and related guides

Official law and forms: Many states print the lien form or notice wording right in the law. Read the Louisiana lien law and use the state form if it has one.

Frequently asked questions

What is the deadline to file a mechanics lien in Louisiana?

Prime contractors: No NOC: 60 days after filing of notice of termination, or if none, 60 days after substantial completion or abandonment (and no privilege at all if price > $100k). NOC filed: 60 days after notice of termination, or if none, 7 months after substantial completion or abandonment. Subcontractors and suppliers: No NOC: 60 days after notice of termination or, if none, after substantial completion/abandonment. NOC properly and timely filed: 30 days after filing of notice of termination, or if none, 6 months after substantial completion/abandonment; must also deliver a copy of the statement to the owner if the owner's address is in the NOC.

How do I file a mechanics lien in Louisiana?

Send any required notices first, then record your lien claim before the deadline and serve the owner. Prime contractors: 60 days after completion of the project. Subcontractors and suppliers: 60 days after completion of the project. Then sue to enforce it on time, or release it once you are paid. The step-by-step section above walks through each part.

Do subcontractors need to send a preliminary notice in Louisiana?

No general preliminary notice for subcontractors. Special notices: professional consultants not engaged by owner - notice to owner within 30 days after engagement (9:4804(A)); lessors of movables - notice to contractor (and owner if NOC filed), late notice limits claim to rent after notice (9:4804(B)); sub with no contract with the GC - 30 days' notice to GC before suing GC/surety (9:4804(D)).

Do I need to send a notice of intent to lien in Louisiana?

No mandatory notice of intent. Optional residential notice of nonpayment (9:4822(D)): only for residential work with NO timely NOC, only for 4801(3)/(4) or 4802 claimants (not the GC); given to owner before the 60-day period expires and at least 10 days before filing; extends period to 70 days after notice of termination or substantial completion/abandonment.

Are there special lien rules for homes in Louisiana?

Two separate residential regimes: (1) Residential Truth in Construction Act, 9:4851-4855 - applies to residential home improvements on property occupied by the owner principally as a single-family dwelling; contractor must give owner the statutory Notice of Lien Rights for signature prior to or at contracting (9:4852(A)); not a condition of the contract (9:4852(B)); signed copy to owner and to potential lien claimants on request (9:4853); failure does NOT impair anyone's lien rights (9:4854); if liens are perfected and contractor failed to comply, owner has civil action for reasonable damages and attorney fees, unless contractor/sub bonds the lien under 9:4841 or reimburses owner with written acknowledgment (9:4855). (2) Private Works Act residential work (9:4810(8), single/double family, occupancy not required): 70-day extension under 9:4822(D).

How long do I have to enforce a mechanics lien in Louisiana?

Suit against owner within 1 year after filing the statement of claim or privilege, or claim/privilege is extinguished (9:4823(A)(2)). Claim vs contractor/surety: suit within 1 year after expiration of the 9:4822 filing period (9:4823(B)). Separately, a notice of pendency of action (lis pendens) must be filed within 1 year after filing the statement, or the statement's effect as to third persons ceases and it can be cancelled (9:4833(E)).

Does Louisiana have a prompt payment act?

On private jobs: owner pays the prime: no set deadline; prime pays the sub: 14 days after prime is paid. On public jobs: owner pays the prime: 45 days after certified pay request; prime pays the sub: 14 days after prime is paid. Check the statute for exceptions.

Mechanics lien deadlines in nearby states

See mechanics lien deadlines for all 50 states

Get paid before it gets to a lien.

AR Workflow works with QuickBooks and follows up on every invoice for you, from the first friendly reminder to the final notice. Bring one overdue invoice to a demo and see what we would send, and when.

Book a demo

Sam Frenzley
About the authorSam Frenzley

Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.

You did the work. Let AI chase the money.

AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.

  • Keep QuickBooks
  • Start with one invoice
  • Stay in control