Change Order Template: Free Word and Excel Form

Free change order template for construction in Word and Excel. What to include on a change order form, a filled-in example, and how to price and bill it.

Sam Frenzley
Founder, AR Workflow
6 min read

A change order is how you get paid for extra work. Skip it, and the extra work turns into a fight at the end of the job. This guide gives you a free change order template in Word and Excel, shows a filled-in example, and explains how to price and bill a change order so it gets paid.

Free change order template for construction in Word and Excel

Quick answer: what is a change order?

Last updated: November 23, 2026

Free download: change order template (Word and Excel)

Fill in the blanks in Word, or use the Excel version that adds up labor, materials, markup and the new contract sum for you.

Download Word (.docx)Download Excel (.xlsx)

Not sure what to charge? Use our free markup and margin calculator.

What is a change order in construction?

A change order is a written change to your contract. The owner asks for more work, you find a problem behind a wall, or the design changes. The change order puts the new work, the new price and the new finish date in writing, and both sides sign it.

Without one, you are doing work on a handshake. When the final bill comes, the owner may not remember asking for it, or may remember a lower price. A signed change order ends that argument before it starts.

What to include on a change order form

How to write a change order

1Stop before you start. Do not do the extra work until the change order is signed. If it is an emergency, get approval by email or text, then send the form the same day.
2Describe the work in plain words. Say what you will do, where, and with what materials. Add photos if a hidden condition caused the change.
3Price every cost. List labor hours, materials, equipment, subs and fees. Then add your markup.
4Show the new contract total. The owner should see exactly how the job price changes.
5Add the time. Extra work takes extra days. Put the new finish date in writing.
6Get both signatures. Then add the change to your schedule of values and bill it on your next invoice or pay app.

Change order example

Here is a filled-in change order for a homeowner who asks for an extra exterior door. These are the same sample numbers in our Excel template.

LineAmount
Labor: 14 hours at $68$952.00
Materials: door, header, trim$1,140.00
Subcontractor: painter$320.00
Direct cost$2,412.00
Markup for overhead and profit: 20%$482.40
Price of this change order$2,894.40
Original contract sum$48,500.00
Earlier change orders$1,250.00
New contract sum$52,644.40
Days added2

How to price a change order

Start with your real cost, then add markup for overhead and profit. Many contractors use a higher markup on change orders than on the base bid, because small changes break up the work and take office time to price, track and bill. Check your contract first. Some contracts cap the markup you can charge on changes.

Watch the difference between markup and margin. A 20% markup is only a 16.7% margin. Use our markup and margin calculator to see what you really keep.

How to get a change order paid

Change orders are often the first thing to go unpaid, because they are billed late and nobody follows up. A few habits fix most of it:

Change order vs change directive

A change order is agreed and signed by both sides, with a set price and time. A construction change directive is used when the owner orders the work but you have not agreed on the price yet. You do the work, track your costs, and settle the price later. If you get a directive, keep daily records of hours and materials so you can prove your cost. On AIA contracts, the change order form is the AIA G701.

Frequently asked questions

What is a change order form?

A change order form is a document that changes the scope, price or schedule of a construction contract. It describes the new work, lists the cost, shows the new contract total and finish date, and is signed by both the owner and the contractor.

Who signs a change order?

The owner (or the GC, if you are a sub) and the contractor. On some commercial jobs, the architect signs too. Get every signature before the extra work starts.

Can I do extra work without a signed change order?

You can, but it is risky. If there is no signed change order, the owner may refuse to pay or argue about the price. In an emergency, get approval in writing by email or text, then send the change order the same day.

What markup should I put on a change order?

It depends on your overhead, your trade and your contract. Many contracts set a limit, so check yours first. Use a markup and margin calculator to make sure the price covers your overhead and leaves a profit.

Is there a free change order template in Word?

Yes. Download our free change order template above in Word (.docx) or Excel (.xlsx). The Excel version does the math for you.

How do I bill a change order?

Add the approved amount as a new line on your next invoice, or add it to your schedule of values and bill it on your next pay application. Attach the signed change order so the customer can approve it fast.

Tools and related guides

The change order is signed. Now get it paid.

AR Workflow works with QuickBooks and follows up on every invoice for you by email, text and voicemail. Bring one overdue invoice to a demo and see what we would send, and when.

Book a demo

AIA and G701 are trademarks of the American Institute of Architects. Our template is not an official AIA document. This article is general information, not legal advice.

Sam Frenzley
About the authorSam Frenzley

Sam owned and ran three restoration companies for more than 14 years and collected over $100 million in receivables. He built AR Workflow in 2020 to give contractors the collections system he wished he'd had.

You did the work. Let AI chase the money.

AI writes the emails, sends the texts, and leaves the voicemails. Your team handles the conversations that matter, and your cash keeps moving.

  • Keep QuickBooks
  • Start with one invoice
  • Stay in control